Typical assembly (not a tested listing)
3-Hour Fire Rated Steel Truss Roof/Ceiling — 2 layers Spray-applied fireproofing
Typical 3-hour fire-rated steel truss roof/ceiling assembly. Steel bar joists at 48" o.c. with R-30 fiberglass batt, 2 layers of Spray-applied fireproofing ceiling, 22 ga. steel deck. Illustrative example of typical construction — not a tested UL or GA listing. Use a listed design (UL Product iQ or GA-600) for construction documents.
Steel bar joists at 48" o.c. with R-30 fiberglass batt, 2 layers of Spray-applied fireproofing ceiling, 22 ga. steel deck
The rest of 3-Hour Fire Rated Steel Truss Roof/Ceiling — 2 layers Spr… is for members
You're reading the opening of 3-Hour Fire Rated Steel Truss Roof/Ceiling — 2 layers Spr…. Members see the complete text, every cross-reference and the tools on this page — free for 14 days, no card required.
- Layer-by-layer components with thicknesses
- Cross-section diagram
- Applicable code sections and test standard