DRIVEN PILES SECTION 605 194 f. Approve the driven test pile for load testing when requiring static load testing. The engineer may select 1 of the above requirements before authorizing performance of a load test, or if a load test is unsatisfactory.
inconclusive, or unsatisfactory in any way, the engineer will order another test pile driven for additional information within 2 working days after receipt of the p ost-driving report.
tests in accordance with the procedures specified in ASTM D1143. Upon completion, the engineer will review the load test records and make 1 or more of the requirements in Section 605.3.3.C.1. 605.3.4 Preparation and Driving of Production Piles.
piles. Prior to installation, repair or replace piles with damage incurred during shipping, handling, or storage. Piles with any of these defects will caus e rejection by the engineer:
test or production piles at any location until the engineer approves the schedule for that location. Do not depart from these schedules without the prior approval of the engineer.
proceeding outwards in both directions, or starting at the outside row and proceeding progressively across the group.
changes to the pile driving system, see Section 605.3.1.F.
allows the engineer to obtain essential measurements and data. The engineer will observe the progress of all pile driving work. The engineer will record a co mplete driving log for each pile driven. The driving log will list all data essential for the determination of correct bearing resistance.
maintain alignment of the pile during driving. Do not apply side pressure to move piles into the correct position for driving. DRIVEN PILES SECTION 605 195 4. Place the tip of each pile in the correct plan location before attaching the helmet. Ensure the heads of all piles are in a true plane and perpendicular to the longitudinal axis of the pile before attaching the helmet.
Secure the pile cushion within the helmet prior to attaching the helmet to the pile. Provide a new pile cushion for each pile. During the driving of a single pile, replace the pile cushion if the cushion is compressed more than 1/2 the original thickness or it begins to burn.
the test piles as established in Section 605.3.3.C, except as required for splicing the pile or replacement of the pile cushion.
driving for 3 consecutive inches. Immediately inform the engineer if blow counts exceed these limits at a tip elevation above the minimum tip elevation specified.
perpendicular to the length to remove damage or deformations detrimental to the performance of the pile driving system or to the integrity of the pile. Allow steel piles to cool before continuing.
or batter shown in the contract. The maximum allowable variation at the top of the pile is 3 - inches in any direction from the location shown in the contract.
engineer for review and approval. After completing the splice, drive the spliced pile to meet the driving criteria. If it becomes necessary to splice timber pi les, submit the method for splicing and driving to the engineer for written approval.
Provide the survey results to the engineer.
tolerance specified.
the damaged pile, if driving of additional piles can occur without detriment to the structure, and if approved by the engineer.
out of tolerance or added piles.
heaved more than 1/4 -inch to the nominal bearing resistance and at least to the original tip elevation, or as directed by the engineer. Remove any material forced up between the piles during driving to the correct elevation before placement of foundation concrete.
responses depending on the what the driving records show:
DRIVEN PILES SECTION 605 196 b. Re-strike selected production piles. Perform the production pile re -strikes in accordance with the requirements of Section 605.3.5.
accordance with the requirements of Section 605.3.3. 605.3.5 Pile Re -strike.
result of Section 605.3.3.C or of production piles as a result of Section 605.3.4.C when the contractor does not meet the driving criteria.
unless otherwise noted in the contract. If pile installation continues adjacent to a pile requiring a re-strike, the engineer reserves the right to delay the re - strike until at least 48 hours after the contractor completes all adjacent pile driving.
dynamically test production pile re -strikes.
driving.
during re -strike.
or pile cut -off at least 20 blows at full stroke.
instrumentation. Strike the pile 20 blows at the required stroke height.
perform additional re -strikes until the pile driving system operates properly through a complete continuous re -strike procedure in accordance with thisSe ction.
days, make 1 or more of the following decisions:
change for production piles re -strikes, based on satisfactory test pile re -strike results.
satisfactory.
engineer may order: DRIVEN PILES SECTION 605 197 i. An additional re -strike with a longer wait time; ii. additional driving until the driving criteria is met or the full length of pile is driven, in cases where the top of pile remains above existing grade; or iii. a driving splice, in cases where the top of pile reaches existing grade. 605.3.6 Additional Installation Requirements.
accordance with the contract. Dispose of cut -off material in accordance with Section 106.8.
remains, deepen the remaining hole or drill a new hole of adequate length.
of the superimposed structure:
ii. Install 2 layers of metal sheet covering of either 13 -gauge zinc or 20 -gauge copper a minimum of 4 -inches greater than the diameter of the pile on top of the treatment.
water from entering the pile until placement of grout or concrete. Remove dirt or water from holes or sleeves of pre -stressed concrete piles before grouting in bar reinforcement.
below finished grade or final stream bed elevation, upon satisfactory completion of test driving,
fasten the bars and ties together at all bar intersections, in accordance with the details shown in the contract.
the pile shell. Do not use interior bracing or spacers.
concrete placement.
DRIVEN PILES SECTION 605 198 a. Do not place concrete in steel shells until completion and acceptance of all driving within the same substructure unit. If it is not possible to follow this limitation, do not drive within the same substructure unit until the placed concrete reaches 50 percent of the 28 -day strength.
by the engineer.
entire casing to provide a permanent bond with all bar reinforcement embedded in the pile.
or dowels occupy only the upper section of the pile, do not place bar reinforcement in the pile casing or shell until the concrete reaches the elevation of th e lowest end of the bar reinforcement. At this point, set the bar reinforcement in the casing, and continue to place the concrete until reaching the cut -off elevation. Concrete must remain plastic throughout placement. When bar reinforcement caging or dowe ls occupy only the upper section of the pile, the contractor may place reinforcement before placing concrete if the contractor uses a tremie or similar piece of equipment that allows the contractor to deposit concrete in the portion of the pile below the b ottom elevation of the reinforcement.
28-day strength.
discoloration caused by construction.
605.4Method of Measurement.
Department will measure the quantity of:
production pile tested and for each production pile initial drive tested.
605.5Basis of Payment.
unit price per linear foot for each type of pile. Price and payment constitute full compensation for:
steel pipe piles;
DRIVEN PILES SECTION 605 199 6. pile splice and pile build -up materials.
contract unit price per linear foot for each type of pile installed. Payment is full compensation for:
of metal sheeting atop timber piles;
quantity of test piles under this section.
per each. Price and payment will constitute full compensation for all work associated with the set up and conducting the pile re -strikes, except for dynamic pile testing of re -strikes.
contract unit price per each. Payment is full compensation for:
required to perform dynamic pile testing during initial driving;
the contract unit price per each. Payment is full compensation for:
work required to perform dynamic pile testing during re -strikes or production pile driving;
ITEM DESCRIPTION UNIT 605000 PROVIDE TIMBER PILES - TREATED, 12" LF 605001 PROVIDE TIMBER PILES - TREATED, 14" LF 605002 PROVIDE TIMBER PILES - TREATED, 16" LF 605010 PROVIDE CAST -IN-PLACE CONCRETE PILES, 12" LF 605011 PROVIDE CAST -IN-PLACE CONCRETE PILES, 14" LF