B
HomeLibrariesCopilotSearchProjectsBookmarks
FeedbackHelp Desk
Libraries
Building Codes
Code LibraryIBC — BuildingIRC — ResidentialIFC — FireIPC — PlumbingIMC — MechanicalIFGC — Fuel GasIECC — EnergyNEC — ElectricalModel Codes
Specifications
CSI SpecificationsDOT SpecsTransit SpecsUSACE
Standards
TransportationRailroadFire SafetyAccessibilityStructural
Tools & References
DiagramsAssembliesProductsCalculatorsChecklistsPermits
PricingLog in
Finishes & Coatings (09000-12999)

108.12Termination of the Contractor's Responsibility

DE · 2025 Standard SpecificationsBook pages 94104View official source ↗

SUBCONTRACTING, NTP, PROGRESS SCHEDULES, SECTION 108 TIME EXTENSIONS; LIQUIDATED DAMAGES; TERMINATION 84 Termination of the contractor's responsibility for the work occurs upon final acceptance in accordance with Section 105.16, Partial Acceptance; Project Acceptance; Final Acceptance; and Project Closeout , except to the extent provided in Section 107.13 , Contractor’s Responsibility for the Work after Final Acceptance; No Waiver of Legal Rights .

MEASUREMENT AND PAYMENT SECTION 109

85 SECTION 109 — MEASUREMENT AND PAYMENT

109.1Measurement of Quantities.

A.Unless stated otherwise, weigh material measured by weight as follows:
1.Weigh each loaded truck or other approved hauling equipment and deduct the tare weight of

the truck or hauling equipment. Check the tare weight once daily, or as often as directed by the engineer. Make appropriate adjustments in the use of the tare weig ht as directed by the engineer. Computer generate all weight tickets. A Department Materials & Research inspector will sign weight tickets showing a net weight of each material load originating from a bituminous production plant and delivered to the projec t.

2.Use a scale platform capable of holding all trucks and other hauling equipment. Ensure that the

entire vehicle rests on the scale platform to weigh it as 1 unit.

3.The State Sealer of Weights and Measures will certify scales used to weigh loads for payment.
4.Materials measured by weight that are stockpiled after delivery and before being placed, will

not be paid by ticket. The volume will be measured by template, calculated, and converted to the items Unit of Measure. Unless a project specific conversion fact or is mutually agreed to by the Department and Contractor, the conversion factors listed at https://deldot.gov/Business/drc/index.shtml?dc=pavement govern.

B.The Department defines a station, when used as a definition or term of measurement, as 100

linear feet.

C.Unless otherwise specified, the engineer will make longitudinal measurements for area

computations horizontally. The engineer will make no deductions for fixtures having an area of 9 square feet or less such as manholes or utility poles. The engineer wi ll make measurements for area computations using the neat dimensions shown on the plans.

D.The engineer will measure structures according to neat lines shown in the contract.
E.The engineer will take linear foot measurements for items such as pipes, culverts, guardrails, and

underdrains parallel to the base or foundation the structures rest on.

F.The word "ton" for this specification means the United States unit of weight consisting of 2,000 -

pounds. Weigh material on scales approved by the State sealer of weights and measures. For materials shipped by rail, the engineer will accept the car weight information provided by the railroad. The engineer will not accept car weights for material that w ill pass through mixing plants. Ensure that each truck bears a plainly legible identification mark.

G.When requested by the contractor and approved by the engineer in writing, the contractor may

weigh material specified for measurement by the cubic yard in the contract. The engineer will convert the weights to volumes for payment purposes. The engineer will determine the factors for converting weight measurement to volume measurement. The engineer and the contractor must mutually agree to conversions before using them. If the engineer and the contractor cannot agree on the conversion factors, the enginee r will measure the material by volume in place.

H.The engineer will measure bituminous materials by the gallon.
I.The engineer will measure volumes at 60 degrees F or the engineer will correct the volume to 60

degrees F using ASTM D4311 for asphalt or ASTM D633 for tars. MEASUREMENT AND PAYMENT SECTION 109

86 J. When the contractor ships bituminous materials by truck or transport, the engineer may use net certified weights or volume, subject to correction for loss or foaming, for computing quantities.

K.The engineer will measure cement by the pound.
L.The engineer will measure timber by the actual MFBM incorporated into a structure.
M.The engineer will not measure lump sum items of work.
1.When a complete structure or structural unit is specified as the unit of measurement, the lump

sum for the structure will include all necessary fittings and accessories.

2.The bid proposal may contain breakout sheets for lump sum items. Fill in a unit price for each

line item on the breakout sheet. The Department will consider the lump sum bid for the respective pay items as the sum of the price items listed on the breakout sheet. Breakout sheets must be submitted with the bid documents or within 7 calendar days following the bid due date by the lowest apparent bidder.

N.When the contract specifies standard manufactured items identified by unit weight or section

dimensions, the Department will consider this identification as nominal weights or dimensions. Unless more stringently controlled by tolerances specified elsewhere in the contract, the Department will accept manufacturing tolerances established by the industries involved.

109.2Scope of Payment for Unit Prices; Payment of Subcontractors.

A.Receive and accept compensation provided in the contract as full payment for providing all

materials and for performing work under the contract and for accepting all risk, loss, damage, and expense of any kind arising out of the nature or performance of the work, subject to the provisions of Section 107.13 , Contractor’s Responsibility for the Work after Final Acceptance; No Waiver of Legal Rights .

B.If the basis of payment clause, for an item relating to a unit price in the contract, states that the

unit price is compensation for certain work or materials used to complete the work for that pay item, the Department will not measure or pay this same work or material under any other pay item appearing in the contract.

C.When requirements, responsibilities, and providing materials (collectively called “requirements”

in this section) are outlined in the details, notes on the plans, or in the paragraphs preceding the “Basis of Payment” paragraph in these specifications or special provisions, such requirements are included in the payment for the item. No separate payment will be made for the above - mentioned requirements even if those requirements are not expressly reiterated in the “Basis of Payment” section of the specific ation.

D.Within 30 days of receipt of payment from the Department, submit a form provided by the

Department stating that all subcontractors that provided labor or material at that stage of the project are paid in full except for funds withheld under the terms of the contract as required by Chapter 8, Title 17 of the Delaware Code, annotated revised 1974, and as amended.

109.3Compensation for Altered Quantities.

A.When the accepted quantities of work vary from the quantities in the bid proposal, the contractor

shall accept payment at the original contract unit prices for the accepted quantities of work performed. The Department will make no allowance for any incr eased costs, except as provided in MEASUREMENT AND PAYMENT SECTION 109

87 Sections 104.2 , Contract Changes, and 108.11 , Termination of the Contract for Convenience, or in any escalation clauses in accordance with the contract.

109.4Compensation for Changes.

A.General
1.If the Department changes the contract, as provided in Section 104.2, Contract Changes, and the

contractor provides timely notice in accordance with Section 104.3, Notification of Contract Changes, the engineer will determine the pricing method for the change following the sequence specified below in Sections 109.4.B through D.

2.Compensation for a change in accordance with Section 109.4 , Compensation for Changes,

constitutes full and complete compensation for performing the change.

3.The Department reserves the right to provide the materials for performing the changed work.

The contractor is not entitled to payment for the cost of these materials or mark ups on the value of these materials.

4.If the change includes a time extension for compensable delays as provided by Section 108.7,

Extensions of Contract Time, the Department will compensate the contractor for the costs associated with the time extension in accordance with Section 109.6 , Compensation for Delay .

5.The Department will not pay for non -allowable charges specified in Section 109.5 , Non -

Allowable Charges, or duplicate payments that may result from the application of Section 109.6, Compensation for Delay, or any other provisions of the contract.

B.Unit Prices

Before proceeding to another pricing method, the engineer will attempt to price and pay for the change using unit prices in the contractor’s proposal. The Department will pay for the change using unit prices when the change incorporates work that does not differ significantly from the work in the original bid.

C.Negotiated Prices
1.If the engineer and the contractor cannot agree on compensation for the change in accordance

with Section 109.4.B, Unit Prices, the engineer and the contractor will attempt to negotiate unit or lump sum prices for the changed work using 1 or more of the following methods:

a.Unit bid prices for similar pay items adjusted for increased or decreased costs.
b.Historical unit bid prices for similar work and quantities.
c.Unit prices determined by the Department.
d.Cost analysis of labor, material, equipment, and mark ups as allowed in Section 109.4.D , Force

Account .

2.Negotiated mark -ups for subcontractor work may not exceed that provided for in Section

109.4.D.14 , Subcontracting .

3.Within 7 calendar days of the Department's request, submit a written proposal that includes

pricing, cost justification, and a schedule for performing the changed work.

4.The Department will respond within 7 calendar days after receiving the contractor’s proposal.

MEASUREMENT AND PAYMENT SECTION 109

88 5. The Department and the contractor can mutually agree in writing to extend the 7 -day time limits.

D.Force Account.
1.If the engineer and contractor are unable to agree to a price for a change in accordance with

Sections 109.4.B , Unit Prices, or C, Negotiated Prices, the engineer may direct the contractor to perform all or part of the change using the force account pricing method. Obtain the engineer’s written approval before proceeding with force account work.

2.When the engineer directs the contractor to perform the change using the force account pricing

method, the Department will pay the contractor as specified in Sections 109.4.D.5. through 14.

3.Prior to starting work using the force account pricing method, the engineer will meet with the

contractor to determine and agree on the labor, equipment, and materials needed to perform the change.

4.The engineer will make the final determination concerning what labor, equipment, and

materials are needed to perform the change.

5.Follow the engineer’s direction when performing the change.
6.The Department will not pay for the change in excess of the agreed amount using the force

account pricing method if the engineer was not given an opportunity to review and approve the labor, equipment, and materials proposed by the contractor to perform the change and if the contractor did not follow the engineer’s direction when performing the change.

7.Labor.
a.The Department will compensate the contractor for labor at the actual rate of wage paid and

shown on the certified payroll for every hour that the labor and working supervision worked exclusively on the changed work.

b.The Department will pay for a foreman in charge of the changed work as direct labor and not

in the overhead markup.

c.The Department considers the cost of home office personnel, project executives, project

managers, superintendents, general foreman, clerical personnel, assistants, and all other management and supervisory personnel as compensated by the mark ups allowed by Section 109.4.D.12, Overhead.

d.Unless already included in the wage rates paid, the Department will also pay the actual labor -

related costs of health and welfare benefits, pension funds, or other benefits, provided those payments are required by a collective bargaining agreement or ot her employment contract generally applicable to the classes of labor employed to perform the change.

8.Bond, Insurance, and Tax
a.For bond premiums; property damage, liability, and workers compensation insurance

premiums; unemployment insurance contributions; and social security taxes, the Department will compensate the contractor for the actual incremental cost necessarily and di rectly resulting from the performance of the change.

b.Provide documentation, satisfactory to the Department, of the rate or rates paid for bonds,

insurance, and taxes. MEASUREMENT AND PAYMENT SECTION 109

89 9. Materials.

a.The Department will compensate the contractor for the cost of materials the contractor

provided and used for the changed work.

b.The material purchaser is the entity that purchased the material to perform the change. For

example, if the change requires fabrication of structural steel, the steel fabricator that purchased the steel to fabricate the structural steel for the change i s the material purchaser, not the contractor.

c.The cost of contractor -furnished materials is the cost to the purchaser, together with

transportation charges paid by the purchaser, except as the following apply:

i.If a cash or trade discount by the actual supplier of the material is offered or available to the

purchaser, credit that amount to the Department even if the purchaser did not take the discount. ii. For materials obtained from a supplier or source owned wholly or in part by the purchaser, the Department will pay the lowest of the following:

(1)The price of similar materials previously purchased from a supplier.
(2)The price of materials used by the purchaser on other Department projects.

iii. The Department will pay the current wholesale price for materials if it is lower than the contractor’s purchase price from its wholly or partially owned supplier.

d.If the purchaser procures materials by methods other than a direct purchase and direct billing

from the supplier, the engineer will pay the price paid to the supplier, plus the costs incurred in the handling the materials.

e.If the contractor uses materials to complete the change that were taken from the contractor’s

stock, submit an affidavit certifying that the materials came from the contractor’s stock, the quantity was used in the changed work, and the price and transpo rtation costs represent the contractor’s actual costs.

f.If the engineer determines that the cost of materials for the changed work is excessive or the

contractor fails to provide substantiation for material costs from the supplier, the Department will pay the lowest current wholesale price for the materials. The Department will pay for the required quantities delivered to the project site, less available cash or trade discounts offered by the actual supplier of the material.

10.Equipment.
a.General.
i.The Department will pay for each hour that the contractor uses an approved piece of

equipment to perform the changed work. ii. Use equipment that the engineer agrees is in good operating condition. iii. Describe the equipment used in detail to document it for payment. iv. Select equipment of suitable size and suitable capacity for the changed work.

v.The engineer will determine the suitability of the equipment.

MEASUREMENT AND PAYMENT SECTION 109

90 vi. In the event the contractor elects to use equipment of a higher rental or hourly ownership cost than is suitable for performing the work associated with the change, the Department will pay the rate applicable to the suitable equipment. vii. If there is a differential in the rate of pay of the operator of oversize or higher -rate equipment, the Department will pay the rate of an operator of the suitable equipment. viii. The Department will not pay for the use of small tools. Small tools are defined as tools or equipment with a daily ownership and operating cost or daily rental rate and operating cost of less than $5.00. The Department will not pay for owned equipmen t not listed in the Rental Rate Blue Book (Blue Book) published by EquipmentWatch that cost less than $1,500 when new. ix. The Department will pay for subcontractor -owned equipment as "Owned Equipment," as set forth below. The Department will pay for leased or rented equipment or equipment hired from a subcontractor as "Leased, Rented, or Hired Equipment," as set forth bel ow.

x.The Department will not pay standby time for equipment that operated for more than 8

hours in a day or 40 -hours in a week. xi. The Department will pay standby time for equipment that operated less than 8 -hours in a day or less than 40 -hours in a week. The Department will base standby time on the difference between the operating time on a normal working day and 8 hours per day or the difference between the operating time in a normal work week and 40 hours per week. xii. The Department will not pay for the time equipment is idle on a day that is not a normal working day.

b.Owned Equipment.
i.The Department will compensate the contractor for contractor -owned equipment at a rate

determined from the Blue Book. ii. Owned equipment is equipment and plant owned directly by the contractor or by entities that are divisions, affiliates, subsidiaries, or in any other way related to the contractor or its parent company. iii. Use the Blue Book in the following manner:

(1)Determine the hourly rate by dividing the monthly rate by 176. Do not use the weekly,

hourly, or daily rates.

(2)The Department will pay for the number of hours that the equipment or plant is used to

perform the changed work.

(3)The Department will not pay for more than 176 hours per calendar month.
(4)Use the current edition of the Blue Book to establish the rates. The applicable current

edition is the one that is current as of the first day of work performed on the change. That rate applies throughout the time it takes to perform the changed work.

(5)Make the area adjustment.
(6)Make the equipment life adjustment in accordance with the Blue Book rate adjustment

tables.

(7)Charge the same rate for equipment used on overtime as charged for regular hours.

MEASUREMENT AND PAYMENT SECTION 109

91 (8) Use the Blue Book operating rate for each hour the equipment or plant was in operation for the change. The Blue Book operating rate does not apply to idle time regardless of the cause.

(9)The Department will not compensate the contractor for equipment idle time unless the

equipment was held on the project site at the engineer’s written request.

(10)The Department compensates for idle time at 1/2 the rate established in (1) through (6)

above.

(11)Compensation for idle time will not exceed 8 -hours in a day and will not exceed 40 -hours in

a week.

(12)The rates established above include the cost of fuel, oil, lubrication, supplies, attachments,

repairs, overhaul, and maintenance of any kind, depreciation, storage, overhead, profits, insurance, incidentals, and all other costs.

(13)Do not include operator costs in the hourly equipment or plant rate.
(14)If the Blue Book does not have a rate for a piece of equipment, the engineer will establish a

rate determined by audit in accordance with Section 107.15 , Audits . iv. If owned equipment required for the changed work is not available at the project site, the Department will pay the move -in cost of transporting the equipment to the project site and the move -out cost of moving the equipment off the site in accordance w ith the following:

(1)Obtain the engineer’s approval of the equipment location before transporting the

equipment to the project site.

(2)If the contractor chooses to keep the equipment at the project site to perform work other

than the work associated with the change, the Department will not pay for the move -out costs.

(3)If the contractor chooses to return the equipment to a location other than the original

location, the Department will pay a move -out cost that does not exceed the move -in cost.

(4)Calculate the equipment transportation cost to and from the project site using the hourly

rates for labor and equipment determined in accordance with the labor and equipment provisions of this specification. The Department will not pay moving costs tha t exceed the costs of moving the equipment using an independent hauler instead of the contractor’s own forces.

(5)If the contractor uses an independent hauler to transport contractor -owned equipment, the

Department will pay the invoice price paid to the hauler and 50 percent of the hourly ownership costs as determined above in accordance with the Blue Book.

(6)Transportation costs include loading and unloading.
c.Rented Equipment
i.If the contractor does not own the required equipment, inform the engineer of the need to

rent the equipment and of the rental rate before mobilizing the equipment to the site and using it to perform the changed work. ii. The Department will compensate the contractor for the rented equipment by paying the rental rate for the time it is used to perform the changed work. MEASUREMENT AND PAYMENT SECTION 109

92 iii. The Department will compensate the contractor for the cost of moving the rented equipment on and off the project if the moves are necessary only because of the changed work. iv. For idle rental equipment that must remain on the site because of the engineer’s written directive, the Department will pay for the rented equipment at the rental rate established above for rented equipment, not to exceed 8 -hours in a day or 40 -hours in a week.

v.The Department will not pay for rented equipment costs in excess of the actual cost paid for

the rental. vi. Provide a copy of the paid receipt or canceled check for the rental expense incurred. vii. The Department will pay the operating costs of rented equipment used for the changed work based on the Blue Book operating costs for the same piece of equipment.

11.Daily Records
a.Use the Department's Daily Force Account form to document daily the labor, equipment, and

materials used to perform the changed work.

b.Complete the Daily Force Account form to provide a clear distinction between the changed

work and all other work.

c.Provide all information required by the Daily Force Account form, including:
i.The name, classification, date, daily hours, total hours, rate, and extension for each laborer

and foreman. ii. The designation, number, date, daily hours, total hours, rental rate, including a copy of the Blue Book pages used, and extension for each piece of equipment and associated attachments. iii. The quantities of materials, prices, and extensions. Substantiate material costs with copies of vendor's invoices. Submit vendor invoices with the Daily Force Account forms or, if not available that day, submit the invoices with subsequent Daily Force Account forms. Failure to submit vendor's invoices within 60 calendar days after the date of material delivery, or within 15 calendar days after completing the changed work, whichever occurs first, will result in the engineer establishing the material cos ts. The engineer will use the lowest current wholesale prices for similar materials, available in the quantities used for the changed work, delivered to the project, less any available discounts. iv. The cost of material transportation.

v.The cost of insurance premiums for property damage, liability, and workers compensation

insurances; unemployment insurance contributions; bonds; and social security taxes.

d.At the end of each workday:
i.The engineer will compare the records the engineer kept with the completed Daily Force

Account form the contractor submitted. ii. The engineer and the contractor will review and attempt to reconcile differences with the Daily Force Account form record. iii. After the engineer and the contractor agree on the content of the Daily Force Account form submitted at the end of the workday, both parties will sign the form. MEASUREMENT AND PAYMENT SECTION 109

93 e. The Department will use the completed and signed Daily Force Account form as the basis for determining the amount due the contractor. However, the Department may subsequently increase or decrease the compensation paid based on an audit of the contractor ’s records. Allow the Department access to force account compensation cost records for inspection or audit in accordance with Section 107.15 , Audits .

f.If the contractor fails to submit the Daily Force Account form daily or refuses to sign the Daily

Force Account form, the Department will use the engineer’s records for payment.

12.Overhead.
a.The Department defines overhead to include the following:
i.Home office expenses, including the salaries and expenses of executive officers, area or

regional managers, managers, supervisors, and engineering, estimating, administrative, and clerical personnel. Home office expenses are expenses incurred by the con tractor not charged directly to any one project. These expenses are identified as general and administrative expenses. ii. Field office expenses, including project executives, project managers, general superintendents, superintendents, assistants, and non -working foremen. Field office expenses are expenses incurred by the contractor on a specific project but not charged to a particular item of work. For example, the cost of a job site trailer is a field office expense, but the cost of a cubic yard of concrete used in a bridge footing is not because there is an item, or items, for the bridge work. iii. Cost of small tools, such as shovels, picks, axes, saws, bars, sledges, lanterns, jacks, cables, pails, wrenches, and the cost of other miscellaneous supplies and services. iv. Computers, copiers, and other office equipment.

b.The Department will compensate the contractor for overhead at 10 percent of the following:
i.Bare material costs calculated in accordance with Item 9 above, not including freight on

board (FOB) costs. ii. Direct labor costs calculated in accordance with Item 7 above. iii. Equipment costs calculated in accordance with Item 10 above. iv. The Department may pay for extraordinary overhead expenses, such as hiring of additional supervisory personnel or purchase of a specialty small tool the contractor has to purchase specifically for the changed work. The Department will only pay for extraord inary overhead expenses if the engineer agreed to the costs before the contractor incurred the costs.

13.Profit.
a.The Department will compensate the contractor for profit at five percent of the following:
i.Bare material costs calculated in accordance with Item 9 above, not including FOB.

ii. Direct labor costs calculated in accordance with Item 7 above.

14.Subcontracting.
a.For administration costs in connection with subcontract work, the Department will pay an

amount equal to 10 percent for subcontractor work up to $100,000 and five percent on work exceeding $100,000 determined in accordance with Items 7 through 13 above. MEASUREMENT AND PAYMENT SECTION 109

94 E. Acceleration.

1.The engineer may direct the contractor, in writing, to accelerate the work.
2.If the engineer directs the contractor to complete the work early or directs the contractor to

accelerate to mitigate excusable delays and accelerating the work will result in added costs, provide notice of a change in accordance with Section 104.3 , Notification of Contract Changes .

3.The contractor is not entitled to compensation for the acceleration unless the contractor has:
a.Provided notice in accordance with Section 104.3 , Notification of Contract Changes .
b.The engineer directed the acceleration in writing.
c.The engineer directed the contractor to complete the work in less than the contract time or to

mitigate an excusable delay instead of granting a time extension.

4.The engineer will compensate the contractor for directed acceleration in accordance with
5.If the Department uses the force account method to compensate the contractor for

acceleration, the Department will modify Section 109.4.D , Force Account, as follows:

a.If acceleration requires working overtime or additional shifts, the Department will pay for the

overtime shift premium and the health and welfare benefits, pension fund, or other benefits costs directly related to the overtime shift premium. The Departm ent will pay for benefits required by collective bargaining agreements or other employment contracts applicable to the classes of labor used for the changed work. The Department will also pay for workers compensation insurance premiums, unemployment insura nce contributions, and social security taxes.

b.The Department will not pay for additional supervision to oversee work during overtime hours

or during additional shifts. Compensation for this supervision is included in the allowable labor overhead markup.

c.The Department will pay for equipment used during overtime hours or on extended shifts at

the same rate used for regular time or normal shifts.

d.If the engineer requests the contractor to expedite material deliveries to accelerate the work,

the Department will pay the expediting costs.

F.Payments

Compensation for changed work paid, in accordance with Section 109.4, Compensation for Changes, is full and complete compensation for the changed work, except to the extent that the contractor is also entitled to compensation for an excusable and compensable time extension due to the changed work. The Department will determine the contractor’s entitl ement to a compensable time extension in accordance with Section 108.7 , Extensions of Contract Time . The Department will determine compensation for the time ext ension in accordance with Section 109.6 , Compensation for Delay .

109.5Non -Allowable Charges.

A.The Department will not pay for the following:
Source: Delaware Standard Specifications for Road and Bridge Construction, 2025 Edition. Pages 94104 of 779.