Boise, Idaho Building Permit Cost Calculator
Estimates permit cost in Boise from the city's own published fee schedule — not a national average. Every figure is computed from a rule quoted verbatim from that document, and rules that cannot be computed honestly are shown as the published text instead of a number.
217 jurisdictions with fee schedules on file
Total cost of work, labor and materials
Used by cities that price per square foot
Fences and retaining walls
Electrical permits priced by the ampere
Building Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
Total valuation $1.00 to $2,000.00 $26.37 for the first $500.00 plus $2.95 for each additional $100.00 or fraction thereof, to and including $2,000.00 | see rule |
Total valuation $2,001.00 to $25,000.00 $70.76 for the first $2,000.00 plus $12.71 for each additional $1,000.00 or fraction thereof, to and including $25,000.00 | see rule |
Total valuation $25,001.00 to $50,000.00 $362.80 for the first $25,000.00 plus $9.30 for each additional $1,000.00 or fraction thereof, to and including $50,000.00 | see rule |
Total valuation $50,001.00 to $100,000.00 $595.30 for the first $50,000.00 plus $6.35 for each additional $1,000.00 or fraction thereof, to and including $100,000.00 | see rule |
○Total valuation $100,001.00 and up $913.09 for the first $100,000.00, plus 150 x $5.17 for $150,000.00 over (rounded up per "or fraction thereof") = $1,688.59 | $1,688.59 |
○Reinspection fee Flat fee $55.00 | $55.00 |
○Energy code inspection fee Flat fee $55.00 | $55.00 |
○After hours inspection (two hour minimum) Flat fee $83.00 | $83.00 |
Residential plan review · add-on 20% of the building permit fee — select the permit fee line above to calculate | see rule |
○Certificate of occupancy only plan review and inspection Flat fee $175.00 | $175.00 |
○Residential solar photovoltaic permit Flat fee $165.00 | $165.00 |
○Appeal fee Flat fee $150.00 | $150.00 |
How this jurisdiction calculates the fee
Building permit fees are calculated from total project valuation using Table No. 1-A of the Boise City Building Code Fee Schedule dated October 2023, with residential plan review for one- and two-family dwellings, townhouses and their accessory structures added at 20% of the building permit fee. | 2026-09-14 (lane B run 1068): DOCUMENT DATE CORRECTED. The basis said "Fee Schedule dated October 2023"; the schedule actually in force is captioned Oct. 2021 on every page footer (cityofboise.org/media/8321/final-boise-city-building-code-fee-schedule-10-1-21.pdf, plumbing at media/8324/final-plumbing-code-fee-schedule-10-1-21.pdf). No 2023 revision exists. Both PDFs were downloaded and read in full this pass and every stored figure is confirmed verbatim. NOTE FOR FUTURE PASSES: cityofboise.org/departments/planning-and-development-services/fees/ is an Angular page whose fee list never renders to a non-browser client (the HTML contains only {{item.Title}} placeholders), so the schedule PDFs must be fetched by their media/ paths, not scraped from the fees page.
Source: published fee schedule · Verified 9/17/2026
Deck Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
Total valuation $1.00 to $2,000.00 $26.37 for the first $500.00 plus $2.95 for each additional $100.00 or fraction thereof, to and including $2,000.00 | see rule |
Total valuation $2,001.00 to $25,000.00 $70.76 for the first $2,000.00 plus $12.71 for each additional $1,000.00 or fraction thereof, to and including $25,000.00 | see rule |
Residential plan review · add-on 20% of the building permit fee — select the permit fee line above to calculate | see rule |
How this jurisdiction calculates the fee
Deck permit fees are calculated from total project valuation using Table No. 1-A of the Boise City Building Code Fee Schedule dated October 2023, with residential plan review added at 20% of the building permit fee. | 2026-09-14 (lane B run 1068): DOCUMENT DATE CORRECTED. The basis said "Fee Schedule dated October 2023"; the schedule actually in force is captioned Oct. 2021 on every page footer (cityofboise.org/media/8321/final-boise-city-building-code-fee-schedule-10-1-21.pdf, plumbing at media/8324/final-plumbing-code-fee-schedule-10-1-21.pdf). No 2023 revision exists. Both PDFs were downloaded and read in full this pass and every stored figure is confirmed verbatim. NOTE FOR FUTURE PASSES: cityofboise.org/departments/planning-and-development-services/fees/ is an Angular page whose fee list never renders to a non-browser client (the HTML contains only {{item.Title}} placeholders), so the schedule PDFs must be fetched by their media/ paths, not scraped from the fees page. 2026-09-17 (lane B run 1390, pipeline run 94): SOURCING GAP CLOSED. fee_source_url pointed at cityofboise.org/departments/planning-and-development-services/fees/, which is an Angular index that prints no dollar amounts at all (curl returns "{{doc.Title}}" placeholders). Rendered with headless Chromium, that index links the department's actual schedules, and they were downloaded and read in full today. Boise City Building Code Fee Schedule (10-1-23) prints the valuation ladder verbatim: "$1.00 to $2,000.00 - $26.37 for the first $500.00 plus $2.95 for each additional $100.00", "$2,001.00 to $25,000.00 - $70.76 for the first $2,000.00 plus $12.71 for each additional $1,000.00", and "Reinspection fee: $55". Boise City Plumbing Code Fee Schedule (10-1-21) Table B(3) prints "Water or waste re-piping $80", "Re-plumbing entire house or unit: $110", "Installation of single fixtures or appliances including bidets, bathtubs, showers, hot water heaters... $55", the $32 residential base permit fee and "Water heaters $12 Each". fee_source_url now points at the schedule that carries each row's figures. No figure changed; these remain the current schedules the city links.
Source: published fee schedule · Verified 11/9/2026
Electrical Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Single branch circuit, including electric hot water heaters, wall heaters, electric vehicle outlets, fans, single outlets, and air conditioner or heat pump condensers Flat fee $55.00 | $55.00 |
○More than one branch circuit installed or altered for an addition, alteration, repair or fixture replacement Flat fee $110.00 | $110.00 |
○Photovoltaic system Flat fee $110.00 | $110.00 |
○Radiant floor Flat fee $110.00 | $110.00 |
○Swimming pools Flat fee $165.00 | $165.00 |
○Hot tub or spa Flat fee $110.00 | $110.00 |
○Miscellaneous residential Flat fee $110.00 | $110.00 |
New dwelling up to 2,500 square feet $135 per dwelling unit | see rule |
○New dwelling 2,501 to 3,500 square feet Flat fee $155.00 | $155.00 |
○New dwelling 3,501 to 4,500 square feet Flat fee $175.00 | $175.00 |
New dwelling 4,501 square feet and above $210 per dwelling unit plus $65 for each additional 1,000 sq. ft. or portion thereof over 4,501 sq. ft. | see rule |
How this jurisdiction calculates the fee
Electrical permit fees are set by flat amounts in the Electrical Code Fee Schedule, which charges by scope of work for existing dwellings and by conditioned square footage for new dwellings.
Source: published fee schedule · Verified 9/18/2026
Fence Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
Total valuation $1.00 to $2,000.00 $26.37 for the first $500.00 plus $2.95 for each additional $100.00 or fraction thereof, to and including $2,000.00 | see rule |
Total valuation $2,001.00 to $25,000.00 $70.76 for the first $2,000.00 plus $12.71 for each additional $1,000.00 or fraction thereof, to and including $25,000.00 | see rule |
How this jurisdiction calculates the fee
Fence permit fees are calculated from total project valuation using Table No. 1-A of the Boise City Building Code Fee Schedule dated October 2023. | 2026-09-14 (lane B run 1068): DOCUMENT DATE CORRECTED. The basis said "Fee Schedule dated October 2023"; the schedule actually in force is captioned Oct. 2021 on every page footer (cityofboise.org/media/8321/final-boise-city-building-code-fee-schedule-10-1-21.pdf, plumbing at media/8324/final-plumbing-code-fee-schedule-10-1-21.pdf). No 2023 revision exists. Both PDFs were downloaded and read in full this pass and every stored figure is confirmed verbatim. NOTE FOR FUTURE PASSES: cityofboise.org/departments/planning-and-development-services/fees/ is an Angular page whose fee list never renders to a non-browser client (the HTML contains only {{item.Title}} placeholders), so the schedule PDFs must be fetched by their media/ paths, not scraped from the fees page. 2026-09-17 (lane B run 1390, pipeline run 94): SOURCING GAP CLOSED. fee_source_url pointed at cityofboise.org/departments/planning-and-development-services/fees/, which is an Angular index that prints no dollar amounts at all (curl returns "{{doc.Title}}" placeholders). Rendered with headless Chromium, that index links the department's actual schedules, and they were downloaded and read in full today. Boise City Building Code Fee Schedule (10-1-23) prints the valuation ladder verbatim: "$1.00 to $2,000.00 - $26.37 for the first $500.00 plus $2.95 for each additional $100.00", "$2,001.00 to $25,000.00 - $70.76 for the first $2,000.00 plus $12.71 for each additional $1,000.00", and "Reinspection fee: $55". Boise City Plumbing Code Fee Schedule (10-1-21) Table B(3) prints "Water or waste re-piping $80", "Re-plumbing entire house or unit: $110", "Installation of single fixtures or appliances including bidets, bathtubs, showers, hot water heaters... $55", the $32 residential base permit fee and "Water heaters $12 Each". fee_source_url now points at the schedule that carries each row's figures. No figure changed; these remain the current schedules the city links.
Source: published fee schedule · Verified 11/9/2026
Reroof Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
Total valuation $1.00 to $2,000.00 $26.37 for the first $500.00 plus $2.95 for each additional $100.00 or fraction thereof, to and including $2,000.00 | see rule |
Total valuation $2,001.00 to $25,000.00 $70.76 for the first $2,000.00 plus $12.71 for each additional $1,000.00 or fraction thereof, to and including $25,000.00 | see rule |
○Reinspection fee Flat fee $55.00 | $55.00 |
How this jurisdiction calculates the fee
Re-roofing permit fees are calculated from total project valuation using Table No. 1-A of the Boise City Building Code Fee Schedule dated October 2023. | 2026-09-14 (lane B run 1068): DOCUMENT DATE CORRECTED. The basis said "Fee Schedule dated October 2023"; the schedule actually in force is captioned Oct. 2021 on every page footer (cityofboise.org/media/8321/final-boise-city-building-code-fee-schedule-10-1-21.pdf, plumbing at media/8324/final-plumbing-code-fee-schedule-10-1-21.pdf). No 2023 revision exists. Both PDFs were downloaded and read in full this pass and every stored figure is confirmed verbatim. NOTE FOR FUTURE PASSES: cityofboise.org/departments/planning-and-development-services/fees/ is an Angular page whose fee list never renders to a non-browser client (the HTML contains only {{item.Title}} placeholders), so the schedule PDFs must be fetched by their media/ paths, not scraped from the fees page. 2026-09-17 (lane B run 1390, pipeline run 94): SOURCING GAP CLOSED. fee_source_url pointed at cityofboise.org/departments/planning-and-development-services/fees/, which is an Angular index that prints no dollar amounts at all (curl returns "{{doc.Title}}" placeholders). Rendered with headless Chromium, that index links the department's actual schedules, and they were downloaded and read in full today. Boise City Building Code Fee Schedule (10-1-23) prints the valuation ladder verbatim: "$1.00 to $2,000.00 - $26.37 for the first $500.00 plus $2.95 for each additional $100.00", "$2,001.00 to $25,000.00 - $70.76 for the first $2,000.00 plus $12.71 for each additional $1,000.00", and "Reinspection fee: $55". Boise City Plumbing Code Fee Schedule (10-1-21) Table B(3) prints "Water or waste re-piping $80", "Re-plumbing entire house or unit: $110", "Installation of single fixtures or appliances including bidets, bathtubs, showers, hot water heaters... $55", the $32 residential base permit fee and "Water heaters $12 Each". fee_source_url now points at the schedule that carries each row's figures. No figure changed; these remain the current schedules the city links.
Source: published fee schedule · Verified 11/9/2026
Retaining Wall Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
Total valuation $1.00 to $2,000.00 $26.37 for the first $500.00 plus $2.95 for each additional $100.00 or fraction thereof, to and including $2,000.00 | see rule |
Total valuation $2,001.00 to $25,000.00 $70.76 for the first $2,000.00 plus $12.71 for each additional $1,000.00 or fraction thereof, to and including $25,000.00 | see rule |
Total valuation $25,001.00 to $50,000.00 $362.80 for the first $25,000.00 plus $9.30 for each additional $1,000.00 or fraction thereof, to and including $50,000.00 | see rule |
How this jurisdiction calculates the fee
Retaining wall permit fees are calculated from total project valuation using Table No. 1-A of the Boise City Building Code Fee Schedule dated October 2023.
Source: published fee schedule · Verified 9/18/2026
Shed Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
Total valuation $1.00 to $2,000.00 $26.37 for the first $500.00 plus $2.95 for each additional $100.00 or fraction thereof, to and including $2,000.00 | see rule |
Total valuation $2,001.00 to $25,000.00 $70.76 for the first $2,000.00 plus $12.71 for each additional $1,000.00 or fraction thereof, to and including $25,000.00 | see rule |
Residential plan review · add-on 20% of the building permit fee — select the permit fee line above to calculate | see rule |
How this jurisdiction calculates the fee
Accessory structure permit fees are calculated from total project valuation using Table No. 1-A of the Boise City Building Code Fee Schedule dated October 2023, with residential plan review for accessory structures added at 20% of the building permit fee. | 2026-09-14 (lane B run 1068): DOCUMENT DATE CORRECTED. The basis said "Fee Schedule dated October 2023"; the schedule actually in force is captioned Oct. 2021 on every page footer (cityofboise.org/media/8321/final-boise-city-building-code-fee-schedule-10-1-21.pdf, plumbing at media/8324/final-plumbing-code-fee-schedule-10-1-21.pdf). No 2023 revision exists. Both PDFs were downloaded and read in full this pass and every stored figure is confirmed verbatim. NOTE FOR FUTURE PASSES: cityofboise.org/departments/planning-and-development-services/fees/ is an Angular page whose fee list never renders to a non-browser client (the HTML contains only {{item.Title}} placeholders), so the schedule PDFs must be fetched by their media/ paths, not scraped from the fees page. | 2026-10-20 (lane B run 2153): the cited PDF (media/17652, 10-1-23 file) now carries "Oct. 2023" footers, so a 2023 edition exists at this URL, contradicting the 2026-09-14 note that none exists. Stored Table 1-A figures ($26.37/$2.95, $70.76/$12.71, 20% plan review) all re-confirmed in it; no figure changed.
Source: published fee schedule · Verified 11/10/2026
Water Heater Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Installation of single fixtures or appliances including hot water heaters Flat fee $55.00 | $55.00 |
○Base permit fee under the per-fixture table Flat fee $32.00 | $32.00 |
○Water heaters, per-fixture charge Flat fee $12.00 | $12.00 |
○Water or waste re-piping Flat fee $80.00 | $80.00 |
○Re-plumbing entire house or unit Flat fee $110.00 | $110.00 |
How this jurisdiction calculates the fee
Water heater work is permitted under the Plumbing Code Fee Schedule dated October 2021, which charges either a flat single-fixture fee or a base permit fee plus a per-fixture charge depending on the table applied. | 2026-09-14 (lane B run 1068): DOCUMENT DATE CORRECTED. The basis said "Fee Schedule dated October 2023"; the schedule actually in force is captioned Oct. 2021 on every page footer (cityofboise.org/media/8321/final-boise-city-building-code-fee-schedule-10-1-21.pdf, plumbing at media/8324/final-plumbing-code-fee-schedule-10-1-21.pdf). No 2023 revision exists. Both PDFs were downloaded and read in full this pass and every stored figure is confirmed verbatim. NOTE FOR FUTURE PASSES: cityofboise.org/departments/planning-and-development-services/fees/ is an Angular page whose fee list never renders to a non-browser client (the HTML contains only {{item.Title}} placeholders), so the schedule PDFs must be fetched by their media/ paths, not scraped from the fees page. 2026-09-17 (lane B run 1390, pipeline run 94): SOURCING GAP CLOSED. fee_source_url pointed at cityofboise.org/departments/planning-and-development-services/fees/, which is an Angular index that prints no dollar amounts at all (curl returns "{{doc.Title}}" placeholders). Rendered with headless Chromium, that index links the department's actual schedules, and they were downloaded and read in full today. Boise City Building Code Fee Schedule (10-1-23) prints the valuation ladder verbatim: "$1.00 to $2,000.00 - $26.37 for the first $500.00 plus $2.95 for each additional $100.00", "$2,001.00 to $25,000.00 - $70.76 for the first $2,000.00 plus $12.71 for each additional $1,000.00", and "Reinspection fee: $55". Boise City Plumbing Code Fee Schedule (10-1-21) Table B(3) prints "Water or waste re-piping $80", "Re-plumbing entire house or unit: $110", "Installation of single fixtures or appliances including bidets, bathtubs, showers, hot water heaters... $55", the $32 residential base permit fee and "Water heaters $12 Each". fee_source_url now points at the schedule that carries each row's figures. No figure changed; these remain the current schedules the city links.
Source: published fee schedule · Verified 11/9/2026
See the full write-up: Boise building permit cost
Estimate only.Fee schedules change, and building departments set the final valuation and decide which fees apply to your scope. Confirm with the jurisdiction before budgeting. Lines marked “see rule” could not be computed from the published wording and are shown verbatim rather than guessed.