B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Calculators
All Calculators
Permits
Permit Fee
Egress
Occupant Load & Egress
Structural
Beam SpanConcrete VolumeExcavationDeck Footings
Electrical
Electrical LoadWire Size
Mechanical
HVAC Load
Fire Safety
Fire Resistance
General
Stair Layout
Elsewhere
Code LibraryDiagramsAssembliesChecklistsNeed a custom calculation? →
PricingLog in
Home / Calculators / Building Permit Fee Calculator

Detroit, Michigan Building Permit Cost Calculator

Estimates permit cost in Detroit from the city's own published fee schedule — not a national average. Every figure is computed from a rule quoted verbatim from that document, and rules that cannot be computed honestly are shown as the published text instead of a number.

217 jurisdictions with fee schedules on file

Total cost of work, labor and materials

Used by cities that price per square foot

Fences and retaining walls

Electrical permits priced by the ampere

Building Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

How this jurisdiction calculates the fee

The building permit fee is set by City Council resolution and is calculated from the volume of the building or structure, the total cost of the improvement, and a schedule of unit costs for the applicable use and occupancy group and type of construction.

Source: published fee schedule · Verified 8/3/2026

Electrical Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Base fee
Flat fee $66.00
$66.00
○A1 Circuits - each circuit (New or Extended, Altered or Removed)
Flat fee $20.00
$20.00
○A2 Rough inspection (concealed wiring, each permit) - for inspection of single-family or two-family dwellings
Flat fee $59.00
$59.00
○A3 Fixtures - residential, per fixture
Flat fee $1.17
$1.17
○A3 Fixtures - commercial (luminaires), per fixture
Flat fee $1.46
$1.46
○A4 Motors/transformers, 1/4 HP, KW or KVA to 10 HP, KW, KVA or power plug, each
Flat fee $29.00
$29.00
○A5 Service, 100 or less amperes, each
Flat fee $59.00
$59.00
○A5 Service, over 100 to 200 amperes, each
Flat fee $117.00
$117.00
○A7 Distribution panel boards, 100 amps or less, each
Flat fee $51.00
$51.00
○A9 Feeders, each 100 feet or fraction thereof
Flat fee $41.00
$41.00
○A12 Sign connection, each circuit, sign or sign section
Flat fee $22.00
$22.00
○A14 Residential smoke alarms, hard-wired / interconnected, each
Flat fee $2.81
$2.81
How this jurisdiction calculates the fee

BSEED electrical permits are charged as a flat base fee plus per-item unit charges: per circuit, per fixture, per service by ampere rating, per distribution panel by ampere rating, per motor/transformer by horsepower, per 100 feet of feeder, and so on. There is no valuation-based or square-foot electrical fee.

Source: published fee schedule · Verified 9/15/2026

See the full write-up: Detroit building permit cost