Tulsa, Oklahoma Building Permit Cost Calculator
Estimates permit cost in Tulsa from the city's own published fee schedule — not a national average. Every figure is computed from a rule quoted verbatim from that document, and rules that cannot be computed honestly are shown as the published text instead of a number.
217 jurisdictions with fee schedules on file
Total cost of work, labor and materials
Used by cities that price per square foot
Fences and retaining walls
Electrical permits priced by the ampere
Building Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Building permit application fee (Sec. 301) - declared valuation $0 to $15,000.00 Flat fee $66.00 | $66.00 |
○Building permit application fee (Sec. 301) - declared valuation $15,000.01 to $100,000.00 Flat fee $101.50 | $101.50 |
○Building permit application fee (Sec. 301) - declared valuation above $100,000.00 $1.00 x 250 = $250.00 | $250.00 |
○Building permit fee (Sec. 302.A) - estimated valuation $0 to $5,000.00 Flat fee $137.00 | $137.00 |
○Building permit fee (Sec. 302.A) - estimated valuation $5,000.01 to $40,000.00 Flat fee $219.00 | $219.00 |
Building permit fee (Sec. 302.B) - estimated valuation over $40,000.00 up to and including $150,000.00, in $1,000 increments $6.18 per thousand of estimated valuation | see rule |
Building permit fee (Sec. 302.C) - additional fee on estimated valuation above $150,000.00, in $1,000 increments $3.09 per thousand of estimated valuation above $150,000.00 | see rule |
○Zoning clearance permit fee for construction or for a site with or without improvements, residential (Sec. 303.G) Flat fee $75.50 | $75.50 |
○Zoning clearance permit fee for construction or for a site with or without improvements, commercial (Sec. 303.F) Flat fee $92.00 | $92.00 |
○Residential certificate of occupancy associated with a new single-family residence, new duplex, or new townhouse (Sec. 303.B) Flat fee $34.00 | $34.00 |
○Certificate of occupancy fee for a new building with an associated building permit (Sec. 303.A) Flat fee $70.00 | $70.00 |
○Expediting fee - professional home builders (Sec. 305.A) Flat fee $121.00 | $121.00 |
○Expediting fee - residential fast track (Sec. 305.B) Flat fee $500.00 | $500.00 |
How this jurisdiction calculates the fee
Tulsa publishes no flat building permit price. Title 49, Chapter 3 charges two valuation-based amounts: a non-refundable application fee under Section 301, paid when the application is accepted, and a building permit fee under Section 302, paid at issuance and reduced by the amount of any application fee already paid. A zoning clearance permit fee under Section 303 applies to construction in addition. General administrative fees under Title 49, Chapter 1 are required on top of all of these, and watershed and stormwater fees under Chapter 12 may also apply. SUPERSEDED AND REPRICED 2026-09-11: Ordinance No. 25794, passed May 13, 2026, amended Title 49 Section 301 (s 2) and Section 302 (s 3). The Tulsa Code is now codified through Ordinance No. 25794 (Supp. No. 3, Update 2), so that is the schedule in force. Building permit application fee: $0 to $15,000 rose from $64.00 to $66.00 and $15,000.01 to $100,000 rose from $98.50 to $101.50. Building permit fee: $0 to $5,000 rose from $133.00 to $137.00, $5,000.01 to $40,000 rose from $213.00 to $219.00, and the increment above $40,000 up to $150,000 rose from $6.00 to $6.18 per thousand; Section 302.C now also states a band above $150,000 at $3.09 per thousand. Section 303 zoning clearance fees and the Section 304 carport fee were NOT amended by Ordinance 25794 and are unchanged.
Source: published fee schedule · Verified 10/1/2026
Deck Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Building permit application fee (Sec. 301) - declared valuation $0 to $15,000.00 Flat fee $66.00 | $66.00 |
○Building permit application fee (Sec. 301) - declared valuation $15,000.01 to $100,000.00 Flat fee $101.50 | $101.50 |
○Building permit fee (Sec. 302.A) - estimated valuation $0 to $5,000.00 Flat fee $137.00 | $137.00 |
○Building permit fee (Sec. 302.A) - estimated valuation $5,000.01 to $40,000.00 Flat fee $219.00 | $219.00 |
Building permit fee (Sec. 302.B) - estimated valuation over $40,000.00 up to and including $150,000.00, in $1,000 increments $6.18 per thousand of estimated valuation | see rule |
○Zoning clearance permit fee for construction or for a site with or without improvements, residential (Sec. 303.G) Flat fee $75.50 | $75.50 |
How this jurisdiction calculates the fee
Tulsa publishes no deck-specific permit fee. A residential deck is permitted as a building permit, so the charge is the valuation-based application fee under Title 49, Section 301 plus the building permit fee under Section 302, with the application fee already paid deducted from the permit fee at issuance. A residential zoning clearance permit fee applies in addition, as do the general administrative fees in Title 49, Chapter 1. SUPERSEDED AND REPRICED 2026-09-11: Ordinance No. 25794, passed May 13, 2026, amended Title 49 Section 301 (s 2) and Section 302 (s 3). The Tulsa Code is now codified through Ordinance No. 25794 (Supp. No. 3, Update 2), so that is the schedule in force. Building permit application fee: $0 to $15,000 rose from $64.00 to $66.00 and $15,000.01 to $100,000 rose from $98.50 to $101.50. Building permit fee: $0 to $5,000 rose from $133.00 to $137.00, $5,000.01 to $40,000 rose from $213.00 to $219.00, and the increment above $40,000 up to $150,000 rose from $6.00 to $6.18 per thousand; Section 302.C now also states a band above $150,000 at $3.09 per thousand. Section 303 zoning clearance fees and the Section 304 carport fee were NOT amended by Ordinance 25794 and are unchanged.
Source: published fee schedule · Verified 10/1/2026
Electrical Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Residential (one- and two-family dwellings)—New construction and additions only, 1—2,000 sq. ft. Flat fee $230.00 | $230.00 |
○Residential (one- and two-family dwellings)—New construction and additions only, 2,001—6,000 sq. ft. Flat fee $293.00 | $293.00 |
○Residential (one- and two-family dwellings)—Each additional 1,000 sq. ft. Flat fee $58.00 | $58.00 |
○Other electrical work — Electrical service (first 100 amps) Flat fee $98.00 | $98.00 |
○Other electrical work — Each additional 100 amps, or portion thereof Flat fee $18.00 | $18.00 |
○Other electrical work — Swimming pools Flat fee $235.00 | $235.00 |
○Other electrical work — Generator Flat fee $235.00 | $235.00 |
○Other electrical work — HVAC unit Flat fee $81.00 | $81.00 |
○Other electrical work — Electrical equipment, 1—25 Flat fee $81.00 | $81.00 |
○Other electrical work — Reconnect fee Flat fee $81.00 | $81.00 |
○Electrical Contractor certificate of registration Flat fee $178.00 | $178.00 |
How this jurisdiction calculates the fee
Electrical permit fees for one- and two-family dwellings involving new construction and additions are the electric service fee plus a base fee set by the size of the construction; other electrical work is charged per item, and administrative fees under Title 49, Chapter 1 are required in addition. | 2026-09-25 (lane B run 1754) RE-VERIFIED VERBATIM. Tulsa Title 49 Chapter 4 read today; the most recent amendment in the citation trail is Ord. No. 25351, s. 1, 7-17-2024, unchanged, so no new supplement has touched these fees.
Source: published fee schedule · Verified 9/25/2026
Fence Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Zoning clearance permit fee for construction or for a site with or without improvements, residential (Sec. 303.G) - fences and walls not over 7 feet Flat fee $75.50 | $75.50 |
○Zoning clearance permit fee for construction or for a site with or without improvements, commercial (Sec. 303.F) Flat fee $92.00 | $92.00 |
○Building permit application fee (Sec. 301) - declared valuation $0 to $15,000.00 - fences and walls over 7 feet Flat fee $66.00 | $66.00 |
○Building permit fee (Sec. 302.A) - estimated valuation $0 to $5,000.00 Flat fee $137.00 | $137.00 |
○Building permit fee (Sec. 302.A) - estimated valuation $5,000.01 to $40,000.00 Flat fee $219.00 | $219.00 |
How this jurisdiction calculates the fee
Tulsa has no separate fence permit fee line. Per the Development Services Residential Building Guidelines, fences and walls not over 7 feet tall require a zoning clearance only permit, so the charge is the zoning clearance permit fee in Title 49, Section 303. Fences and walls over 7 feet tall require a building permit, which is priced on construction valuation under Sections 301 and 302. General administrative fees under Title 49, Chapter 1 are required in addition. SUPERSEDED AND REPRICED 2026-09-11: Ordinance No. 25794, passed May 13, 2026, amended Title 49 Section 301 (s 2) and Section 302 (s 3). The Tulsa Code is now codified through Ordinance No. 25794 (Supp. No. 3, Update 2), so that is the schedule in force. Building permit application fee: $0 to $15,000 rose from $64.00 to $66.00 and $15,000.01 to $100,000 rose from $98.50 to $101.50. Building permit fee: $0 to $5,000 rose from $133.00 to $137.00, $5,000.01 to $40,000 rose from $213.00 to $219.00, and the increment above $40,000 up to $150,000 rose from $6.00 to $6.18 per thousand; Section 302.C now also states a band above $150,000 at $3.09 per thousand. Section 303 zoning clearance fees and the Section 304 carport fee were NOT amended by Ordinance 25794 and are unchanged.
Source: published fee schedule · Verified 10/1/2026
Reroof Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Building permit application fee (Sec. 301) - declared valuation $0 to $15,000.00 Flat fee $66.00 | $66.00 |
○Building permit application fee (Sec. 301) - declared valuation $15,000.01 to $100,000.00 Flat fee $101.50 | $101.50 |
○Building permit fee (Sec. 302.A) - estimated valuation $0 to $5,000.00 Flat fee $137.00 | $137.00 |
○Building permit fee (Sec. 302.A) - estimated valuation $5,000.01 to $40,000.00 Flat fee $219.00 | $219.00 |
Building permit fee (Sec. 302.B) - estimated valuation over $40,000.00 up to and including $150,000.00, in $1,000 increments $6.18 per thousand of estimated valuation | see rule |
How this jurisdiction calculates the fee
Tulsa publishes no re-roofing-specific permit fee. A re-roof is permitted as a building permit, priced on the declared and estimated construction valuation under Title 49, Sections 301 and 302: a non-refundable application fee at submittal, then the building permit fee at issuance less the application fee already paid. General administrative fees under Title 49, Chapter 1 are required in addition. SUPERSEDED AND REPRICED 2026-09-11: Ordinance No. 25794, passed May 13, 2026, amended Title 49 Section 301 (s 2) and Section 302 (s 3). The Tulsa Code is now codified through Ordinance No. 25794 (Supp. No. 3, Update 2), so that is the schedule in force. Building permit application fee: $0 to $15,000 rose from $64.00 to $66.00 and $15,000.01 to $100,000 rose from $98.50 to $101.50. Building permit fee: $0 to $5,000 rose from $133.00 to $137.00, $5,000.01 to $40,000 rose from $213.00 to $219.00, and the increment above $40,000 up to $150,000 rose from $6.00 to $6.18 per thousand; Section 302.C now also states a band above $150,000 at $3.09 per thousand. Section 303 zoning clearance fees and the Section 304 carport fee were NOT amended by Ordinance 25794 and are unchanged.
Source: published fee schedule · Verified 10/1/2026
Retaining Wall Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Zoning clearance permit fee for construction or for a site with or without improvements, residential (Sec. 303.G) - retaining walls not over 4 feet Flat fee $75.50 | $75.50 |
○Zoning clearance permit fee for construction or for a site with or without improvements, commercial (Sec. 303.F) Flat fee $92.00 | $92.00 |
○Building permit application fee (Sec. 301) - declared valuation $0 to $15,000.00 - retaining walls over 4 feet Flat fee $66.00 | $66.00 |
○Building permit application fee (Sec. 301) - declared valuation $15,000.01 to $100,000.00 Flat fee $101.50 | $101.50 |
○Building permit fee (Sec. 302.A) - estimated valuation $0 to $5,000.00 Flat fee $137.00 | $137.00 |
○Building permit fee (Sec. 302.A) - estimated valuation $5,000.01 to $40,000.00 Flat fee $219.00 | $219.00 |
How this jurisdiction calculates the fee
Tulsa has no separate retaining wall permit fee line. Per the Development Services Residential Building Guidelines, retaining walls measured from bottom of footing to top of wall that are not over 4 feet tall require a zoning clearance only permit, so the charge is the zoning clearance permit fee in Title 49, Section 303. Retaining walls over 4 feet require a building permit and engineer-sealed design, and the building permit is priced on construction valuation under Sections 301 and 302. General administrative fees under Title 49, Chapter 1 are required in addition, and stormwater or watershed fees under Chapter 12 may apply where the work involves an earth change. SUPERSEDED AND REPRICED 2026-09-11: Ordinance No. 25794, passed May 13, 2026, amended Title 49 Section 301 (s 2) and Section 302 (s 3). The Tulsa Code is now codified through Ordinance No. 25794 (Supp. No. 3, Update 2), so that is the schedule in force. Building permit application fee: $0 to $15,000 rose from $64.00 to $66.00 and $15,000.01 to $100,000 rose from $98.50 to $101.50. Building permit fee: $0 to $5,000 rose from $133.00 to $137.00, $5,000.01 to $40,000 rose from $213.00 to $219.00, and the increment above $40,000 up to $150,000 rose from $6.00 to $6.18 per thousand; Section 302.C now also states a band above $150,000 at $3.09 per thousand. Section 303 zoning clearance fees and the Section 304 carport fee were NOT amended by Ordinance 25794 and are unchanged.
Source: published fee schedule · Verified 10/1/2026
Shed Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Zoning clearance permit fee for construction or for a site with or without improvements, residential (Sec. 303.G) - accessory structure 200 sq. ft. or less Flat fee $75.50 | $75.50 |
○Zoning clearance permit fee for construction or for a site with or without improvements, commercial (Sec. 303.F) Flat fee $92.00 | $92.00 |
○Building permit application fee (Sec. 301) - declared valuation $0 to $15,000.00 Flat fee $66.00 | $66.00 |
○Building permit application fee (Sec. 301) - declared valuation $15,000.01 to $100,000.00 Flat fee $101.50 | $101.50 |
○Building permit application fee (Sec. 301) - declared valuation above $100,000.00 $1.00 x 250 = $250.00 | $250.00 |
○Building permit fee (Sec. 302.A) - estimated valuation $0 to $5,000.00 Flat fee $137.00 | $137.00 |
○Building permit fee (Sec. 302.A) - estimated valuation $5,000.01 to $40,000.00 Flat fee $219.00 | $219.00 |
Building permit fee (Sec. 302.B) - estimated valuation over $40,000.00 up to and including $150,000.00, in $1,000 increments $6.18 per thousand of estimated valuation | see rule |
Building permit fee (Sec. 302.C) - estimated valuation over $150,000.00, in $1,000 increments, additional $3.09 per thousand of estimated valuation above $150,000.00 | see rule |
○Carport permit fee (Sec. 304) Flat fee $98.00 | $98.00 |
How this jurisdiction calculates the fee
Tulsa has no separate shed permit fee line. A one-story detached accessory structure of 200 square feet or less that is at least 5 feet from other structures needs no footing or building permit, but a zoning clearance permit is still required, so the charge is the zoning clearance permit fee in Title 49, Section 303. A larger accessory building requires a building permit priced on construction valuation under Sections 301 and 302. General administrative fees under Title 49, Chapter 1 are required in addition. SUPERSEDED AND REPRICED 2026-09-11: Ordinance No. 25794, passed May 13, 2026, amended Section 301 (s 2) and Section 302 (s 3) and raised every valuation-based amount. The Tulsa Code is now codified through Ordinance No. 25794 (Supp. No. 3, Update 2), so this is the schedule in force. Building permit application fee: $0 to $15,000 rose from $64.00 to $66.00 and $15,000.01 to $100,000 rose from $98.50 to $101.50; a band above $100,000 at $1.00 per $1,000 of value is now stated. Building permit fee: $0 to $5,000 rose from $133.00 to $137.00, $5,000.01 to $40,000 rose from $213.00 to $219.00, and the increment above $40,000 up to $150,000 rose from $6.00 to $6.18 per thousand; a further band above $150,000 at $3.09 per thousand is now stated. The Section 303 zoning clearance fees and the Section 304 carport fee were NOT amended by Ordinance 25794 (both still carry Ord. No. 25351, 7-17-2024) and are unchanged at $75.50 residential, $92.00 commercial and $98.00 carport.
Source: published fee schedule · Verified 10/1/2026
Water Heater Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Water heater fee Flat fee $35.00 | $35.00 |
○Water service fee Flat fee $35.00 | $35.00 |
○Plumbing fixtures, appliances, and appurtenances (except those listed above)—Base fee, including the first fixture, appliance, or appurtenance Flat fee $81.00 | $81.00 |
○Plus, each additional fixture, appliance, or appurtenance Flat fee $3.31 | $3.31 |
○Backflow prevention assembly fee Flat fee $79.00 | $79.00 |
○Interceptor/separator fee Flat fee $150.00 | $150.00 |
○Gas Piping per meter Flat fee $41.00 | $41.00 |
○Outside of City permit/inspection fee, where an inspection requires travel outside the corporate limits Flat fee $92.00 | $92.00 |
○Plumbing Contractor certificate of registration Flat fee $178.00 | $178.00 |
How this jurisdiction calculates the fee
Permit and inspection fees for all plumbing work are charged per item of work under Title 49, Chapter 8, and administrative fees under Title 49, Chapter 1 are required in addition. | 2026-09-25 (lane B run 1754) RE-VERIFIED VERBATIM from Tulsa Title 49 Chapter 8 (Plumbing Permit Fees). All nine stored figures present. Note the sibling tulsa/electrical row: Title 49 Chapter 4's latest amendment is Ord. No. 25351, 7-17-2024, unchanged.
Source: published fee schedule · Verified 9/25/2026
See the full write-up: Tulsa building permit cost
Estimate only.Fee schedules change, and building departments set the final valuation and decide which fees apply to your scope. Confirm with the jurisdiction before budgeting. Lines marked “see rule” could not be computed from the published wording and are shown verbatim rather than guessed.