Burlington, Vermont Building Permit Cost Calculator
Estimates permit cost in Burlington from the city's own published fee schedule — not a national average. Every figure is computed from a rule quoted verbatim from that document, and rules that cannot be computed honestly are shown as the published text instead of a number.
217 jurisdictions with fee schedules on file
Total cost of work, labor and materials
Used by cities that price per square foot
Fences and retaining walls
Electrical permits priced by the ampere
Building Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Rate per $1,000.00 of the estimated cost of the work and construction Flat fee $8.50 | $8.50 |
○Minimum charge per permit, Burlington Code of Ordinances Sec. 8-28(a) Flat fee $20.00 | $20.00 |
○Tolerance between estimated and actual cost within which no additional fee or refund is required Flat fee $2,500.00 | $2,500.00 |
○Administrative processing fee added where the building inspector enforces Chapter 8 and a building permit is required as a result, estimated cost of construction $3,000.00 or less Flat fee $30.00 | $30.00 |
Administrative processing fee where the estimated cost of construction is $3,000.00 or greater one (1) percent of the estimated cost of construction | see rule |
How this jurisdiction calculates the fee
The permit fee is eight dollars and fifty cents ($8.50) for every one thousand dollars ($1,000.00) of the estimated cost of the work and construction as the building inspector may approve. Burlington Code of Ordinances Sec. 8-28(a) sets a minimum charge of twenty dollars ($20.00) per permit, while the Department of Permitting & Inspections page Permit Applications and Forms states a minimum permit fee of thirty ($30.00) dollars. On projects with an estimated cost of construction of ten thousand dollars ($10,000.00) or more, the owner furnishes the building inspector a signed statement of total actual cost at completion and pays an additional fee on any excess over the estimate, or receives a proportionate refund where actual cost is lower, provided the refund does not reduce the fee below the minimum. If actual costs are within two thousand five hundred dollars ($2,500.00) of the original estimate, no additional fee or refund is required.
Source: published fee schedule · Verified 11/10/2026
Deck Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○New $1,500 deck, COA Level I - Zoning Permit Application Fee (includes application, filing, and certificate of occupancy fees) Flat fee $122.00 | $122.00 |
○New $1,500 deck, COA Level I - Construction Permit Fee (any project up to $2858 construction cost) Flat fee $30.00 | $30.00 |
New $1,500 deck, COA Level I - total $152-162 in fees | see rule |
○New $50,000 deck, COA Level II - Zoning Permit Application Fee (the first 'half' of the zoning fee, due at application) Flat fee $250.00 | $250.00 |
○New $50,000 deck, COA Level II - Development Review Fee (the second 'half' of the zoning fee, due when the zoning permit is picked up) Flat fee $225.00 | $225.00 |
○New $50,000 deck, COA Level II - Construction Permit Fee ($8.50 per $1,000 of construction cost plus $15 recording fee) Flat fee $440.00 | $440.00 |
New $50,000 deck, COA Level II - total $915 or $925 in fees | see rule |
○Additional charge that may be added where the project requires a Building Certificate of Occupancy Flat fee $10.00 | $10.00 |
How this jurisdiction calculates the fee
Fees are calculated based upon the Estimated Construction Cost, so applicants should be prepared with the project's estimated construction cost dollar figure. Permit processing fees are due at application time; Development Review fees, Impact fees, and fees to request the Final Unified Certificate of Occupancy (for zoning permits applied for before July 1, 2020) are due after the permit has been approved. RE-VERIFIED 2026-09-28 (lane B, pipeline run 98). Both the Fence Checklist PDF and the Permit Fees web page (burlingtonvt.gov/558) were fetched directly and read; every stored figure re-reads verbatim, including the $107 fence application fee plus $15 filing fee, the $122 and $30 COA Level I components, the $250 / $225 / $440 COA Level II components with the $8.50 per $1,000 construction-cost basis and $15 recording fee, and the $10 that may be added where a Building Certificate of Occupancy is required. No supersession.
Source: published fee schedule · Verified 11/12/2026
Electrical Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Rate per $1,000.00 of the estimated cost of the work Flat fee $8.50 | $8.50 |
○Minimum charge per permit Flat fee $50.00 | $50.00 |
○Additional administrative processing fee where electrical work requiring a permit commences before a permit has been issued and the estimated cost of the work is less than or equal to $6,000.00 Flat fee $75.00 | $75.00 |
Additional administrative processing fee where the estimated cost of construction is $6,000.00 or greater one (1) percent of the estimated cost of the work | see rule |
○Each reinspection for code violations Flat fee $100.00 | $100.00 |
How this jurisdiction calculates the fee
The wiring permit fee is eight dollars and fifty cents ($8.50) for every one thousand dollars ($1,000.00) of the estimated cost of the work as the wiring inspector may approve, with a minimum charge of fifty dollars ($50.00) per permit.
Source: published fee schedule · Verified 11/10/2026
Fence Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
Fence application, replacement fences and new fences $107 plus a $15 filing fee | see rule |
How this jurisdiction calculates the fee
A fence application carries a flat application fee plus a filing fee, payable in cash, checks, and credit cards. Checks are made out to the 'City of Burlington', and credit card payments incur a convenience fee. RE-VERIFIED 2026-09-28 (lane B, pipeline run 98). Both the Fence Checklist PDF and the Permit Fees web page (burlingtonvt.gov/558) were fetched directly and read; every stored figure re-reads verbatim, including the $107 fence application fee plus $15 filing fee, the $122 and $30 COA Level I components, the $250 / $225 / $440 COA Level II components with the $8.50 per $1,000 construction-cost basis and $15 recording fee, and the $10 that may be added where a Building Certificate of Occupancy is required. No supersession.
Source: published fee schedule · Verified 11/12/2026
Reroof Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Construction permit rate per $1,000.00 of the estimated cost of the work (Code Section 8-28(a)) Flat fee $8.50 | $8.50 |
○Minimum charge per permit (Code Section 8-28(a)) Flat fee $20.00 | $20.00 |
○Minimum construction permit fee for any project up to $2,858 construction cost (Department of Permitting & Inspections Permit Fees page) Flat fee $30.00 | $30.00 |
○Land records recording fee included in the construction permit fee Flat fee $15.00 | $15.00 |
Alterations or repairs costing not more than $1,000.00 (Code Section 8-28(d)) No permit or fee required | see rule |
○Administrative processing fee added where the building inspector enforces Chapter 8 and a building permit is required as a result, estimated cost of construction $3,000.00 or less (Code Section 8-28(f)) Flat fee $30.00 | $30.00 |
Administrative processing fee where the estimated cost of construction is $3,000.00 or greater (Code Section 8-28(f)) one (1) percent of the estimated cost of construction | see rule |
Zoning permit application fee if a zoning permit is required (historic building or Design Review District), COA Level I, estimated construction cost under $29,000, FY2027 $15 filing fee plus $107 | see rule |
○Additional charge where the project requires a Building Certificate of Occupancy Flat fee $10.00 | $10.00 |
How this jurisdiction calculates the fee
Re-roofing requires a building (construction) permit from the Burlington Department of Permitting & Inspections Building & Trades Division: a building permit is required for all non-mechanical, electrical and plumbing work in Burlington except carpeting, painting, nonsolid fences, storm doors and storm windows, and in-kind repair work costing $1,000.00 or less. The permit fee is codified at Burlington Code of Ordinances Section 8-28(a) as a per-$1,000 rate on the estimated cost of the work approved by the building inspector, subject to a minimum charge per permit. A zoning permit is generally not needed for design changes to the roof of a building that is not a historic building and is not within the Design Review District; where a zoning permit is required, the zoning application fee is added.
Source: published fee schedule · Verified 9/15/2026
Retaining Wall Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
COA Level I / Basic Zoning Permit, estimated construction cost less than $29,000 (FY2027) $15 filing fee plus $107 | see rule |
○COA Level II application fee, estimated construction cost $29,000 or greater (FY2027) $140.00 base plus $2.20 x 250 = $690.00 | $690.00 |
○COA Level II development review fee, due prior to release of permit $4.50 x 250 = $1,125.00 | $1,125.00 |
○Construction (building) permit rate per $1,000.00 of the estimated cost of the work (Code Section 8-28(a)) Flat fee $8.50 | $8.50 |
○Minimum construction permit charge (Code Section 8-28(a)) Flat fee $20.00 | $20.00 |
○Minimum construction permit fee for any project up to $2,858 construction cost (Permit Fees page) Flat fee $30.00 | $30.00 |
Final Zoning Certificate of Occupancy, included in application fees above $30 plus 10% of the total application fees | see rule |
○Conditional Use or Variance, in addition to any applicable COA fees Flat fee $195.00 | $195.00 |
○Appeals of administrative and enforcement decisions to the Development Review Board Flat fee $250.00 | $250.00 |
Credit card payment surcharge $3 processing fee plus 2.65% for transactions over $123.00 | see rule |
Permit application resulting from a zoning Notice of Violation double, triple, or triple plus up to $500 the application fee | see rule |
How this jurisdiction calculates the fee
Retaining walls are expressly listed among the projects that require a Burlington zoning permit. Zoning fees are set by the Department of Permitting & Inspections FY2027 Fee Schedule and are banded by Estimated Construction Cost (ECC): below the Certificate of Appropriateness Level I/II threshold ($29,000 for FY2027) the project is a COA Level I / Basic Zoning Permit charged a flat application fee plus a filing fee; at or above the threshold it is a COA Level II, charged an application fee with a per-$1,000 component at application plus a separate development review fee due before the permit is released. Most projects requiring a zoning permit also require a construction (building) permit, charged per $1,000 of estimated cost under Burlington Code of Ordinances Section 8-28.
Source: published fee schedule · Verified 9/15/2026
Shed Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
COA Level I / Basic Zoning Permit, estimated construction cost less than $29,000 (FY2027) $15 filing fee plus $107 | see rule |
○COA Level II application fee, estimated construction cost $29,000 or greater (FY2027) $140.00 base plus $2.20 x 250 = $690.00 | $690.00 |
○COA Level II development review fee, due prior to release of permit $4.50 x 250 = $1,125.00 | $1,125.00 |
○Construction (building) permit rate per $1,000.00 of the estimated cost of the work (Code Section 8-28(a)) Flat fee $8.50 | $8.50 |
○Minimum construction permit charge (Code Section 8-28(a)) Flat fee $20.00 | $20.00 |
○Minimum construction permit fee for any project up to $2,858 construction cost (Permit Fees page) Flat fee $30.00 | $30.00 |
Final Zoning Certificate of Occupancy, included in application fees above $30 plus 10% of the total application fees | see rule |
○Additional charge where the project requires a Building Certificate of Occupancy Flat fee $10.00 | $10.00 |
○Conditional Use or Variance, in addition to any applicable COA fees Flat fee $195.00 | $195.00 |
Credit card payment surcharge $3 processing fee plus 2.65% for transactions over $123.00 | see rule |
Permit application resulting from a zoning Notice of Violation double, triple, or triple plus up to $500 the application fee | see rule |
How this jurisdiction calculates the fee
Sheds are expressly listed among the projects that require a Burlington zoning permit. Zoning fees are set by the Department of Permitting & Inspections FY2027 Fee Schedule and are banded by Estimated Construction Cost (ECC): below the Certificate of Appropriateness Level I/II threshold ($29,000 for FY2027) the project is a COA Level I / Basic Zoning Permit charged a flat application fee plus a filing fee; at or above the threshold it is a COA Level II, charged an application fee with a per-$1,000 component at application plus a separate development review fee due before the permit is released. Most projects requiring a zoning permit also require a construction (building) permit, charged per $1,000 of estimated cost under Burlington Code of Ordinances Section 8-28.
Source: published fee schedule · Verified 9/15/2026
Water Heater Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Rate per $1,000.00 of the cost of the work Flat fee $8.50 | $8.50 |
○Minimum charge per permit, including the land records recording fee Flat fee $30.00 | $30.00 |
○Administrative processing fee added where the plumbing inspector enforces Chapter 25 and a plumbing permit is required as a result, estimated cost of the work $3,000.00 or less Flat fee $30.00 | $30.00 |
Administrative processing fee where the estimated cost of construction is $3,000.00 or greater one (1) percent of the estimated cost of the work | see rule |
How this jurisdiction calculates the fee
The plumbing permit fee is eight dollars and fifty cents ($8.50) for every one thousand dollars ($1,000.00) of the cost of the work, with a minimum charge of thirty dollars ($30.00) per permit, which includes the land records recording fee. The fee submitted with the application is based on the estimated cost of the work; on completion the applicant furnishes the inspector with a correct statement of total actual cost and pays the fee on the difference, with a refund of any excess of estimate over actual cost provided the refund does not reduce the fee below the minimum charge. | 2026-09-25 (lane B run 1754) RE-VERIFIED, NOTHING CHANGED. codepublishing.com returned HTTP 403 to curl and to headless Chromium and the Cloudflare challenge was NOT solved; the chapter was read through WebFetch to confirm presence only. All four stored figures came back verbatim: "$8.50 for every one thousand dollars ($1,000.00) of the cost", minimum charge "$30.00, which includes the land records recording fee, per permit", administrative processing fee $30.00 under $3,000 and one (1) percent of estimated cost at $3,000 or greater. Most recent amendment shown is Ord. of 1-22-18(2), which predates our last verification; no supersession.
Source: published fee schedule · Verified 11/11/2026
See the full write-up: Burlington building permit cost
Estimate only.Fee schedules change, and building departments set the final valuation and decide which fees apply to your scope. Confirm with the jurisdiction before budgeting. Lines marked “see rule” could not be computed from the published wording and are shown verbatim rather than guessed.