495 Barrier Delineators ...................................................... 926.02(c) Cast-in-Place Barriers .................................................. 702 Cast-in-Place Concrete Glare Screens ......................... 702 Concrete Sealers .......................................................... 709 Construction Warn ing Lights ...................................... 923.03 Precast Barriers ............................................................ 707 Precast Concrete Glare Screen .................................... 707 Reinforcing Bars .......................................................... 910.01 CONSTRUCTION REQUIREMENTS
602.03 Concrete Barrier an d Concrete Glare Screen
Concrete barrier and concrete glare screen may be precast or cast-in-place. The option selected shall be used continuously throughout the project. Irregular sections shall be cast-in-place regard less of the option selected. Concrete glare screen may only be precas t when constructed in combination with new precast barrier. Concrete glare screen shall be cast-in-place when constructed in combination with cast-in-place barrier and when constructed on top of existing 30 concrete barrier. Excavation and compaction shall be in accordance with 605.03(a). Backfilling shall be in accordance with appli cable requirements of 605.03(d).
702.21 If slip-form construction is used, an approved brush finish will be allowed.
Curing material in accordance with 912.01(e) shall be applied as a bond breaker to all areas which result in concrete-to-concrete contact. It shall be applied at a minimum 70 rate of 1 gal./75 sq ft. If material is applied at a rate less than the minimum rate, a second application shall be applied.
602.04 Blank
602.05 Method of Measurement
Concrete barrier will be measured by the linear foot along the centerline of the barrier, including irregular barrier sections around median obstructions such as bridge piers. Barrier delineators will be measured per each provided there is a pay item shown in the Schedule of Pay Items. Concrete glare screen will be measured by the linear foot along the centerline of the glare screen. Cl ass A concrete for cast-in-place modified concrete barriers will be measured by the cubic yard for the modified barrier section. No deductions will be made for reinforcing bars or joints. Reinforcing bars for cast- 100 in-place modified concrete barriers will be measured in accordance with 703.07.
602.06 Basis of Payment
Concrete barrier will be paid for at the contract unit price per linear foot, complete 602.04 497 in place. Class A concrete for cast-in-place modified concrete barriers will be paid for at the contract unit price per cubic yard. Re inforcing bars for cast-in-place modified concrete barriers will be paid for in acco rdance with 703.08. Barrier delineators used on concrete barrier will be paid for at the contract unit price per each, complete in place. 110 Concrete glare screen will be paid for at the contract unit price per linear foot, complete in place. Payment will be made under: Pay Item Pay Unit Symbol Barrier Delineator ...................................................................... EACH Concrete Barrier Glare Screen ................................................... LFT Concrete Barrier ........................................................................ LFT 120 Concrete Barrier, Modified Section ........................................... CYS The cost of polyethylene film, surface seal, and curing material shall be included in the cost of concrete barrier.