encountered, intermediate or line posts shall be driven and furnished with an approved anchor plate or other satisfactory device to hold the post in proper alignment and plumb. The plate or anchor shall be welded or riveted to the post with no less than two rivets. Gate posts shall be set in concrete as shown on the plans. Extra length posts shall be required at stream crossings as shown on the plans or as directed and also at ground depressions where it is not practicable for the fencing to follow closely the contour of the ground. These posts shall be set in concrete as 80 shown on the plans. At small stream crossings and ground depressions, the space below the fence fabric shall be closed with barbed or ground tension wire, either on horizontal lines or fanned, as shown on the plans or as directed. The wires shall be stretched taut between and fastened to the posts to prevent vertical movement of the wires. Barbed or tension wire shall not be placed where its installation would cause collecting drifts in the channel. 603.05 Placing Barbed and Tension Wire and Fabric 90 The bottom of the fabric shall be placed above the ground line as shown on the plans. Over irregular ground, a minimum of 1 in. and a maximum of 4 in. clearance will be allowed. All necessary excavation and backfilling required shall be in accordance with 201.03. The tension required to stretch the fabric and wire shall be applied by mechanical fence stretchers and with single wire st retchers designed and manufactured for the purpose, and in accordance with the fe nce manufacturer’s recommendations. All splices in the fabric and wire sha ll be securely made in accordance with the 100 best practice and the manufacturer’s recommendations, and by the use of tools designed for that purpose. Farm field fence shall be placed by fastening one end and then applying sufficient tension to remove all slack before making permanent attachments elsewhere. The line wires shall be fastened to end, corner, and pull posts by wrapping the wires around the posts and tying the wire back on itself with no less than 1 1/2 tightly wrapped twists. Tying shall be with tools designed for the purpose in accordance with the fence manufacturer’s recommendations. This same method shall be used in placing barbed or tension wire. Fence fabric shall be fastened to intermediate or line posts with at least 110 five wire ties. Barbed or tension wire shall be fastened in the same manner with one fastening device for each post.
The top and bottom tension wires of chain link fence shall be placed, stretched taut, and secured at the ends and to all posts before the fabric is placed. The ends of the fabric shall be secured by the use of stretcher-bars threaded through the loops of 603.05 500 the fabric and secured to the posts by means of clamps with bolts and nuts. The number of clamps shall be as indicated on the plans. The fabric shall be placed by securing one end and then applying tension to remove all slack before making attachments elsewhere. The fabric shall be fastened to the line posts and to the top and bottom 120 tension wires with tie wires spaced as shown on the plans. 603.06 Resetting Fence Resetting fence shall consist of the removal of existing fence within the specified limits and, if necessary, storing and resetting it in accordance with the plans, or as directed. Resetting fence shall be in accordance with 603.03, 603.04, and 603.05. Damaged or missing parts, in cluding posts shall be replaced.
603.07Method of Measurement
Fence and resetting fence will be measured by the linear foot for the type 130 specified. Measurement will be made along the top of the fence from outside to outside of end posts for each continuous run of fence. Gates will be measured as complete units of the size and type specified. 603.08 Basis of Payment The accepted quantities of fence and resetting fence will be paid for at the contract unit price per linear foot for the type specified, complete in place. Gates will be paid for at the contract unit price per each for fence gate, of the type and size specified, complete in place. 140
Payment will be made under: Pay Item Pay Unit Symbol Fence Gate, _____, ______ in. x _____ ft ................................. EACH type height length Fence, _____, ______ in. .......................................................... LFT type height Fence, _____, Reset ................................................................... LFT 150 type Fence, Farm Field, Barbed Wire, _____ in. .............................. LFT Fence, Farm Field, Tension Wire, _____ in. ............................. LFT
The cost of adding grounding in accordance with the NEC including all materials and labor shall be included in the cost of the fence. The cost of fence fabric, corner, end, line, and pull posts shall be included in the cost of the fence. 160 The cost of fence fabric for gates, posts, and miscellaneous hardware shall be included in the cost of the gate. 603.06 501 The cost of all miscellaneous hardware re lated to the type of fence including brace connections, caps, clips, clamps, hinges, rivets, ties, truss rods, diagonal braces, and stretcher bars shall be included in the cost of the fence. The cost of concrete for posts, braces or anchors shall be included in the cost of the fence and gates. 170 The cost of removal, storage, re-installation, and the replacement of damaged or missing parts shall be included in the cost of the resetting fence.