B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Calculators
All Calculators
Permits
Permit Fee
Egress
Occupant Load & Egress
Structural
Beam SpanConcrete VolumeExcavationDeck Footings
Electrical
Electrical LoadWire Size
Mechanical
HVAC Load
Fire Safety
Fire Resistance
General
Stair Layout
Elsewhere
Code LibraryDiagramsAssembliesChecklistsNeed a custom calculation? →
PricingLog in
Home / Calculators / Building Permit Fee Calculator

Augusta, Georgia Building Permit Cost Calculator

Estimates permit cost in Augusta from the city's own published fee schedule — not a national average. Every figure is computed from a rule quoted verbatim from that document, and rules that cannot be computed honestly are shown as the published text instead of a number.

217 jurisdictions with fee schedules on file

Total cost of work, labor and materials

Used by cities that price per square foot

Fences and retaining walls

Electrical permits priced by the ampere

Building Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○New construction, residential single family or duplex, building permit
$0.24 x 2,000 = $480.00
$480.00
Electrical permit, new house
$72.00 flat fee
see rule
Mechanical permit, new house
$72.00 flat fee
see rule
Plumbing permit, new house
$72.00 flat fee
see rule
○Addition or alteration, residential
$225.00 base plus $0.24 x 2,000 = $705.00
$705.00
○Building plan review, new construction or addition
$0.09 x 2,000 = $180.00
$180.00
○Re-inspection
Flat fee $50.00
$50.00
○Permit renewal or extension, residential
Flat fee $72.00
$72.00
○Certificate of Occupancy (commercial)
Flat fee $100.00
$100.00
How this jurisdiction calculates the fee

Augusta-Richmond County Building Division Fee Schedule, approval date January 7, 2025. Augusta is a consolidated city-county, so this one schedule covers the whole of Richmond County. New single-family and duplex construction is charged per square foot under roof for the building permit, with separate flat-rate trade permits for electrical, mechanical and plumbing. Additions and alterations are charged a flat base plus a per-square-foot rate. Commercial and multi-family new building permits are calculated from the building's square footage multiplied by the 2018 International Building Code square-foot construction cost for its occupancy group and construction type, multiplied by a factor of .0062. CONFLICT BETWEEN TWO OFFICIAL AUGUSTA SOURCES, RECORDED NOT RESOLVED (found 2026-09-07): the figures above are from the Building Division Fee Schedule PDF (DocumentCenter/View/19493), approval date January 7, 2025. Augusta also currently publishes, at augustaga.gov/1112/Permit-Fees under Departments > Planning & Development > Building/Construction > Permit Information, an undated residential schedule stating Building $.06 per square foot under roof; Electrical, Mechanical and Plumbing $50.00 each per house; Fireplace $8.00 each; inspection fee per house $238.00 on crawl space (14 inspections at $17.00) or $255.00 on slab (15 inspections at $17.00); and a plan review fee of 66% of the permit amount for General, Electrical, Mechanical and Plumbing permits with one- and two-family dwellings exempt. That page carries no effective or approval date and names the License and Inspection Department as contact. The two documents disagree on the residential per-square-foot rate, the trade permit amounts and the plan review basis. The dated adopted schedule is used above; a human should confirm which governs. | CONFLICT OPENED 2026-09-12 (lane B run 814), NOT RESOLVED, FIGURES UNCHANGED: three official Augusta sources publish three different residential building rates. The cited Building Division Fee Schedule (DocumentCenter/View/19493, approval date January 7, 2025) gives $0.24 per square foot under roof and $72.00 flat electrical/mechanical trade permits; the live City page augustaga.gov/1112/Permit-Fees gives $0.06 per square foot and $50.00 trade permits with plan review at 66%; and augustaga.gov/DocumentView.aspx?DID=1993 gives $0.048 per square foot and $21.60 trade permits. Our stored figures follow View/19493, which is the schedule the Building Permits page (augustaga.gov/2101) currently links, so it is the newest and the departmentally-endorsed one - but the other two remain live on the City site and were not withdrawn. Protocol forbids picking one; both alternate readings are recorded here and the row is reported for human resolution. The 2026 Residential Packet (View/21801) was also read in full and contains no fee schedule.

Source: published fee schedule · Verified 11/2/2026

Deck Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Residential deck or porch
$135.00 base plus $0.20 x 2,000 = $535.00
$535.00
○Re-inspection
Flat fee $50.00
$50.00
○Permit renewal or extension, residential
Flat fee $72.00
$72.00
How this jurisdiction calculates the fee

Augusta-Richmond County Building Division Fee Schedule, approval date January 7, 2025. Decks and porches are a named line item in the residential addition/alteration/general repairs section and are charged as a flat base fee plus a per-square-foot rate. CONFLICT BETWEEN TWO OFFICIAL AUGUSTA SOURCES, RECORDED NOT RESOLVED (found 2026-09-07): the figures above are from the Building Division Fee Schedule PDF (DocumentCenter/View/19493), approval date January 7, 2025. Augusta also currently publishes, at augustaga.gov/1112/Permit-Fees under Departments > Planning & Development > Building/Construction > Permit Information, an undated residential schedule stating Building $.06 per square foot under roof; Electrical, Mechanical and Plumbing $50.00 each per house; Fireplace $8.00 each; inspection fee per house $238.00 on crawl space (14 inspections at $17.00) or $255.00 on slab (15 inspections at $17.00); and a plan review fee of 66% of the permit amount for General, Electrical, Mechanical and Plumbing permits with one- and two-family dwellings exempt. That page carries no effective or approval date and names the License and Inspection Department as contact. The two documents disagree on the residential per-square-foot rate, the trade permit amounts and the plan review basis. The dated adopted schedule is used above; a human should confirm which governs. | CONFLICT OPENED 2026-09-12 (lane B run 814), NOT RESOLVED, FIGURES UNCHANGED: three official Augusta sources publish three different residential building rates. The cited Building Division Fee Schedule (DocumentCenter/View/19493, approval date January 7, 2025) gives $0.24 per square foot under roof and $72.00 flat electrical/mechanical trade permits; the live City page augustaga.gov/1112/Permit-Fees gives $0.06 per square foot and $50.00 trade permits with plan review at 66%; and augustaga.gov/DocumentView.aspx?DID=1993 gives $0.048 per square foot and $21.60 trade permits. Our stored figures follow View/19493, which is the schedule the Building Permits page (augustaga.gov/2101) currently links, so it is the newest and the departmentally-endorsed one - but the other two remain live on the City site and were not withdrawn. Protocol forbids picking one; both alternate readings are recorded here and the row is reported for human resolution. The 2026 Residential Packet (View/21801) was also read in full and contains no fee schedule.

Source: published fee schedule · Verified 11/4/2026

Electrical Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

Stand-alone residential electrical trade permit
$72.00 flat fee
see rule
Electrical permit, new house
$72.00 flat fee
see rule
Electrical service change out, residential
$72.00 up to 400 amps, plus $50.00 for each additional 200 amps
see rule
Electrical temporary pole, residential
$72.00 flat fee
see rule
Electrical, commercial
$100.00 up to 400 amps, plus $50.00 for each additional 200 amps
see rule
Electrical temporary pole, commercial
$100.00 flat fee
see rule
○Re-inspection
Flat fee $50.00
$50.00
How this jurisdiction calculates the fee

Augusta-Richmond County Building Division Fee Schedule, approval date January 7, 2025. Residential electrical permits are flat-rate, whether taken with a new house, as part of an addition or alteration, or as a stand-alone trade permit. Service change-outs are flat-rate up to 400 amps with a step charge for larger services. Commercial electrical permits are priced on the same amperage structure at a higher base. CONFLICT BETWEEN TWO OFFICIAL AUGUSTA SOURCES, RECORDED NOT RESOLVED (found 2026-09-07): the figures above are from the Building Division Fee Schedule PDF (DocumentCenter/View/19493), approval date January 7, 2025. Augusta also currently publishes, at augustaga.gov/1112/Permit-Fees under Departments > Planning & Development > Building/Construction > Permit Information, an undated residential schedule stating Building $.06 per square foot under roof; Electrical, Mechanical and Plumbing $50.00 each per house; Fireplace $8.00 each; inspection fee per house $238.00 on crawl space (14 inspections at $17.00) or $255.00 on slab (15 inspections at $17.00); and a plan review fee of 66% of the permit amount for General, Electrical, Mechanical and Plumbing permits with one- and two-family dwellings exempt. That page carries no effective or approval date and names the License and Inspection Department as contact. The two documents disagree on the residential per-square-foot rate, the trade permit amounts and the plan review basis. The dated adopted schedule is used above; a human should confirm which governs. | CONFLICT OPENED 2026-09-12 (lane B run 814), NOT RESOLVED, FIGURES UNCHANGED: three official Augusta sources publish three different residential building rates. The cited Building Division Fee Schedule (DocumentCenter/View/19493, approval date January 7, 2025) gives $0.24 per square foot under roof and $72.00 flat electrical/mechanical trade permits; the live City page augustaga.gov/1112/Permit-Fees gives $0.06 per square foot and $50.00 trade permits with plan review at 66%; and augustaga.gov/DocumentView.aspx?DID=1993 gives $0.048 per square foot and $21.60 trade permits. Our stored figures follow View/19493, which is the schedule the Building Permits page (augustaga.gov/2101) currently links, so it is the newest and the departmentally-endorsed one - but the other two remain live on the City site and were not withdrawn. Protocol forbids picking one; both alternate readings are recorded here and the row is reported for human resolution. The 2026 Residential Packet (View/21801) was also read in full and contains no fee schedule.

Source: published fee schedule · Verified 11/4/2026

Fence Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

How this jurisdiction calculates the fee

Augusta-Richmond County publishes no fence permit fee, and the search for one is closed rather than open. Most fences do not require a building permit in Augusta, so no fee attaches: the city's Planning and Zoning FAQ states that most fences do not require a building permit, the When Permits are Required page does not list fences among the work that requires a building permit, and the Building Division Fee Schedule approved January 7, 2025 - the document that prices every other permit type in Augusta - contains no fence line item in either its residential or its commercial sections. Where a fence is in one of the three Historic Districts, Historic Preservation Commission approval is required instead of, and separately from, a building permit; the fee schedule prices no such approval either.

Source: published fee schedule · Verified 8/12/2026

Reroof Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

Residential roof, general repair or foundation permit
$125.00 flat fee
see rule
○Commercial or multi-family roofing, construction cost up to $15,000.00
Flat fee $100.00
$100.00
○Commercial or multi-family roofing, construction cost $15,001.00 to $25,000.00
Flat fee $155.00
$155.00
○Commercial or multi-family roofing, construction cost $25,001.00 to $50,000.00
Flat fee $310.00
$310.00
○Commercial or multi-family roofing, construction cost $50,001.00 to $75,000.00
Flat fee $465.00
$465.00
○Re-inspection
Flat fee $50.00
$50.00
How this jurisdiction calculates the fee

Augusta-Richmond County Building Division Fee Schedule, approval date January 7, 2025. Residential re-roofing falls under the addition/alteration/general repairs section, which charges roofing, general repair and foundation work at a single flat fee regardless of project size. Commercial and multi-family roofing is charged instead from a construction-cost tier table. CONFLICT BETWEEN TWO OFFICIAL AUGUSTA SOURCES, RECORDED NOT RESOLVED (found 2026-09-07): the figures above are from the Building Division Fee Schedule PDF (DocumentCenter/View/19493), approval date January 7, 2025. Augusta also currently publishes, at augustaga.gov/1112/Permit-Fees under Departments > Planning & Development > Building/Construction > Permit Information, an undated residential schedule stating Building $.06 per square foot under roof; Electrical, Mechanical and Plumbing $50.00 each per house; Fireplace $8.00 each; inspection fee per house $238.00 on crawl space (14 inspections at $17.00) or $255.00 on slab (15 inspections at $17.00); and a plan review fee of 66% of the permit amount for General, Electrical, Mechanical and Plumbing permits with one- and two-family dwellings exempt. That page carries no effective or approval date and names the License and Inspection Department as contact. The two documents disagree on the residential per-square-foot rate, the trade permit amounts and the plan review basis. The dated adopted schedule is used above; a human should confirm which governs. | CONFLICT OPENED 2026-09-12 (lane B run 814), NOT RESOLVED, FIGURES UNCHANGED: three official Augusta sources publish three different residential building rates. The cited Building Division Fee Schedule (DocumentCenter/View/19493, approval date January 7, 2025) gives $0.24 per square foot under roof and $72.00 flat electrical/mechanical trade permits; the live City page augustaga.gov/1112/Permit-Fees gives $0.06 per square foot and $50.00 trade permits with plan review at 66%; and augustaga.gov/DocumentView.aspx?DID=1993 gives $0.048 per square foot and $21.60 trade permits. Our stored figures follow View/19493, which is the schedule the Building Permits page (augustaga.gov/2101) currently links, so it is the newest and the departmentally-endorsed one - but the other two remain live on the City site and were not withdrawn. Protocol forbids picking one; both alternate readings are recorded here and the row is reported for human resolution. The 2026 Residential Packet (View/21801) was also read in full and contains no fee schedule.

Source: published fee schedule · Verified 11/4/2026

Retaining Wall Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

Residential retaining wall less than 8 feet
$100.00 plus $0.20 per linear foot
see rule
Residential retaining wall over 8 feet
$200.00 plus $0.20 per linear foot
see rule
Retaining wall plan review
$100.00 flat fee
see rule
○Commercial or multi-family retaining wall, construction cost up to $15,000.00
Flat fee $100.00
$100.00
○Commercial or multi-family retaining wall, construction cost $15,001.00 to $25,000.00
Flat fee $155.00
$155.00
○Commercial or multi-family retaining wall, construction cost $25,001.00 to $50,000.00
Flat fee $310.00
$310.00
○Commercial or multi-family retaining wall, construction cost $50,001.00 to $75,000.00
Flat fee $465.00
$465.00
○Re-inspection
Flat fee $50.00
$50.00
How this jurisdiction calculates the fee

Augusta-Richmond County Building Division Fee Schedule, approval date January 7, 2025. Residential retaining walls are a named line item, charged as a flat base plus a per-linear-foot rate, with the base doubling for walls over 8 feet tall. A separate flat plan review fee applies to retaining walls. Commercial retaining walls are charged from the construction-cost tier table. CONFLICT BETWEEN TWO OFFICIAL AUGUSTA SOURCES, RECORDED NOT RESOLVED (found 2026-09-07): the figures above are from the Building Division Fee Schedule PDF (DocumentCenter/View/19493), approval date January 7, 2025. Augusta also currently publishes, at augustaga.gov/1112/Permit-Fees under Departments > Planning & Development > Building/Construction > Permit Information, an undated residential schedule stating Building $.06 per square foot under roof; Electrical, Mechanical and Plumbing $50.00 each per house; Fireplace $8.00 each; inspection fee per house $238.00 on crawl space (14 inspections at $17.00) or $255.00 on slab (15 inspections at $17.00); and a plan review fee of 66% of the permit amount for General, Electrical, Mechanical and Plumbing permits with one- and two-family dwellings exempt. That page carries no effective or approval date and names the License and Inspection Department as contact. The two documents disagree on the residential per-square-foot rate, the trade permit amounts and the plan review basis. The dated adopted schedule is used above; a human should confirm which governs. | CONFLICT OPENED 2026-09-12 (lane B run 814), NOT RESOLVED, FIGURES UNCHANGED: three official Augusta sources publish three different residential building rates. The cited Building Division Fee Schedule (DocumentCenter/View/19493, approval date January 7, 2025) gives $0.24 per square foot under roof and $72.00 flat electrical/mechanical trade permits; the live City page augustaga.gov/1112/Permit-Fees gives $0.06 per square foot and $50.00 trade permits with plan review at 66%; and augustaga.gov/DocumentView.aspx?DID=1993 gives $0.048 per square foot and $21.60 trade permits. Our stored figures follow View/19493, which is the schedule the Building Permits page (augustaga.gov/2101) currently links, so it is the newest and the departmentally-endorsed one - but the other two remain live on the City site and were not withdrawn. Protocol forbids picking one; both alternate readings are recorded here and the row is reported for human resolution. The 2026 Residential Packet (View/21801) was also read in full and contains no fee schedule.

Source: published fee schedule · Verified 11/4/2026

Shed Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Residential accessory structure (shed or utility building), building permit
$0.24 x 2,000 = $480.00
$480.00
○Re-inspection
Flat fee $50.00
$50.00
○Permit renewal or extension, residential
Flat fee $72.00
$72.00
How this jurisdiction calculates the fee

Augusta-Richmond County Building Division Fee Schedule, approval date January 7, 2025. Accessory structures are named in the residential new construction section and are charged at the same per-square-foot-under-roof rate as a new dwelling, rather than at a flat shed fee. CONFLICT BETWEEN TWO OFFICIAL AUGUSTA SOURCES, RECORDED NOT RESOLVED (found 2026-09-07): the figures above are from the Building Division Fee Schedule PDF (DocumentCenter/View/19493), approval date January 7, 2025. Augusta also currently publishes, at augustaga.gov/1112/Permit-Fees under Departments > Planning & Development > Building/Construction > Permit Information, an undated residential schedule stating Building $.06 per square foot under roof; Electrical, Mechanical and Plumbing $50.00 each per house; Fireplace $8.00 each; inspection fee per house $238.00 on crawl space (14 inspections at $17.00) or $255.00 on slab (15 inspections at $17.00); and a plan review fee of 66% of the permit amount for General, Electrical, Mechanical and Plumbing permits with one- and two-family dwellings exempt. That page carries no effective or approval date and names the License and Inspection Department as contact. The two documents disagree on the residential per-square-foot rate, the trade permit amounts and the plan review basis. The dated adopted schedule is used above; a human should confirm which governs. | CONFLICT OPENED 2026-09-12 (lane B run 814), NOT RESOLVED, FIGURES UNCHANGED: three official Augusta sources publish three different residential building rates. The cited Building Division Fee Schedule (DocumentCenter/View/19493, approval date January 7, 2025) gives $0.24 per square foot under roof and $72.00 flat electrical/mechanical trade permits; the live City page augustaga.gov/1112/Permit-Fees gives $0.06 per square foot and $50.00 trade permits with plan review at 66%; and augustaga.gov/DocumentView.aspx?DID=1993 gives $0.048 per square foot and $21.60 trade permits. Our stored figures follow View/19493, which is the schedule the Building Permits page (augustaga.gov/2101) currently links, so it is the newest and the departmentally-endorsed one - but the other two remain live on the City site and were not withdrawn. Protocol forbids picking one; both alternate readings are recorded here and the row is reported for human resolution. The 2026 Residential Packet (View/21801) was also read in full and contains no fee schedule.

Source: published fee schedule · Verified 11/4/2026

Water Heater Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

Stand-alone residential plumbing trade permit
$72.00 flat fee
see rule
Plumbing permit taken with new residential construction or an addition/alteration
$72.00 flat fee
see rule
Mechanical permit, residential
$72.00 flat fee, plus $25.00 for each additional unit or system
see rule
Commercial plumbing permit
$125.00 flat fee
see rule
○Re-inspection
Flat fee $50.00
$50.00
How this jurisdiction calculates the fee

Augusta-Richmond County Building Division Fee Schedule, approval date January 7, 2025. A water heater replacement is plumbing work and is charged as a flat-rate plumbing trade permit; the schedule prices plumbing as a flat fee whether taken stand-alone, with a new house, or as part of an addition or alteration. A gas-fired unit additionally involves the mechanical trade, which is charged at its own flat rate. CONFLICT BETWEEN TWO OFFICIAL AUGUSTA SOURCES, RECORDED NOT RESOLVED (found 2026-09-07): the figures above are from the Building Division Fee Schedule PDF (DocumentCenter/View/19493), approval date January 7, 2025. Augusta also currently publishes, at augustaga.gov/1112/Permit-Fees under Departments > Planning & Development > Building/Construction > Permit Information, an undated residential schedule stating Building $.06 per square foot under roof; Electrical, Mechanical and Plumbing $50.00 each per house; Fireplace $8.00 each; inspection fee per house $238.00 on crawl space (14 inspections at $17.00) or $255.00 on slab (15 inspections at $17.00); and a plan review fee of 66% of the permit amount for General, Electrical, Mechanical and Plumbing permits with one- and two-family dwellings exempt. That page carries no effective or approval date and names the License and Inspection Department as contact. The two documents disagree on the residential per-square-foot rate, the trade permit amounts and the plan review basis. The dated adopted schedule is used above; a human should confirm which governs. | CONFLICT OPENED 2026-09-12 (lane B run 814), NOT RESOLVED, FIGURES UNCHANGED: three official Augusta sources publish three different residential building rates. The cited Building Division Fee Schedule (DocumentCenter/View/19493, approval date January 7, 2025) gives $0.24 per square foot under roof and $72.00 flat electrical/mechanical trade permits; the live City page augustaga.gov/1112/Permit-Fees gives $0.06 per square foot and $50.00 trade permits with plan review at 66%; and augustaga.gov/DocumentView.aspx?DID=1993 gives $0.048 per square foot and $21.60 trade permits. Our stored figures follow View/19493, which is the schedule the Building Permits page (augustaga.gov/2101) currently links, so it is the newest and the departmentally-endorsed one - but the other two remain live on the City site and were not withdrawn. Protocol forbids picking one; both alternate readings are recorded here and the row is reported for human resolution. The 2026 Residential Packet (View/21801) was also read in full and contains no fee schedule.

Source: published fee schedule · Verified 11/2/2026

See the full write-up: Augusta building permit cost

Estimate only.Fee schedules change, and building departments set the final valuation and decide which fees apply to your scope. Confirm with the jurisdiction before budgeting. Lines marked “see rule” could not be computed from the published wording and are shown verbatim rather than guessed.