New Orleans, Louisiana Building Permit Cost Calculator
Estimates permit cost in New Orleans from the city's own published fee schedule — not a national average. Every figure is computed from a rule quoted verbatim from that document, and rules that cannot be computed honestly are shown as the published text instead of a number.
217 jurisdictions with fee schedules on file
Total cost of work, labor and materials
Used by cities that price per square foot
Fences and retaining walls
Electrical permits priced by the ampere
Building Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Building permit fee $60.00 base plus $5.00 x 250 = $1,310.00 | $1,310.00 |
○Plan review fee, when plans are required $1.00 x 250 = $250.00 | $250.00 |
○Minimum plan review fee Flat fee $60.00 | $60.00 |
Property within a local historic district 50% surcharge on the permit fee | see rule |
Ordinary construction begun before a building permit is obtained two (2) times the building permit price plus the regular permit fees | see rule |
Demolition begun before a permit is obtained five (5) times the permit price or 10% of the assessed value of the building, whichever is greater | see rule |
How this jurisdiction calculates the fee
The building permit fee is calculated from the market value of the work to be performed, with an added plan review fee when plans are required and a surcharge for property in a local historic district.
Source: published fee schedule · Verified 10/30/2026
Deck Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Building permit fee $60.00 base plus $5.00 x 250 = $1,310.00 | $1,310.00 |
○Plan review fee, when plans are required $1.00 x 250 = $250.00 | $250.00 |
Property within a local historic district 50% surcharge on the permit fee | see rule |
How this jurisdiction calculates the fee
A deck that exceeds the exemption thresholds is permitted as building work, and the fee is calculated from the market value of the work to be performed.
Source: published fee schedule · Verified 11/13/2026
Electrical Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
Application fee plus circuits and service amperage $40 application fee plus $3 per new circuit plus $0.30 per service amperage | see rule |
○Construction loop Flat fee $40.00 | $40.00 |
○Elevator, moving stair, dumbwaiter or man lift installation or modification Flat fee $60.00 | $60.00 |
○Sign, indoors or outdoors Flat fee $40.00 | $40.00 |
How this jurisdiction calculates the fee
Electrical permit fees combine an application fee with per-unit charges based on the complexity of the work, including service amperage, new service connections and number of circuits.
Source: published fee schedule · Verified 10/1/2026
Fence Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Building permit fee $60.00 base plus $5.00 x 250 = $1,310.00 | $1,310.00 |
○Plan review fee, when plans are required $1.00 x 250 = $250.00 | $250.00 |
Property within a local historic district 50% surcharge on the permit fee | see rule |
How this jurisdiction calculates the fee
A fence that exceeds the exemption thresholds is permitted as building work, and the fee is calculated from the market value of the work to be performed.
Source: published fee schedule · Verified 10/30/2026
Reroof Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Base Fee Flat fee $60.00 | $60.00 |
Historic Districts (HDLC and VCC) +$30 | see rule |
How this jurisdiction calculates the fee
The residential re-roofing permit carries a flat base fee, with an additional amount for properties in a historic district.
Source: published fee schedule · Verified 11/11/2026
Retaining Wall Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Building permit fee $60.00 base plus $5.00 x 250 = $1,310.00 | $1,310.00 |
○Plan review fee, when plans are required $1.00 x 250 = $250.00 | $250.00 |
Property within a local historic district 50% surcharge on the permit fee | see rule |
How this jurisdiction calculates the fee
A retaining wall over three feet in height is permitted as building work, and the fee is calculated from the market value of the work to be performed.
Source: published fee schedule · Verified 10/29/2026
Shed Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Accessory Structure permit fee $60.00 base plus $5.00 x 250 = $1,310.00 | $1,310.00 |
○Plan review fee, when plans are required $1.00 x 250 = $250.00 | $250.00 |
Property within a local historic district subject to VCC or HDLC regulation 50% surcharge on the permit fee | see rule |
How this jurisdiction calculates the fee
An Accessory Structure permit fee is calculated from the value of the work to be performed, with an added plan review fee when plans are required and a surcharge for property in a local historic district.
Source: published fee schedule · Verified 11/2/2026
Water Heater Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Water heaters through 50K BTU, per unit Flat fee $20.00 | $20.00 |
○Water heaters 51K to 200K BTU, per unit Flat fee $25.00 | $25.00 |
100 ft. gas line and five outlets $15 entry only | see rule |
○Each additional outlet over 5 outlets Flat fee $1.00 | $1.00 |
○Each additional 100 ft. or part thereof over 1st 100 ft. gas line Flat fee $12.00 | $12.00 |
How this jurisdiction calculates the fee
Water heaters are itemized on the Mechanical Gas Permit Application, Supplement D.2, and are charged per unit by BTU rating; gas, electric, heat pump and geothermal water heaters are all listed.
Source: published fee schedule · Verified 11/2/2026
See the full write-up: New Orleans building permit cost
Estimate only.Fee schedules change, and building departments set the final valuation and decide which fees apply to your scope. Confirm with the jurisdiction before budgeting. Lines marked “see rule” could not be computed from the published wording and are shown verbatim rather than guessed.