Estimates permit cost in Portland from the city's own published fee schedule — not a national average. Every figure is computed from a rule quoted verbatim from that document, and rules that cannot be computed honestly are shown as the published text instead of a number.
217 jurisdictions with fee schedules on file
Total cost of work, labor and materials
Used by cities that price per square foot
Fences and retaining walls
Electrical permits priced by the ampere
Building Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
Total value of construction work $1 - $500 $167.00 Minimum Fee | see rule |
Total value of construction work $501 - $2,000 $167.00 for the first $500, plus $3.59 for each additional $100 or fraction thereof up to and including $2,000 | see rule |
Total value of construction work $2,001 - $25,000 $220.85 for the first $2,000, plus $13.91 for each additional $1,000 or fraction thereof up to and including $25,000 | see rule |
Total value of construction work $25,001 - $50,000 $540.78 for the first $25,000, plus $10.26 for each additional $1,000 or fraction thereof up to and including $50,000 | see rule |
Total value of construction work $50,001 - $100,000 $797.28 for the first $50,000, plus $6.81 for each additional $1,000 or fraction thereof up to and including $100,000 | see rule |
○Total value of construction work $100,001 and up $1,137.78 for the first $100,000.00, plus 150 x $5.63 for $150,000.00 over (rounded up per "or fraction thereof") = $1,982.28 | $1,982.28 |
Plan Review/Process Fee for the original submittal, maximum of 2 allowable checksheets · add-on 65% of the building permit fee — select the permit fee line above to calculate | see rule |
Development Services Fee - Residential, total value of construction work $1 - $500 $21.19 Minimum Fee | see rule |
○Zoning Permit Fee for 1 & 2 Family Dwellings Flat fee $48.00 | $48.00 |
○Zoning Inspection Fee for 1 & 2 Family Dwellings Flat fee $125.00 | $125.00 |
○Reinspection Fee - fee charged per inspection Flat fee $167.00 | $167.00 |
○Requested Inspection Fee, One and Two-Family Dwellings Flat fee $252.00 | $252.00 |
How this jurisdiction calculates the fee
Building permit fees are based on the total value of construction work to be performed, using the tiered fee table in the Building and Other Permits Fee Schedule, with a plan review fee of 65 percent of the permit fee and separate Development Services, zoning and trade permit fees.
Source: published fee schedule · Verified 9/18/2026
Deck Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Building permit fee, minimum (valuation $1-$500) Flat fee $167.00 | $167.00 |
○Building permit fee at $2,000 valuation Flat fee $220.85 | $220.85 |
○Building permit fee at $25,000 valuation Flat fee $540.78 | $540.78 |
○Plan review/process fee at the $167.00 minimum permit fee (65%) Flat fee $108.55 | $108.55 |
○Development Services Fee - Residential, minimum Flat fee $21.19 | $21.19 |
○Zoning inspection fee, one and two family dwellings Flat fee $125.00 | $125.00 |
○Reinspection fee, per inspection Flat fee $167.00 | $167.00 |
How this jurisdiction calculates the fee
Portland Permitting & Development (PP&D) Building and Other Permits Fee Schedule, City of Portland, effective July 10, 2026. A building permit is required for a deck more than 30 inches above grade. There is no flat deck fee: the building permit fee is a tiered function of the total value of construction work - $167.00 minimum for $1-$500; $167.00 plus $3.59 per additional $100 up to $2,000; $220.85 plus $13.91 per additional $1,000 up to $25,000; $540.78 plus $10.26 per additional $1,000 up to $50,000; $797.28 plus $6.81 per additional $1,000 up to $100,000; $1,137.78 plus $5.63 per additional $1,000 above that. Valuation follows OAR 918-050-0100: alterations and repairs use the fair market value of the permitted work, while new construction and additions use the greater of the applicant stated value or a value derived from the ICC building valuation data table (copyrighted, not reproduced here) applied to occupancy, construction type and square footage. Percentage add-ons stack on top: plan review/process fee at 65% of the building permit fee, a State of Oregon surcharge of 12% on building permits, a tiered residential Development Services Fee (minimum $21.19), and a $125.00 zoning inspection fee for one and two family dwellings where planning/zoning review applies. Improvements valued at $100,000 or more also pay the 1% Affordable Housing Construction Excise Tax.
Source: published fee schedule · Verified 11/5/2026
Electrical Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Residential Square Foot Wiring Package, 1,000 square feet or less Flat fee $408.00 | $408.00 |
○Residential Square Foot Wiring Package, each additional 500 square feet or portion thereof Flat fee $93.00 | $93.00 |
○Services or Feeders: Installation, alteration or relocation, 200 amps Flat fee $212.00 | $212.00 |
○Services or Feeders: Installation, alteration or relocation, 201 to 400 amps Flat fee $298.00 | $298.00 |
○Branch circuits with the purchase of service or feeder fee Flat fee $21.00 | $21.00 |
○Branch circuits without the purchase of service or feeder fee, first branch circuit Flat fee $174.00 | $174.00 |
○Renewable Energy: Installation, alteration or relocation, 5 kva or less Flat fee $212.00 | $212.00 |
How this jurisdiction calculates the fee
Residential electrical permit fees are charged either as a square foot wiring package for new work and remodels, or by the individual service, feeder and branch circuit items installed, altered or relocated.
Source: published fee schedule · Verified 9/18/2026
Fence Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Building permit fee, minimum (valuation $1-$500) Flat fee $167.00 | $167.00 |
○Building permit fee at $2,000 valuation Flat fee $220.85 | $220.85 |
○Plan review/process fee at the $167.00 minimum permit fee (65%) Flat fee $108.55 | $108.55 |
○Development Services Fee - Residential, minimum Flat fee $21.19 | $21.19 |
○Zoning permit fee, one and two family dwellings Flat fee $48.00 | $48.00 |
How this jurisdiction calculates the fee
Portland Permitting & Development (PP&D) Building and Other Permits Fee Schedule, City of Portland, effective July 10, 2026. A building permit is required for a wood fence taller than 7 feet, a masonry or concrete fence taller than 4 feet, a woven wire or chain link fence taller than 8 feet, or any fence enclosing a swimming pool; a shorter compliant fence needs no building permit, though a zoning permit may apply ($48.00 for one and two family dwellings). There is no flat fence fee. The building permit fee is a tiered function of the total value of construction work - $167.00 minimum for $1-$500; $167.00 plus $3.59 per additional $100 up to $2,000; $220.85 plus $13.91 per additional $1,000 up to $25,000; and higher tiers above that. Valuation for this kind of work is the fair market value of the permitted work per OAR 918-050-0100. Percentage add-ons stack on top: plan review/process fee at 65% of the building permit fee, a State of Oregon surcharge of 12% on building permits, and a tiered residential Development Services Fee (minimum $21.19).
Source: published fee schedule · Verified 11/2/2026
Reroof Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Re-roof permits, packet of 5 (pre-registered commercial roofing contractors) Flat fee $2,142.00 | $2,142.00 |
○Plan review/process fee for a re-roof packet of 5 Flat fee $359.00 | $359.00 |
○Building permit fee, minimum (valuation $1-$500) Flat fee $167.00 | $167.00 |
○Building permit fee at $25,000 valuation Flat fee $540.78 | $540.78 |
○Plan review/process fee at the $167.00 minimum permit fee (65%) Flat fee $108.55 | $108.55 |
○Development Services Fee - Residential, minimum Flat fee $21.19 | $21.19 |
How this jurisdiction calculates the fee
Portland Permitting & Development (PP&D) Building and Other Permits Fee Schedule, City of Portland, effective July 10, 2026. Most residential reroofing needs no building permit: reroofing with a roofing material of similar weight, including replacement of some or all existing roof sheathing, is exempt. A permit is required to reroof a dwelling in a Wildfire Zone, to reroof a townhouse, or to install building-integrated photovoltaic roof panels. Where a permit is required the fee comes off the general valuation table - $167.00 minimum for $1-$500 of construction value; $167.00 plus $3.59 per additional $100 up to $2,000; $220.85 plus $13.91 per additional $1,000 up to $25,000; and higher tiers above - with valuation set as the fair market value of the permitted work under OAR 918-050-0100. Add-ons stack: plan review/process fee at 65% of the building permit fee, a State of Oregon surcharge of 12%, and a tiered residential Development Services Fee (minimum $21.19). Separately, the schedule prices bulk re-roof permits sold in packets of five to commercial roofing contractors who pre-register with PP&D: $2,142.00 per packet of 5 permits plus a $359.00 plan review/process fee, which works out to $428.40 per permit before the plan review charge.
Source: published fee schedule · Verified 11/5/2026
Retaining Wall Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Building permit fee, minimum (valuation $1-$500) Flat fee $167.00 | $167.00 |
○Building permit fee at $2,000 valuation Flat fee $220.85 | $220.85 |
○Building permit fee at $25,000 valuation Flat fee $540.78 | $540.78 |
○Plan review/process fee at the $167.00 minimum permit fee (65%) Flat fee $108.55 | $108.55 |
○Development Services Fee - Residential, minimum Flat fee $21.19 | $21.19 |
○Zoning permit fee, one and two family dwellings Flat fee $48.00 | $48.00 |
How this jurisdiction calculates the fee
Portland Permitting & Development (PP&D) Building and Other Permits Fee Schedule, City of Portland, effective July 10, 2026. A building permit is required for a retaining wall more than 4 feet high measured from the bottom of the footing to the top of the wall, or for any wall supporting a surcharge (a load beyond level earth backfill); below that a zoning permit may apply ($48.00 for one and two family dwellings), and a separate site development permit may be required on complex sites or where slope stabilization is needed. There is no flat retaining wall fee. The building permit fee is a tiered function of the total value of construction work - $167.00 minimum for $1-$500; $167.00 plus $3.59 per additional $100 up to $2,000; $220.85 plus $13.91 per additional $1,000 up to $25,000; $540.78 plus $10.26 per additional $1,000 up to $50,000; and higher tiers above - with valuation set per OAR 918-050-0100. Add-ons stack: plan review/process fee at 65% of the building permit fee, a State of Oregon surcharge of 12%, and a tiered residential Development Services Fee (minimum $21.19).
Source: published fee schedule · Verified 11/5/2026
Shed Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Zoning permit fee, one and two family dwellings (shed 200 sq ft or under) Flat fee $48.00 | $48.00 |
○Building permit fee, minimum (valuation $1-$500) Flat fee $167.00 | $167.00 |
○Building permit fee at $2,000 valuation Flat fee $220.85 | $220.85 |
○Building permit fee at $25,000 valuation Flat fee $540.78 | $540.78 |
○Plan review/process fee at the $167.00 minimum permit fee (65%) Flat fee $108.55 | $108.55 |
○Development Services Fee - Residential, minimum Flat fee $21.19 | $21.19 |
○Zoning inspection fee, one and two family dwellings Flat fee $125.00 | $125.00 |
How this jurisdiction calculates the fee
Portland Permitting & Development (PP&D) Building and Other Permits Fee Schedule, City of Portland, effective July 10, 2026. A building permit is required for a detached accessory structure over 200 square feet or taller than 15 feet; on parcels over 2 acres the threshold rises to 400 square feet where the structure is at least 20 feet from property lines and other structures. A non-habitable structure of 200 square feet or less needs no building permit, but a zoning permit may be required - $48.00 for one and two family dwellings. Where a building permit is required there is no flat shed fee: the fee is a tiered function of the total value of construction work - $167.00 minimum for $1-$500; $167.00 plus $3.59 per additional $100 up to $2,000; $220.85 plus $13.91 per additional $1,000 up to $25,000; and higher tiers above - with valuation for new construction set under OAR 918-050-0100 as the greater of the applicant stated value or a value derived from the ICC building valuation data table (copyrighted, not reproduced here) applied to occupancy, construction type and square footage. Add-ons stack: plan review/process fee at 65% of the building permit fee, a State of Oregon surcharge of 12%, a tiered residential Development Services Fee (minimum $21.19), and a $125.00 zoning inspection fee for one and two family dwellings, which applies to all new construction.
Source: published fee schedule · Verified 11/5/2026
Water Heater Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Fixture or Item - Water heater Flat fee $63.00 | $63.00 |
○Minimum Fee Flat fee $161.00 | $161.00 |
○Reinspection Fee - per inspection Flat fee $161.00 | $161.00 |
○Requested Inspection Fee, One and Two-Family Dwellings Flat fee $243.00 | $243.00 |
How this jurisdiction calculates the fee
A water heater is charged as a single plumbing fixture under the Plumbing Permit Fee Schedule, subject to the minimum permit fee.
Source: published fee schedule · Verified 9/18/2026