New structural steel and drilled holes for installation of bolts will be measured in accordance with 711.72.
729.17Basis of Payment
New structural steel and drilled holes for installation of bolts will be paid for in accordance with 711.73. The accepted heat straightened steel members will be paid for at the contract lump sum price for straighten steel member. 260 Payment will be made under: Pay Item Pay Unit Symbol
Straighten St eel Member ........................................................... LS The cost for all material, labor, equipm ent, and incidentals for the inspection of the steel members, the temperature verification devices, calibration of the temperature verification devices, grinding, and drilling crack-arrest holes if shown on the plans or 270 directed by the Engineer, shall be included in the cost of straighten steel member. The cost for all NDT activities, including but not limited to all material, equipment, and labor necessary to clean the test areas, perform and interpret NDT, and preparation of all NDT reports shall be included in the cost of straighten steel member.
The cost for all materials, labor, eq uipment, and incidentals necessary for disconnecting, supporting, or adjusting the steel members or secondary steel members, jacks or other augmenting devices, the for ce measurement system, and calibration of the force measurement system sh all be included in the cost of straighten steel member. 280
The cost for all materials, labor, equipment, and incidentals required for existing coating removal, preparing, priming, and painting of the steel members shall be included in the cost of straighten steel member. If the Engineer deems it necessary for the Contractor to perform epoxy injection as outlined above, this extra work will be paid for in accordance with 109.05.
If, as a result of the Contractor’s methods used in the prosecution of the work, the integrity of the steel member has been co mpromised as determined by the Engineer, 290 all costs to remedy the situation up to and including replacing of the steel members and all costs associated with replacing the steel members shall be at no additional cost to the Department.