805.01Description
This work shall consist of furnishing miscellaneous materials, not furnished by the Department, and installing traffic signals in accordance with these specifications and in reasonably close conformance with the lines, grades, and locations shown on the plans or as directed.
MATERIALS
805.02Materials
Materials shall be in acco rdance with the following:
Castings for Handhole ................................................. 910.05(b) Coarse Aggregate, Class E or Higher, Size No. 8 ....... 904.03 Loop Detector Sealant ................................................. 906.02(a) Reinforced Concrete Pipe ............................................ 907.02 Reinforci ng Bars .......................................................... 910.01 805.02
Traffic Signal Materials and Equipment...................... 922 20 Treated Lumber ........................................................... 911.02
The proposed work shall be examined in order to determine what materials not furnished by the Department are required to complete the contract. The Department will furnish only the materials specified on the Department Furnished Materials special provision. If materials to be furnished by the Contractor are listed, the list is only a guide for estimating purposes. All additional materials required to complete an operating installation as specified shall be furnished.
Signal handholes shall be Type I or Type II as shown on the plans. 30
Pedestrian push buttons shall be the type designated in the contract documents, APS or Non-APS.
Joint sealant material shall be compatible with the roadway materials. If polyethylene duct loop wire is used, only sealant in accordance with 906.02(a)1 shall be used.
Timber poles to be furnished shall be in accordance with the current ANSI specifications and dimensions. They shall be of the length and class specified, be fully 40 treated in accordance with 922.10(b), and dry. Minimum circumference at the top and at a point 6 ft from the butt shall be in accordance with ANSI specifications.
Steel strain poles greater than 24 ft in length shall be in accordance with 922.10(a).
The battery cabinet and program timing module for solar powered flashing beacons shall be from the QPL of Traffic Signal and ITS Devices.
CONSTRUCTION REQUIREMENTS
805.03General Requirements
The Contractor shall maintain existing traffic signals in operation until the Engineer determines that the progress of the work necessitates their removal. The new installation shall not interfere with the operation of the existing signal. The work shall proceed in such a manner that the signals are not out of service at any two adjacent intersections at any time. When the operation of an existing traffic signal needs to be interrupted before the new signal is placed in operation, the traffic shall be controlled at all times. The work shall be scheduled so that the interruption is limited to a minimum amount of time and at off peak hours. The new span and catenary installation shall not interfere with the operation of the existing traffic signal. Traffic shall be 60 controlled at all times during the changeover when the existing traffic signal is turned off and the new signal is turned on. This changeover shall take place such that the interruption is limited to a minimum amount of time.
805.03
When directed, temporary stop signs shall be erected at the intersection. When no work is in progress, the intersection shall have at least two operating signal faces for each approach. When the new installati ons are completed, all existing signal equipment and materials including timber poles, steel poles, and cast-iron handhole rings and covers which have not been used in the new installation shall be carefully removed. Regardless of the right to materials found on the project, as set out in other 70 sections of these specifications, items designated in the contract documents, and field identified by the Department, as traffic signal equipment to be salvaged by the Department or local unit of government shall be stored at a secure site until such time as it is transported to the designated location, when designated as a pay item, or salvaged by the Department or local unit of government. The Contractor shall verify that the field identification placed by the Department has not been removed by vandalism or natural causes. If the Contractor has reason to believe that field identifications have been removed, the Department shall be contacted. The Contractor shall be responsible for all damage or loss of this equipment and shall repair or replace the damaged or lost equipment as directed. All signal equipment removed and not 80 designated to be salvaged shall become the property of the Contractor and shall be disposed of in accordance with 202.
All existing painted metallic signal equipment to be reused, such as pedestals, bases, controller cabinets, signal weatherheads, pipe arms, shall be cleaned and painted with two coats of highway yellow enamel in accordance with 909.02(c). Existing metallic signal heads to be reused shall be painted with two coats of black or highway yellow enamel as directed by the Engineer and in accordance with 909.02(c). Aluminum poles and signal support structures shall not be painted.
Existing concrete foundations, which have not been used in the new installation, shall be removed to a minimum of 4 in. below the adjacent grade. The openings shall be filled with concrete and the surface finished and broomed, if they are located in sidewalk areas. Otherwise, they shall be filled with acceptable material conforming with the surrounding area.
Existing signal handholes to be removed, shall be filled after removing rings and covers, with B borrow with a minimum of 4 in. of concrete on top to bring it up to grade in a sidewalk area. Surfaces shall be finished and broomed. Otherwise, they shall be filled with acceptable material conforming with the surrounding area. 100
The signal controller timings will be provided and the Engineer shall be present when the signal intersection is to be placed in operation.
All electrical wiring terminations and splices; controller and cabinet set-up; and testing, review, and turn-on of all operational apparatus at each location shall be done by or in the presence of and under the responsible charge of an employee of the Contractor who holds an IMSA Traffic Signal Construction Technician Level II certification or an IMSA Traffic Signal Fi eld Technician Level II certification. Installation inspections, troubleshooting, maintenance and repair of these systems 110 805.03
shall be accomplished by, or in the presence of and under the responsible charge of, an employee of the Contractor who holds an IMSA Traffic Signal Construction Technician Level II certification. Supervision of non-electrical, traffic signal related construction work and traffic control shall be done by a person holding, at a minimum, an IMSA Work Zone Temporary Traffic Control Technician certification or an equivalent certification approved by the Department.
Before starting work, the Contractor shall provide the names of the Level II Traffic Signal Construction Technicians, the Level II Traffic Signal Field Technicians, and Work Zone Temporary Traffic Control Technicians who have been assigned to 120 perform signal related work, and a photocopy of each such person’s certification card. If the Level II Traffic Signal Construction, or Field Technicians, or Work Zone Temporary Traffic Control Technicians are dismissed from the work, all signal related work requiring such certified personnel on th e project site shall cease until the names and photocopies of certification cards for replacement personnel are provided to the Engineer.
Electrical work shall be executed in accordance with the requirements of the National Board of Fire Underwriters, the St ate Fire Marshal, and the power company which will furnish the electric service. The work shall be in accordance with any local 130 regulations that may apply. The Department will arrange and provide for power service which the power company will bring to the point designated on the plans. Prior to the start of construction, the schedule of activities shall be coordinated with the power company and they shall be contacted again at least 14 days prior to the time the service work is to be completed.
The Department will obtain permits from local officials, companies, or individuals for the use of poles, right-of-way, or other property incidental to the installation of traffic signal. Although entering into the contract implies permission and authority to cut into and push under pavement, sidewalks, and alleys, any damage 140 to underground utilities or inte rruption of such service sh all be the responsibility of the Contractor. The Contractor shall be in accordance with local regulations as well as
107.08. Protective devices shall be in accordance with 107.12 and 801
The location of signal heads, controllers, signal poles, signal cantilever structures, detector housing, disconnect hangers, and other installation items will be shown on the plans. However, a change in the location of an item may be ordered during the progress of the work. The work shall be completed as shown on the plans except for those changes specifically authorized in writing.
Flashing beacons shall flash at a rate for each beacon of 50 to 60 times per minute with the illuminated period from 1/2 to 2/ 3 of the total cycle. Second beacons, if specified, shall flash alternately with the exception of intersection control beacons which shall flash simultaneously.
805.04Pole Installation
Working drawings for strain poles or cantilever structures shall be provided in 805.04
accordance with 105.02. Metal poles shall be erected on concrete foundations and shall be reasonably plumb after installation of signal heads. The handhole side of the pole shall be at right angles to the direction of the signal cantilever arm or span, catenary, 160 and tether. Signal cables shall be brought up inside the poles. Any steel pole, signal cantilever arm, or hardware not galvanized shall be painted with structural steel coating system in accordance with 619.09(a). The surface shall be prepared in accordance with 619.08(a) and 619.08(d). Pain t shall be applied in accordance with 619. All rust, scale, and dirt shall be cl eaned from the metal surface so that paint adheres to the surface.
The construction of concrete foundations shall be in accordance with 805.13. Timber poles shall be set a minimum of 7 ft in the ground and raked 12 in.
805.05Placing Signal Heads
Signal cantilever arm and span mounted signal heads shall have 17.5 ft minimum and 22.5 ft maximum clearance over the road way unless there are visual obstructions which require lowering the signal head. A signal head over the roadway shall not have a clearance of less than 15 ft. Such signal h eads shall be located over the intersection as shown on the plans. Such signal heads shall have a uniform clearance, which will be determined. Signal heads not mounted over a paved roadway, on the top or side of a pole, shall not be less than 10 ft or more than 15 ft above the sidewalk or, if none, above the pavement grade at the center of th e roadway. Signal faces shall be directed to the proper approach lane in each direction. Flasher signal faces that supplement 180 signs shall be mounted with the bottom of the housing at not less than 3 ft or more than 13 ft above the edge of pavement. Flasher signal faces that supplement signs shall be directed towards oncoming traffic. Pedestrian signal faces shall be mounted with
the bottom of the housing at not less than 7 ft or more than 10 ft above the sidewalk.
The pedestrian signal shall be in line with the pedestrian’s vision at the appropriate
crosswalk being used. Pedestrian push-buttons shall be mounted at a height of 3 1/2 to
4 ft above the sidewalk as shown on the plans. A pedestrian actuated signal sign shall
be mounted immediately above the push-button.
Signal heads shall be assembled and wired with one conductor, Type THW,190
stranded wire. Where splices are made, a 2 ft minimum length of cable or wire in
excess of that required for a continuous run shall be provided. Splices shall be twisted
together and soldered or approved type connectors used. Each splice shall be
completely insulated by wrapping with an approved tape and sealed with an approved
electrical coating material. Splices shall be made in such manner that the connections
are moisture proof. The cables coming out of the signal weatherhead shall be looped
to form a drip loop. The drip loop shall be made so that the cables coming out of the
weatherhead loop down below the elevation of the weatherhead to prevent water from
following the cable into the weatherhead. If used, the splice indicated above shall be
located in the top of the coils of cable forming the drip loop.200
Except for signal heads installed on existing traffic signal cantilever structures, all
overhead signal heads shall have backplates, unless otherwise indicated on the plans.
Backplates shall not be cut or altered upon installation.
805.05
914
Signal heads shall not be installed until all other work has been completed. If it
becomes necessary to mount signal heads for more than 2 h before the lights are to be
turned on, the signal heads shall be hooded by placing sacks or similar cover over them
so as to conceal them from traffic. Hooded signal heads are not allowed to be in place
for more than five days. No signal head shall be left over night with the lights out210
unless it is hooded. Signal heads shall be securely mounted. The polycarbonate signal
face shall be used only when securely supported on both ends of the assembly. In a
span cable installation, a tether cable would satisfy this requirement.
When installing push buttons with accessible pedestrian signals, APS, features the
Contractor shall verify that the audible tone is discernible from the mid-point of the
crosswalk.
805.06Grounding
All signal supports, signal controller supports, and entrance switches shall be220
grounded in accordance with the applicable requirements of 807.12.
805.07Wire and Cable Installations
All cable runs attached to utility poles shall have code clearance relative to utility
cables. They shall be no less than 18 ft above the ground level except over railroad
tracks when a minimum of 27 ft clearance shall be maintained. All cable runs shall be
installed in continuous lengths without splices between terminals except when
necessary at handholes, junction boxes, pole signal bases, and pedestal bases. The type
of cable and the number of conductors as well as the gauge shall be as shown on the
plans unless otherwise specified.230
Cable rings shall be used to support the signal cable on the signal span cable. They
shall be spaced 12 in. on center. Cable shall be pulled through the conduit to the
terminal panel in the controller cabinet. Caution shall be used to prevent damage to
the cable when it is being pulled through conduit.
Coded cable conductors shall be used throughout the installation. Cable
conductors shall be tagged at all detector housings, handholes, signal pole bases, and
controller cabinets. At the ends of each cable, the tag shall be placed between 4 and 8
in. from the end of the wire and on the outer jacket. At all other locations, the tag shall240
be placed in the middle of the length of cable stored at the location. The tag shall be
1/2 in. wide, thermal printed black on yellow or black on white, polyester or nylon
tape with permanent adhesive and shall be water, chemical and scratch resistant. The
font shall be arial, size 10px. Tags shall be installed flag style around the cable with
the backs of the tag ends placed together. Tags shall identify the cables by their use.
The following are the uses which shall be indicated by the tags:
805.06
915
Signal cables shall be tagged to identify the direction of travel. Detector lead-in
cables shall be tagged throughout the installation with the corresponding loop tag
information.
The tagging material and fastening will be subject to approval prior to proceeding
with this work. The color coded wires shall be connected properly. The white wire260
shall be the common or ground. Wire used for all identical indications of any
individual phase shall be color coded and, where possible, shall use red wire to connect
red lenses, orange wire to connect yellow lenses, and green wire to connect green
lenses. Signal heads shall be assembled and wired before being installed. The testing
of the loops shall be documented in the Loop Testing Table provided by the State.
805.08Controller Cabinet, Signal Service, and Detector Housing
Installation
Three document packets shall be prepared in accordance with 922.02(b) for each
cabinet. Each packet shall be labeled with the name of the contract number, the270
intersection, the commission number of the signal, and the date of installation. One
paper packet shall be placed in the cabinet, one paper packet shall be submitted to the
Engineer, and one electronic packet shall be submitted to the Asset Manager in the
Department’s Traffic Management Division within two days after the signal is turned
on. Information in the packets shall include all approved changes to the signal
installation. All detector loop lead-in tags and detector rack labels shall reflect all
approved changes to the signal installation.
Additional detector loop amplifier units and detector racks shall be supplied as
directed by the Engineer. Additional detector racks shall include all cables or harnesses280
including, but not limited to a SDLC cable for each added rack, interface panels and a
BIU to provide a complete and functional installation. Additional auxiliary BIU panels
shall include all cables or harnesses including, but not limited to a SDLC cable for
each additional auxiliary BIU panel, terminal strip on BIU panel and BIU to provide
a complete and functional installation.
For signal cabinets installed by the Contractor, where no detector loop or lead-in
work is included in the contract, the Contractor shall perform detector loop tagging,
testing, and vehicle simulator testing in accordance with 805.09, only to the extent of
documenting the test readings and confirming that all existing detector loops are290
connected correctly and all detector related equipment in the cabinet is operating
correctly.
The controller cabinet shall be mounted securely on a pole, pedestal, or concrete
foundation. All cabinets on concrete foundations shall be installed with the anchor
bolts inside. Controller cabinets on poles or pedestals shall be mounted at a height of
805.08
916
38 in. ±2 in. Pole mounted controller cabinets shall be fastened with two stainless steel
bands as shown on the plans. Signal cables and lead-in cable shall be run in conduit
from the controller cabinet to the signal support base and to detector housing as
indicated on the plans. Galvanized steel elbows shall be used on the detector housing300
as shown on the plans.
The Contractor shall wire the entrance switch and bring service cable up the riser
and out the weatherhead and leave 4 ft of cable outside the weatherhead. The utility
company, at their option, may bring the service cables to the load side of the entrance
switch. Meter bases, if required, shall be obtained from the power company.
A minimum of 12 in. and a maximum of 18 in. of loop wire duct will be allowed
in the detector housing for each loop lead. Concrete used in the installation of detector
housings shall be in accordance with 506.04(a), except 506.05 will not apply and310
calcium chloride shall not be used. A CMDS in accordance with 506.03 shall be
submitted, however, utilization of the Department provided spreadsheet is not
required. Where a portion of the road is closed or where there is no vehicular traffic,
then class A concrete in accordance with 702 may be used. The concrete shall be
placed flush with existing surface and shall be covered with a steel plate during the
setting time.
805.09Loop Wire Detector Installation
This work shall consist of placement and testing of loop wire detectors in
accordance with the installation details shown on the plans.320
The number, size, arrangement, and locations of loops shall be as shown on the
plans except that loop spacing shall be adjusted to avoid PCCP joints. Loops shall be
of a regular octagon shape with sides of 2 1/2 ft in length or a circular shape with a
diameter of 6 ft. Loops placed longitudinally adjacent in the same lane shall be spaced
15 ft from the center of one loop to the center of the next loop. Loops shall be arranged
so that no loop wire will be bent at an angle less than 120°. Regardless of
configuration, the loop installation shall match the intention of the loop tagging table.
330
Prior to installation, loop layout shall be approved in writing by the District
Traffic Engineer. The Contractor shall notify the District Traffic Engineer a minimum
of two business days prior to the date that loop layout approval is required. All
roadway centerlines, edge-lines and stop-bars pertinent to loop layout shall be
accurately and clearly identified at the time loop layouts are reviewed for approval.
An outline shall be painted where the loops are to be placed. The Contractor shall
ensure that the final installed location of each loop matches the intention and
functionality of the approved layout for loop spacing, lane width and geometry.
All loops and lead-in cables shall be tagged according to the plans and 805.07.
805.09
917
The slots shall be saw cut as shown on the plans. A diamond cutting blade shall
be used for sawing all loops. All saw-cut loops shall have individual saw cuts to the
detector housing. Joints shall be overlapped such that the saw cut at the corner is full
depth. Prior to installing roadway loop wire in the roadway saw-cuts, the saw-cuts
shall be cleaned in accordance with the manufacturer’s requirements for the joint
sealant to be used. After proper cleaning, the loop wire shall be installed. All loops
shall be wired clockwise as viewed from above. Loops shall be wired with four turns
or as specified then gently tamped with a blunt non-metallic tool. Backer rod 2 to 4 in.350
in length shall be spaced every 12 in. around the saw-cut above the wire and gently
tamped to hold the loop wire snug in the bottom of the saw-cut. Backer rod shall not
be continuous around the saw-cut.
After installation of the loop wire, the saw-cut shall be sealed with a joint sealant
material. The sealant shall be poured into the saw-cut making a water tight seal. The
joint sealant material shall be installed in accordance with the manufacturer’s
recommendations and 906.02. However, the joint configuration shall not apply. A
copy of the sealant manufacturer’s written application instructions shall be submitted
to the Engineer prior to any sealant operations. If the Contractor elects to use a sealant360
complying with 906.02(a)2, the sealant material shall be heated in a kettle or melter
constructed as a double boiler with the space between the inner and outer shells filled
with oil or other heat-transfer medium. This melter shall have a positive temperature
control and a mechanical agitator.
A backer rod shall be used for both cold applied sealants and hot poured sealants.
The sealant material shall fill the saw-cut as shown on the plans. All excess joint
sealant on the pavement surfaces shall be promptly removed.
The black lead-in wire shall be spliced to the loop wire which goes back to the370
field. Such wire shall be tagged as “Out/Loop (No.)”. The white lead-in wire shall be
spliced to the loop wire which comes in from the field. Such wire shall be tagged as
“In/Loop (No.)”.
For each loop cable and lead-in cable entering a handhole, there shall be 6 ft of
cable jacket remaining on each wire after the splice is complete. For each loop cable
and lead-in cable entering a detector housing, there shall be 2 ft of cable jacket
remaining on each wire after the splice is complete.
380
For all loop splices, there shall be a maximum of 1/2 in. of non-jacketed wire
measured from the end of each cable jacket to the edge of the splice waterproofing
material. The splice of the loop wire and lead-in cable shall be soldered and
waterproofed at the detector housing or handhole. Waterproofing shall consist of the
use of heat shrink tubing which has an internal coating sealant material. The heat
shrink tubing shall not be heated by means of a direct flame tool.
All testing and acceptance procedures performed by the Contractor shall be
805.09
918
performed in the presence of the Department personnel assigned by the Engineer. The390
Contractor shall notify the Engineer a minimum of two business days prior to the date
testing is to be performed.
The Contractor shall meter all new loop wire detectors or a new bank of loop wire
detectors by means of instruments capable of measuring electrical values for installed
loop wires and lead-in cables. The instruments shall measure inductance in
microhenries, resistance in ohms, induced AC voltage in volts, and leakage resistance
in megohms. All measuring tests shall be performed at the detector housing before the
loop wire is spliced to the lead-in cable, and at the cabinet after the loop wire is spliced
to the lead-in cable.400
for Loop Wire
One of the megohm probes shall be connected to ground and the other probe shall
be connected to the “in” or “out” loop wire. The remaining loop wire shall be isolated.
The test shall then be performed.
for Lead-in Cable
The two wires and shield of the lead-in cable at the cabinet shall be isolated and
taped. The test shall consist of recording four readings taken at the detector housing or
handhole as follows:
second probe to the shield. Record the reading.
and the second probe to the shield. Record the reading.420
wire and the second probe to the shield. Record the
reading.
and the second probe to the second lead-in wire. Record
the reading.
The lowest of the four readings taken above shall be recorded on the testing430
document for acceptance.
This test shall be performed after the splice at the detector housing is completed.
A water solution of one tablespoon of baking soda per pint of water shall be placed in
805.09
919
a metal container. The metal container shall be grounded and the splice shall be fully
submerged in the solution for 2 minutes. With the splice submerged, the shield of the
lead-in shall be connected to ground at the cabinet. One megohm probe shall then be
connected to ground and the other probe connected to one of the lead-in wires and the
reading recorded.440
After all detector loop testing is complete, the detector amplifiers shall be installed
and settings adjusted for proper operation at the intersection.
The frequency setting shall be adjusted using the amplifier’s display so that
adjacent loops in the roadway that are connected to different loop amplifiers have a
minimum difference of 5 kHz. This operating frequency setting does not apply to loops
that are adjacent to each other in the roadway but are connected to the same loop
amplifier.450
The sensitivity setting shall be adjusted using the amplifier’s display. With an
average size front wheel drive vehicle with the front axle centered over the back loop
of a series of loops, the sensitivity shall be adjusted in accordance with the
manufacturer’s recommendations.
The count output shall be enabled for all loops designated as counting loops. The
number of loops setting shall be set for loops designated for counting purposes and
shall be set to the number of loops connected to that loop amplifier.
460
This test shall be performed by dragging a test vehicle across the loops using a
non-conducting string. The test vehicle shall be fabricated with an 8 ft length of No. 6
bare copper wire formed into a 2 1/2 ft diameter circle. The two ends shall then be
electrically spliced.
The test shall be started with all detector amplifiers turned ‘Off’ except for one
approach. All amplifiers for that approach shall be turned ‘On’ and adjusted to the
proper settings. All traffic for the approach being tested shall be stopped and not
allowed to cross any loops during the test procedure for that approach. The simulator
shall be dragged slowly across each loop system in the same direction as to simulate a470
vehicle driving through the loop system. As the simulator crosses each loop an IMSA
level II certified Signal Technician shall verify that a call is displayed exclusively on
the corresponding loop amplifier, controller detector input and controller phases. After
completely verifying the loops on the first approach the amplifiers shall be left ‘On’,
and the amplifiers for the next approach to be tested shall be turned ‘On’ and adjusted
to the proper settings. The same procedure shall be followed for each remaining
approach.
With large intersections, as the test proceeds, it may become difficult to verify
that the calls are going to the correct detector inputs. In this case, traffic control shall480
be used to stop vehicles before reaching the loops for as many approaches as needed
805.09
920
to accurately complete the testing to the inspector’s approval. Testing may be paused
between lanes to allow traffic to clear.
The Contractor shall record all test readings, in triplicate, on tabular forms
provided by the Department or by copying the one included elsewhere herein. The
Contractor shall complete, sign, and date the forms before submitting them to the
District Traffic Engineer. The District Traffic Engineer will use these forms for
recording the Department’s readings on the corresponding space provided.490
In order for the loop detector installation to be accepted, the electrical values shall
be as follows:
shall be determined by means of digital readout meter which
drives the field loop system.
500
Loop wire or lead-in cable failing to meet this requirement shall be replaced at no
cost to the Department.
805.10Other Vehicle Detection Systems
When required, the Contractor shall furnish and install an alternative vehicle
detection system from the QPL of Traffic Signal and ITS Devices.510
805.11Steel Conduit
Conduit shall be installed to a depth of no less than 2 ft or more than 5 ft below
the finished grade unless otherwise specified or approved. Pockets or traps where
moisture might accumulate shall be avoided. Conduit shall be placed under existing
pavement by approved jacking or drilling methods. Pavement shall not be disturbed
unless otherwise specified. If specified, cuts in pavement areas shall be no greater than
24 in. wide. All cuts in the pavement and sidewalk areas shall be sawed. Sidewalk
removal and replacement shall be to the nearest tooled joint. Jacking and drilling pits
shall be kept at least 2 ft clear of the edge of any type of pavement or paved shoulder.520
Excessive use of water that may cause undermining of the pavement shall be avoided.
Continuous conduit runs shall not exceed 200 ft in length, unless otherwise shown on
the plans.
Expansion fittings as detailed on structure plans shall be installed where conduit
crosses an expansion joint in the structure. Where it is deemed inadvisable to install
expansion fittings in closely confined areas, the installation of approved flexible tubing
805.10
921
may be allowed. Such expansion joints or tubing shall be the same size as the conduit.
Any existing underground conduit to be incorporated into a new signal installation
shall be cleaned with a mandrel and blown out with compressed air before cable is530
drawn into pipe. All new conduit runs shall be cleaned and swabbed before cables are
installed. All conduit ends shall be capped and shall remain capped until the Contractor
is ready to pull cable into the conduit, at which time the caps shall be removed and
conduit bushings placed on each end to protect the cable. The inside surface of the
conduit shall be kept clean. Conduit to be installed, indicated on the plans for future
use of signal cables, shall be left in place with a pull cord on its entire length.
Larger size conduit may be used with no additional payment, but when it is used,
it shall be for the entire length of the run from outlet to outlet. Conduit runs as shown
on the plans are for bidding purposes only and may be changed, with permission, to540
avoid underground obstructions. A change order may be authorized if the conduit runs
can be made on the opposite side of the street to that shown on the plans in order to
avoid obstruction and traffic inconvenience or to avoid unnecessary tearing up of
existing pavement.
805.12PVC, HDPE, and Fiberglass Conduit
The method of installing PVC, HDPE and rigid fiberglass conduit underground
shall be the same as for steel conduit where applicable except trenches for the conduit
in areas with class X material as described in 206.02 shall be backfilled with 2 in. of
natural sand before the conduit is placed in the trench. Materials excavated may be550
used for backfill, if approved. If the Engineer deems it necessary, approved B borrow
shall be placed over the conduit to a depth of 12 in. and the remainder of the trench
shall be filled with excavated material.
Schedule 40 or 80 PVC, Schedule 40 HDPE, or rigid fiberglass conduit may be
used for conduit placed in trenches with expansion fittings used every 200 ft unless
otherwise indicated on the plans. Schedule 80 HDPE, or steel shall be used for conduit
that is jacked or bored. Schedule 80 PVC or rigid fiberglass shall be used for conduit
on bridges or other structures. A No. 6 AWG copper or No. 14 AWG aluminum ground
wire shall be included in all PVC, HDPE, and rigid fiberglass conduit.560
805.13Foundations
Foundations for traffic signal structures, cabinets, and pedestals of the type
specified shall be constructed, or existing M foundations shall be modified, as shown
on the plans or as directed. Pedestal bases shall be plumb and firmly attached to the
anchor bolts either by using leveling nuts or shims if top of the foundation is not level.
Grouting shall be used when necessary to fill any gap between pedestal base and
foundation. Pipe pedestals shall be screwed tightly into the bases and secured with a
stainless steel pin. Power and signal cables shall then be pulled from the base into the
cabinet. Curing of concrete shall be in accordance with 702.22.570
The foundation concrete for traffic signal cantilever structures shall be placed
monolithically and shall have no construction joint. Structure bases shall be plumb and
805.13
922
attached to the anchor bolts using leveling nuts. A tooled line or other type of
permanent marking shall be provided on the top of the foundation to indicate the
direction of the conduits.
During excavation of the foundation, all material shall be removed to the full
depth as shown on the plans, except if class X material is encountered, the work shall
be performed in accordance with 206.02(b).580
805.14Final Clean-Up
When the installation is completed, all disturbed portions of sidewalk, pavement,
shoulders, driveways, and sod, shall be cleaned and any excess excavation or other
materials shall be disposed. All cutting in the sidewalk and pavement areas shall be
done with a saw. Sidewalk removal and replacement shall be to the nearest tool joint.
Unless otherwise directed, cuts in pavement areas shall be no greater than 12 in. in
width.
Within 30 calendar days after completion of the work, as-built drawings shall be590
submitted in electronic format to the Engineer. The signal as-built drawings shall
indicate the as-built location of steel strain poles, signal cantilevers, service points,
controller cabinet, loop detectors, conduit runs, and signal handholes.
805.15Method of Measurement
Controller and cabinet; controller cabinet foundation; disconnect hanger;
handhole, signal; loop detector delay amplifier; loop detector rack; pedestrian push
button; pedestrian signal head; signal cantilever structure, combination arm; signal
cantilever structure, drilled shaft foundation type; signal cantilever structure, dual arm;
signal cantilever structure, single arm; signal cantilever structure, single arm,600
combination arm; signal cantilever structure, spread footing foundation type; signal
detector housing; signal pole; signal pole foundation; signal service; span catenary and
tether; traffic signal head; and traffic signal head, retrofit; will be measured by the
number of units installed.
The pay length for a signal cantilever arm or combination arm will be the length
shown in the Schedule of Pay Items.
Conduit of the type specified will be measured by the linear foot from outside to
outside of foundations. All signal cable will be measured by the linear foot.610
Saw-cut for roadway loop detector and sealant will be measured by the linear foot
for the full depth of slot cut in the pavement as shown on the plans or as directed.
If class X material is encountered during foundation excavation, measurement
will be made in accordance with 206.10.
Traffic signal installation, flasher installation, miscellaneous equipment for traffic
signals, and final cleanup in accordance with 805.14 will not be measured for payment.
805.14
923
620
Reinforcing bars will not be measured for payment.
Traffic signal equipment removal will be measured per each installation to be
removed. Transportation of salvageable signal equipment will not be measured.
805.16Basis of Payment
Traffic signal installation and flasher installation, all of the type, new or
modernized, and the location number specified, will be paid for at a contract lump sum
price.
630
If specified as pay items, controller and cabinet; controller cabinet foundation;
disconnect hanger; handhole, signal; loop detector delay amplifier; loop detector rack;
pedestrian push button; pedestrian signal head; signal cantilever structure, single arm;
signal cantilever structure, combination arm; signal cantilever structure, single arm,
combination arm; signal cantilever structure, dual arm; signal cantilever structure,
drilled shaft foundation type; signal cantilever structure, spread footing foundation
type; signal detector housing; signal pole; signal pole foundation; signal service; span
catenary and tether; traffic signal head; and traffic signal head, retrofit; will be paid
for at the contract unit price per each.
640
Conduit of the type specified will be paid for at the contract unit price per linear
foot. The cost of any backfill, ground wire, or expansion fittings shall be included in
the cost of conduit.
Saw-cut for roadway loop detector and sealant, and signal cable will be paid for
at the contract unit price per linear foot.
The removal of existing traffic signal equipment designated to be removed will
be paid for at the contract unit price per each for traffic signal equipment, remove for
each location removed. When designated as a pay item, the transportation of650
salvageable signal equipment will be paid for at the contract lump sum price for
transportation of salvageable signal equipment.
Class X excavation will be paid for in accordance with 206.11.
Miscellaneous equipment for traffic signals will be paid for at a contract lump
sum price.
Payment will be made under:
660
Pay Item Pay Unit Symbol
Conduit, ____ ............................................................................ LFT
type
Controller and Cabinet, _____................................................... EACH
type
805.16
924
Controller Cabinet Foundation, _____ ...................................... EACH
type
Disconnect Hanger .................................................................... EACH
Flasher Installation, ______, Location No. _____..................... LS670
type
Handhole, Signal, _______ ....................................................... EACH
type
Loop Detector Delay Amplifier, ______,_____ Channel.......... EACH
type no.
Loop Detector Rack................................................................... EACH
Miscellaneous Equipment for Traffic Signals ........................... LS
Pedestrian Push Button, _____ .................................................. EACH
type
Pedestrian Signal Head, _____, ________ ................................ EACH680
type lens size
Saw-Cut for Roadway Loop Detector and Sealant .................... LFT
Signal Cable, _____, Copper, _____ C/ _____ ......................... LFT
type conductors/size
Signal Cantilever Structure, Combination Arm _____ ft .......... EACH
length
Signal Cantilever Structure, Drilled Shaft Foundation, ____ .... EACH
type
Signal Cantilever Structure, Dual Arm ___ ft, ___ ft ................ EACH
length length690
Signal Cantilever Structure, Single Arm ___ ft,
length
Combination Arm ___ ft..................................................... EACH
length
Signal Cantilever Structure, Single Arm ______ ft ................... EACH
length
Signal Cantilever Structure, Spread Footing
Foundation, _______ .......................................................... EACH
type
Signal Detector Housing............................................................ EACH700
Signal Pole Foundation, _____ in. x _____ in. x _____ in........ EACH
Signal Pole, ______, _____ ft ................................................... EACH
type length
Signal Service ............................................................................ EACH
Span, Catenary, and Tether ....................................................... EACH
Traffic Signal Equipment, Remove ........................................... EACH
Traffic Signal Head, _____ Section, Retrofit ........................... EACH
no.
Traffic Signal Head, _____, Section, __________ .................... EACH
no. lens size710
Traffic Signal Installation, _____, Location No. _____ ............ LS
type
805.16
925
Transportation of Salvageable Signal Equipment ..................... LS
The cost of the controller and cabinet, conduit, foundations, vehicle detection,
pedestrian signals, signal heads, signal poles, signal service, signal cable and all
equipment or materials required to complete the installation shall be included in the
cost of traffic signal installation.
The cost of the controller and cabinet, conduit, foundations, signal heads, signal720
poles, signal service, signal cable and all equipment or materials required to complete
the installation shall be included in the cost of flasher installation. For a solar powered
flasher, the cost of the solar panel, battery cabinet, program timing module, signal
heads, wiring, and all hardware required to complete the installation shall be included
in the cost of flasher installation.
The cost of the controller assembly, standard loop detector racks, all wiring,
hardware, and associated equipment required to operate the intersection shall be
included in the cost of controller and cabinet.
730
The cost of concrete, conduits, grounding bushings, ground rod, ground wire,
drainage, anchor bolts, and all hardware required to complete the installation shall be
included in the cost of controller cabinet foundation.
The cost of all work and hardware required to properly install loop detector delay
amplifier, counting or non-counting, as shown on the plans or as directed shall be
included in the cost of loop detector delay amplifier.
The cost of concrete reinforcing pipe and ring or polymer concrete box, cover and
attachment hardware, handhole bottom if required, and aggregate as shown on the740
plans shall be included in the cost of handhole, signal.
The cost of any supplementary loop detector rack, all wiring, hardware, detector
panel, BIU, and associated equipment shall be included in the cost of the loop detector
rack.
The cost of the push button, pedestrian actuated signal sign, any accessible
pedestrian signal components, and all hardware required to complete the installation
shall be included in the cost of pedestrian push button.
750
The cost of signal face hook-up wire, pole plates and arms for side mounts, pipe
arms, signal brackets, bulbs, weatherhead, and all additional hardware required to
assemble a combination of pedestrian signal indications as shown on the plans shall
be included in the cost of pedestrian signal head.
The cost of the slot cut on the pavement, backer rod, loop sealant, and all testing
in accordance with 805.09 shall be included in the cost of saw-cut for roadway loop
and sealant.
805.16
926
The cost of all work and hardware required to properly install overhead or760
underground signal cable, signal, fiber optic, or interconnect, as shown on the plans or
as directed shall be included in the cost of signal cable.
The cost of signal pole section 2 and combination arm, all hardware including the
metal skirt base plate, where necessary, to complete the installation as shown on the
plans shall be included in the cost of the signal cantilever structure, combination arm.
The cost of concrete, reinforcing bars, conduits, ground rod, ground wire,
grounding bushings, anchor rods, and all hardware required to complete the
installation of the drilled shaft or spread footing foundation for signals shall be770
included in the cost of signal cantilever structure, drilled shaft or spread footing
foundation.
The cost of signal pole and dual arms, all hardware including the metal skirt base
plate, where necessary, to complete the installation as shown on the plans shall be
included in the cost of the signal cantilever structure, dual arm.
The cost of signal pole section 1 and single arm, all hardware including the metal
skirt base plate, where necessary, to complete the installation as shown on the plans
shall be included in the cost of the signal cantilever structure, single arm.780
The cost of signal pole section 1, 2 and single arm, combination arm, all hardware
including the metal skirt base plate, where necessary, to complete the installation as
shown on the plans shall be included in the cost of the signal cantilever structure, single
arm, combination arm, when structure with single arm and combination arm is
required in the same contract.
The cost of aluminum casting, enclosure concrete, conduit and elbow, and all
hardware required to complete the installation shall be included in the cost of signal
detector housing.790
For a steel signal pole, the cost of the base plate, metal skirt base plate, handhole
and cover grounding lug, 2 in. pipe cable entrance, J hook, and top cover as shown on
the plans shall be included in the cost of signal pole.
For a timber signal pole, the cost of downguys, anchor rods, downguy guards, and
hub-eyes as shown on the plans, and all hardware required to complete the installation
shall be included in the cost of signal pole.
For a signal pedestal, the cost of the pedestal metal base, pedestal pole, pole cap,800
and all hardware required to complete the installation shall be included in the cost of
signal pole.
805.16
927
The cost of concrete, reinforcing bars, conduits, ground rod, ground wire,
grounding bushings, anchor rods, and all hardware required to complete the
installation of the signal pole foundation shall be included in the cost of signal pole
foundation.
The cost of weatherhead, 1 in. conduit riser, entrance switch, 1 to 2 in. conduit
reducer, ground rod, ground wire, and all hardware required to complete the810
installation, including the meter base when required and supplied by the utility
company shall be included in the cost of signal service.
The cost of steel pole bands or straight eye bolts, span, catenary, and tether of wire
rope cables, cable rings, Type A support cable, wire rope clips, safety cable, thimble,
service sleeve, and all hardware required to complete the installation as shown on the
plans shall be included in the cost of span, catenary, and tether.
The cost of signal face hook-up wire, pole plates and arms for side mounts, mid-
mast arm mount, pipe arms, signal brackets, visors, louvers, bulbs, span hanger,820
backplates, balance adjuster, weatherhead, and all additional hardware required to
assemble a combination of signal faces as shown on the plans shall be included in the
cost of traffic signal head.
The cost of removing the existing traffic signal head, salvaging the existing LED
indicators, replacing the existing signal head with a new housing and backplate, and
reinstalling shall be included in the cost of traffic signal head, retrofit.
The cost to repair or replace damaged or lost salvageable traffic signal equipment
shall be at no additional cost to the Department.830
The cost of excavation, backfill, final cleanup in accordance with 805.14, the cost
of re-painting existing metallic equipment to be re-used, the preparation and
transmittal of as-built drawings and controller assembly document packets, and
necessary incidentals shall be included in the cost of the pay items in this section.
TRAFFIC SIGNALS in other states
Get an email when 805 changes
Indiana revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.