MAINTENANCE OPERATIONS
801.01Description
This work shall consist of furnishing, placing, and maintaining signs, barricades, temporary pavement markings, and other traffic control devices at construction and maintenance operations in accordance with 105.03.
MATERIALS
801.02Materials
Materials shall be in accordance with the following:
Automated Flagger Assistance Devices ...................... 923.08 Coarse Aggregate, Class D or Higher, Size No. 73 ..... 904.03 Construction Warning Lights ...................................... 923.03 Delineator Posts ........................................................... 910.15 Delineators................................................................... 926.02 Field Paint.................................................................... 909.04 Flashing Arro w Sign.................................................... 923.04 20 Flexible Delineator Posts ............................................. 926.01 Portable Changeable Message Sign ............................. 923.05 Steel Posts ................................................................... 910.14 Temporary Barrier Delineator ..................................... 926.02(d) Temporary Pa nel Signs ................................................ 919.01 Temporary Pavement Marking Tape ........................... 923.01 Temporary Raised Pavement Markers......................... 923.02 Traffic Signal Materials and Equipment...................... 922 30 Tubular Marker ............................................................ 923.07 Wood Sign Posts ......................................................... 911.02(e) Worksite Speed Limit Sign Assembly ......................... 923.06
Non-ground mounted temporary traffic sign backing material and supports shall both be certified to meet NCHRP 350 crash test standards and approved for use by the FHWA. A copy of the FHWA acceptance letter shall be provided to the Engineer upon request. Roll-up materials will not be allowed except as specified in 801.16.
The reflective sheeting type used for construction signs, channelizing and delineation devices such as drums, tubular markers, vertical panels, and 42 in. cones, shall be the same for the entire project and shall be in accordance with 919.01(b)1. 801.02
The background for all construction signs shall be fluorescent orange reflective sheeting.
Steel sign posts need not be galvanized.
Wood posts for temporary panel signs sha ll be dense southern yellow pine or design calculations shall be provided to the Engineer identifying the type of wood and 50 verifying the location and size of the holes to be drilled through the posts to provide break-away capability.
All temporary traffic control devices which will become the property of the Department shall be a new product at the time of final acceptance.
The basis for use for traffic paint; durable pavement marking materials; temporary marking tape Type II; glass beads; barrels; barricades; construction warning lights; steel posts; temporary panel signs; traffic signs, except non-ground mounted signs; tubular markers; and wood sign post used for temporary traffic control will be visual 60 inspection.
The connecting bolt or threaded rod us ed to connect adjoining sections of temporary barrier wall shall have a tensile strength of 120,000 psi. The spacers used between adjoining sections of temporary barrier wall shall be in accordance with ASTM A36 with a tensile strength of 58,000 psi.
CONSTRUCTION REQUIREMENTS
801.03General Requirements 70
The applicable requirements of the MUTCD shall apply to the installation and materials for traffic control devices subject to the requirements of 107.08 and 107.12. When the plans do not include a maintenance of traffic plan, the Engineer will provide such a plan to the Contractor. The Contractor shall be responsible for the field layout, placement, operation, maintenance, and removal of temporary traffic control devices.
A worksite traffic supervisor certified by the American Traf fic Safety Service Association, ATSSA, or approved equal certifying organization, shall direct all field layout, placement, operation, inspection, ma intenance, and removal of temporary traffic control devices. The certified worksite traffic supervisor, CWTS, shall ensure 80 that all traffic control de vices, except temporary concrete barrier, meet acceptable standards as outlined in the plans, specifications, and ATSSA’s “Quality Standards for Temporary Traffic Control Devices” prior to installation. The CWTS shall also, prior to installation, ensure that all traffic control devices can be installed in accordance with the plans, specifications, and the MUTCD. All problems shall be reported to the Engineer so a resolution can be worked out prior to installation. The field layout will be reviewed and is subject to approval by the Engineer prior to placement of any temporary traffic control devices. The CWTS shall be present for the initial setup and all phase changes during the life of the project. The CWTS may designate responsible 801.03
Contractor personnel to perform day to day operation, inspection, and maintenance of 90 the temporary traffic control devices. These responsible personnel shall work under the direction of the CWTS and their names shall be given to the Engineer on the project. A copy of the CWTS’s certification shall be provided to the Engineer prior to the start of construction or placement of te mporary traffic control devices or if the worksite traffic supervisor changes.
Regulatory control devices shall be erected only as directed.
Advisory speeds to be posted will be determined by the Department.
The names and telephone numbers of the superintendent and one other responsible employee shall be furnished. Such employees shall be on call or available at night, on weekends, or during other non-working periods to repair or replace all traffic control devices which may become damaged or inoperative.
When traffic lanes are restricted and when specified as a pay item, a patroller shall inspect and maintain traffic control devices. The patroller shall patrol the construction zone and shall immediately correct, maintain , and repair traffic control devices or notify the Contractor designated persons for immediate repair to such traffic control devices. A full time patroller shall be on duty during periods when work is not in 110 progress.
Temporary traffic control devices shall be maintained to ensure visibility and to protect the public. All reflective sheeting ba ckgrounds and lights shall be kept clean of foreign matter. The Contractor shall complete and submit a “Traffic Control Device Report” when a temporary traffic control device has been installed, removed, relocated, repaired, or at a minimum of once per week based on field observations. This report is provided in the Proposal for the contract and shall be used to ensure that the traffic control devices are inspected daily. The report shall be completed or reviewed by the CWTS. Each report shall be signed by the person who performed the 120 inspection and shall be initialed by the CWTS that it was reviewed. The Engineer will sign and date the report when received. The Engineer will not be responsible for the report’s completeness and accuracy.
The location by reference post and the date and time of operation of Temporary Worksite Speed Limit sign assemblies shall be recorded daily on a form provided by the Department. The completed report shall be submitted weekly to the Engineer. The report shall be completed and signed by the CWTS or their designee and shall be reviewed by the CWTS for completeness and accuracy.
Except for construction warning lights and temporary signals, the ATSSA brochure titled “Quality Guidelines for Temporary Traffic Control Devices and Features” will be used as a guide to determine if temporary traffic control devices and markings are Acceptable, Marginal, or Un acceptable. Upon initial setup and phase changes of temporary traffic control devices, all individual devices shall be of the 801.03
Acceptable classification. A device not completely covered or removed when the message does not apply or when directed, will be considered unacceptable.
A temporary traffic control device will be deemed to be in non-compliance when considered Unacceptable. A type of temporary traffic control device will be deemed 140 to be in non-compliance when 25% or more of the individual devices are considered Marginal. Damages may be assessed in accordance with 105.14 for non-compliance.
Within 10 work days on HMA open to traffic, the edge lines shall be placed and shall be maintained until the next lift of HMA is placed or the permanent lines are placed, as appropriate. On PCCP open to traffic, the edge lines shall be placed, within 10 work days, and shall be maintained until the permanent lines are placed, as appropriate.
A quality assurance unit for placed long itudinal temporary pavement markings 150 shall be 500 lft on marked pavement in any combination or pattern, or portion thereof. A quality assurance unit for transverse marking, message, or symbol shall be each.
When longitudinal durable markings are specified, a quality assurance unit for longitudinal temporary markings shall be 5, 000 lft for markings that have not been placed.
Damages may be assessed in accordance with 105.14 for non-compliance. Damages for temporary pavement markings will not be assessed for patches less than 200 ft in length. 160
Non-compliance of construction warning lights will be in accordance with 801.14.
All barricades, signs, or flashing arrow signs shall be moved from one location and re-erected at another location as shown on the plans or as directed.
Traffic shall be maintained for maintenance activities or for HMA resurface work. The Contractor shall have an extra set of construction signs and an extra flashing arrow sign on the project site so that the taper may be moved forward without suspending the operations and clearing the work area. Additional traffic control devices shall be 170 furnished for situations determined to be more complex, for protection in hazardous areas, and when traffic conditions warrant.
All non-fixed signs shall be removed at the completion of each day’s operations. All fixed signs shall remain in place until all temporary pavement markings have been removed. All lanes shall be open to normal traffic during non-daylight hours. If a traffic lane is directed to remain closed during non-daylight hours, traffic shall be maintained on the remaining lanes as shown on the plans.
Where two-way traffic is to be mainta ined on a one-way pavement, and where the 180 existing shoulders on such roadway are earth, aggregate No. 73 shoulders shall be 801.03
compacted in accordance with 303.06 as s hown on the plans. Compacted aggregate shoulders shall remain in place unlesss ubsequent construction activities on the contract require its removal.
Temporary drainage structures, temporary concrete median barrier units, and other temporary devices required and used for traffic maintenance shall remain the property of the Contractor.
801.04Construction Signs 190
Construction signs shall include the typical sign standards or posts which support the sign, all necessary hardware, and specified construction warning lights.
A route or lane closure notice sign shall consist of a construction sign Type A, in accordance with 801.04(a), which indicates route or lane closure. The sign shall be
mounted for a maximum of 14 calendar days and a minimum of seven calendar days
before the closure date shown on the sign. The sign shall be removed when the route
or lane is closed.
Trailers in accordance with 910.14(f) may be used as supports for portable200
construction signs. The trailer shall be located to hold the sign in a proper position.
The position of the tongue shall be so as to cause no hazard to traffic. Wheel chocks
other than sandbags shall not be used. The tongue may be pinned to reduce
wind-induced rolling if designed to pull up or break from vehicle impact. During non-
working hours, trailers with signs that do not apply to existing conditions shall be
stored in accordance with 107.08(c).
Sign posts and their foundations shall be located and constructed to hold signs in
a proper position; to resist swaying, turning, or displacement; and minimize the hazard
to motorists. No rigidly fixed sign supports will be allowed in exposed areas where it210
would be practicable to utilize a breakaway or yielding type design. Signs shall be
completely covered or removed when the message does not apply.
If the work on a project, or a portion thereof, is not active, and the roadway is
open to unrestricted traffic, construction signs may be removed until work resumes.
Removal of such signs shall not relieve the Contractor of responsibilities or liabilities
described elsewhere herein.
A Type A sign shall consist of a construction sign as detailed in the MUTCD or220
on the standard drawings which is 9 sq ft or more in area.
A Type B sign shall consist of a construction sign as detailed in the MUTCD or
on the standard drawings which is less than 9 sq ft in area.
801.04
872
A Type C sign shall consist of a construction sign which is not detailed in the
MUTCD or on the standard drawings and which is 9 sq ft or more but less than 33 sq ft
in area.230
A Type D sign shall consist of a construction sign which is not detailed in the
MUTCD or on the standard drawings and which is less than 9 sq ft.
A temporary panel sign shall consist of a sign fabricated and constructed in
accordance with 919.01 and which is greater than 33 sq ft. Temporary panel signs shall
be mounted on wood posts as shown on the plans or as approved by the Department.
External bracing shall not be used.240
801.05Detour Route Marker Assembly
Detour route marker assemblies shall be on a single post for a single route or may
be on multiple posts for multiple routes. When two routes are being detoured across a
common roadway, each route shall be shown by a separate detour route marker
assembly. A detour route marker assembly-multiple route shall be used for three or
more routes across a common roadway.
801.06Road Closure Sign Assembly
Road closure sign assemblies shall be used at each road closure location where250
Type III-A barricades or Type III-B barricades are used. Road closure sign assemblies
shall not be used within lane closures where adjacent lanes remain open to traffic,
unless otherwise directed. Road closure sign assemblies may be required at other
locations as directed.
Permanent road closure sign assemblies shall be left in place after the contract is
completed and shall become the property of the Department. They shall be installed
just prior to final acceptance of the contract. Supports shall be painted with white field
paint for wood.
260
801.07Barricades
Barricades shall include rails, posts, and all incidentals necessary to complete this
part of the work.
High intensity reflective sheeting shall be placed on specified rails of all
barricades. The colors for temporary barricades shall be orange and white, and for
permanent barricades red and white.
All Type III barricades shall be skid mounted within pavement, shoulder, or
sidewalk areas, and on ground mounted posts in all other areas. Type III barricades270
shall be used on all slopes which are 3:1 or flatter for roadway closures.
801.05
873
Type III-A barricade shall have rails which are reflectorized on one side and shall
be used for roadway closures and lane closures where traffic can approach from only
one side.
Type III-B barricades shall have rails which are reflectorized on both sides and
shall be used for roadway closures and lane closures where traffic can approach the280
barricade from both sides.
Permanent Type III barricades shall be 10 ft sections and shall be left in place
after the contract is completed, and shall become the property of the Department.
Permanent Type III barricades shall be installed just prior to final acceptance of the
contract. All non-reflectorized wood and non-galvanized steel shall be painted with
white field paint. Such barricades shall otherwise be in accordance with 801.07(a).
801.08Cones and Tubular Markers290
Cones shall be made of a material to withstand impact without damage to striking
vehicles. They shall have a substantial base to restrict overturning. Cones and tubular
markers shall be as shown on the plans.
Cones shall be used only during temporary activities where portability is
advantageous and they remain in place and do not create a hazard to traffic. The use
of cones in lieu of drums will be allowed as shown on the plans except cones shall not
be used for shift or merge tapers on freeways and 42 in. cones may be used in tangent
sections on interstates and freeways only when the use of drums would result in an
effective lane width of less than 10 ft.300
Tubular markers shall be used for separating two-lane two-way traffic on non-
freeways as shown on the plans or as directed. Tubular markers may be used to
delineate a pavement drop-off on non-freeways when the use of drums would result in
an effective lane width of less than 10 ft.
Cones and tubular markers shall be secured in place either by weighting or
adhesives. The use of metal bases will not be allowed.
801.09Drums310
Drums shall be molded orange polyethylene.
The shape of the drum shall appear basically cylindrical to the motorist from any
direction in any given application. The top outside diameter shall not exceed the
bottom outside diameter. Drums shall be multisided, elliptical or have a flattened side
to inhibit rolling.
801.09
874
The top section of the drum shall have at least one construction warning light
mounting bracket. The minimum drum height is exclusive of lifting handles or
construction warning light mounting brackets.320
The drums shall stand on end, be stable against overturning, and shall be internally
or externally ballasted to resist wind speeds of up to 50 mph and gusts created by
traffic. The weight of the ballast shall be 45 to 55 lb. The top of the drum shall be free
from openings. Internally ballasted and externally collar ballasted drums shall not be
mixed in each continuous set-up.
Internal ballast shall be sandbags, a molded plastic base filled with sand and
closed with a locking cover, or a solid rubber base. The internal ballast shall be placed
in the lower 1/4 of the drum. The ballast device shall be self-draining.330
The external ballast shall be two rubber tire base collars. The tire base collars shall
have a circumferential contact with the road surface. The maximum diameter of the
tire base collar shall not exceed 36 in. The height of two tire base collars at the outside
edge shall not exceed 5 in. The rubber ballasting collars shall be clean cut, proper in
size, black in color, and not curved up at the edges. The interior and exterior
circumference of the collar shall not be slit or cut. Drums which are external collar
ballasted shall not be used in situations where the width of the collar interferes with
proper placement of the drum. The Department’s Guidelines for External Ballast will
be used for determining acceptability of rubber tire base collars.340
Upon impact by a vehicle traveling at a speed of 55 mph, the drum and ballast
device shall be of a type that enables the body of the drum to separate from the base,
thus allowing vehicles to easily pass over the base.
Construction warning lights shall be used in accordance with 801.14 and as shown
on the plans and shall be securely fastened to the mounting brackets. Signs shall not
be mounted on drums.
Permanent drums shall be left in place after the contract is complete, and shall350
become the property of the Department. They shall be installed just prior to final
acceptance of the contract.
801.10Temporary Traffic Barriers
Temporary traffic barrier shall be one of the following four types as shown on the
plans.
Type 1
Type 1 temporary traffic barriers shall be used to separate two-way traffic and
shall be precast concrete in accordance with applicable requirements of 707 and 602360
and as shown on the plans. Type 1 barriers may also be used to separate traffic from
the work area. The surfaces of individual precast units shall vary no more than 1/4 in.
in 10 ft from the specified cross-section, as measured from a longitudinal straightedge.
801.10
875
The maximum variation in the vertical and horizontal alignment of adjacent units shall
be 1/4 in. across the joint, as measured from a 10 ft longitudinal straightedge. Sections
that have obvious defects or visual cracks shall not be used. Sections that develop any
of these conditions during the contract shall be repaired with concrete or replaced
within a reasonable amount of time.
Type 1 barrier units precast prior to 2003 shall not be used after January 1, 2012.370
Units precast after March 1, 2003 shall be clearly marked with the name or trademark
of the manufacturer, the year of manufacture, and “INDOT”. The markings shall be
indented on an end or on the top of each barrier section. Units precast after January 1,
2007 shall be from the QPL of Certified Precast Concrete Producers.
Type 2
Type 2 barriers may be used to separate traffic from the work area. Type 2
temporary traffic barriers shall meet the appropriate test level 2 or 3 MASH or NCHRP
350 crash test standards and shall be approved for use by the FHWA. A copy of the
MASH or NCHRP 350 crash test FHWA eligibility letter shall be provided to the380
Engineer prior to placing the unit. The unit selected shall be appropriate for the
location considering the maximum posted speed limit on the project and the allowable
area for deflection. The unit shall be installed according to the manufacturer’s
recommendations.
If concrete barriers are used as Type 2 barriers, they shall be in accordance with
the requirements for Type 1 barriers.
Type 3
Type 3 temporary traffic barriers shall be those Type 1 temporary traffic barriers390
that are to be left in place at the completion of the contract and shall become the
property of the Department. They shall be in like-new condition at the completion of
the contract. All necessary delineation and required anchor systems shall be left in
place.
Type 4
Type 4 temporary traffic barriers shall be those types that are intended to be
readily moveable to accommodate the shifting of traffic lanes on a daily basis to better
facilitate the changing volumes of traffic during the peak hours of a day. Type 4
temporary traffic barriers shall meet the appropriate test level 3 MASH or NCHRP400
350 crash test standards and shall be approved for use by the FHWA. A copy of the
MASH or NCHRP 350 crash test FHWA eligibility letter shall be provided to the
Engineer prior to placing the unit.
Temporary traffic barriers shall be located as shown on the plans or as directed.
Temporary traffic barriers used to close a lane of traffic shall be flared at the rates as
shown on the plans for the applicable regulatory speed within the construction zone.
If field conditions are such that the required flare rate cannot be utilized, the tapered
801.10
876
alignment may be altered, with approval, to a 10:1 flare rate with a 20 ft minimum410
offset from the edge of the through traffic lane to the approaching end of the flared
temporary traffic barrier. If field conditions are such that that the 10:1 flare rate cannot
be utilized, the tapered alignment may be further altered, with approval, to a 6:1 flare
rate with the 20 ft minimum offset. Flare rates for ends of temporary traffic barriers at
locations where a lane of traffic is not being closed to traffic or where the lane has
already been closed shall be the same as above, however the minimum offset from the
edge of the through traffic lane may be 10 ft. The use of flare rates sharper than those
shown on the plans may require additional traffic control devices as directed.
Type 2 barriers shall not be intermixed with Type 1 or Type 3 barriers in any run.420
Type 2 barriers from different manufacturers shall not be intermixed in any run.
Type 1 and Type 3 barrier sections shall be connected as follows:
sufficient overlapping of the smooth bar hooks to allow
placement of the connecting bolt or threaded rod and the top
spacer.
430
directions for a sufficient distance to develop the maximum
contact between the smooth bar hooks and the connecting bolt
or threaded rod.
plans. The nut shall be sufficiently tightened to eliminate all
gaps between the adjacent bolt heads, spacers, nuts, and
washers which form the connection.
440
Type 1 and Type 3 precast units which have previously been cast meeting earlier
Department standards may be used. The Contractor will be allowed to mix Type 1 and
Type 3 units in a run as long as the units are in good condition and the connecting
devices are compatible. If units meeting earlier Department standards are used, a 1 in.
bolt will be allowed to link the units together. The spacer detail shall, however, be in
accordance with the current standard. Units cast after March 1, 2003 shall be linked
with the 1 1/4 in. bolt.
Type 2 temporary traffic barriers shall be connected as recommended by the
barrier manufacturer.450
Type 1 and Type 3 temporary traffic barriers shall be anchored in accordance with
the methods shown on the plans, at the locations described herein. Type 2 barriers shall
be anchored as recommended by the barrier manufacturer and at locations described
801.10
877
herein. Temporary concrete traffic barriers shall be anchored when located on or
within 60 ft of a bridge, and along tapered alignments. Anchoring at locations in
addition to those described herein will be required when directed.
Chemical anchor systems with removable bolts, or mechanical anchors may be460
used to anchor Type 1 barriers to bridge decks, concrete pavement, and concrete
shoulders. Mechanical anchors may be ferrous or non-ferrous material. All anchors
shall have a shear strength of 10,000 lb and an ultimate pullout strength of 6,500 lb.
Non-ferrous mechanical anchors shall be installed such that the top end of the
sleeve is a minimum of 2 1/2 in. below the final finished concrete surface.
Ferrous mechanical anchors shall be completely removed when no longer
required. All damage to the pavement shall be repaired as directed.
470
Non-ferrous anchor sleeves and the chemical adhesive component of chemical
anchor systems may remain in place when no longer required. The holes remaining in
the pavement shall be filled with appropriate material as directed.
Type 1 barriers used to separate two-way traffic shall be delineated with top
mounted temporary barrier delineators and with side mounted delineators. The top
mounted delineators shall be two-sided, shall be yellow, and shall be placed on every
other section of barrier wall. The top mounted delineators shall be mounted
perpendicular to the direction of traffic flow. The side mounted delineators shall be480
yellow and shall be mounted in accordance with 602.03(f).
Temporary traffic barriers in locations other than separating two-way traffic shall
be delineated with either Type C construction warning lights or top mounted
temporary barrier delineators and with side mounted barrier delineators. The Type C
lights or the top mounted barrier delineators shall be spaced at the number of feet equal
to the number of miles per hour in the posted speed limit with a minimum spacing of
20 ft. Bi-directional lenses will be required on the warning lights when the barrier is
adjacent to a lane that is carrying alternating one-way traffic. The color of the barrier
delineators shall be white when located on the right side of the traffic lane, and yellow490
when located on the left side of the traffic lane. The color of the barrier delineators
shall be white when located adjacent to a lane that is carrying alternating one-way
traffic.
Where the temporary traffic barrier is located along a tapered alignment and is
located behind drums or other reflective delineation devices, the Type C construction
warning lights and barrier delineators shall not be used.
Where possible, the ends of temporary traffic barriers shall be flared in accordance500
with 801.10(a). Where conditions do not allow the temporary traffic barrier to be flared
801.10
878
in accordance with 801.10(a), appropriate end treatments shall be incorporated to
protect vehicles from the ends of the barriers. The end treatments shall have re-direct
capability and shall meet the appropriate test level 2 or 3 NCHRP 350 crash test
standards and be approved for use by the FHWA.
No barrier segments shall be stored on the right-of-way unless written permission
is given by the Department. Requests for permission to store traffic barrier segments
on the right-of-way will not be accepted until after the contract has been awarded.510
.1 Construction Zone Energy Absorbing Terminal, CZ
The construction zone energy absorbing terminal, CZ, shall have passed NCHRP
350 level 3 crash test for all Interstate and other construction sites having a
construction zone speed limit in excess of 45 mph and level 2 for non-Interstate
construction sites having a construction zone speed limit of 45 mph or less. All energy
absorbing terminal, CZ, shall have redirect capabilities and shall be approved by the
FHWA.
A copy of the crash test report confirming the product is NCHRP 350 or MASH520
compliant for the test level specified, or a copy of the FHWA eligibility letter, shall be
furnished to the Engineer prior to the installation of the unit.
The unit’s nose cover shall be reflectorized to provide improved visibility.
Assembly and installation of the unit shall be supervised or performed at all times
by an installer trained and certified by the unit’s manufacturer. The size, assembly,
and installation shall be in accordance with the manufacturer’s recommendations at
the locations shown on the plans. When required for bi-directional traffic protection,
transition panels and all other necessary hardware shall be included in the installation.530
A copy of the installer’s certificate shall be provided to the Engineer prior to the start
of work.
The Contractor shall provide the Department with all necessary manufacturer’s
installation manuals and working drawings in accordance with 105.02.
Sufficient spare parts or complete units shall be stored in a safe, convenient,
nearby location. Such standby materials are not shown in the Schedule of Pay Items.
The standby materials shall be utilized to repair or replace damaged units in the
shortest time possible. Standby materials used in the repair of damaged units shall be540
replaced within 24 h of their use.
801.11Temporary Crossovers
Temporary crossovers shall be either Type A or Type B as shown on the plans
and shall be constructed in accordance with the applicable sections of 207, 402 or 502.
If applicable, a CMDS shall be submitted to the Engineer for approval. Utilization of
the Department provided spreadsheet is not required. When required to maintain
879
median drainage, a 15 in. diameter pipe shall be placed at the centerline of the median
under the crossover. If the crossover is to remain in place for future construction, the
pipe shall have appropriate grated box ends in accordance with 715.550
The pavement structure for the temporary crossover shall be as shown on the
plans.
Traffic control devices, including temporary pavement markings, shall be as
shown on the plans. Separation of opposing vehicular traffic between two crossovers
shall be as shown on the plans.
Refurbishing of a temporary crossover shall consist of the removal of drums or
earth cover from an existing temporary crossover. The temporary crossover shall be560
patched and resurfaced as directed. Excavated soil resulting from the refurbishing
operation, if not used as a part of the contract work, shall become the property of the
Contractor. Removed drums will remain the property of the Department.
After construction is complete, and prior to the opening of all lanes to traffic, the
temporary crossover shall be removed or closed.
Where guardrail is required to be removed for construction or refurbishing of
crossovers, such removal and subsequent re-erection shall be done as shown on the
plans or as directed.570
Acceptance of HMA for temporary crossovers will be in accordance with 402.09.
801.12Temporary Pavement Marking
Temporary pavement markings shall be new materials placed in accordance with
808.04and 808.05. However, when temporary markings are to be in place for 10 work
days or less the dashed line pattern used on center line and lane lines may be 4 ft line
segments on 40 ft centers and gore areas shall be marked by outline only and may be
5 in. wide lines. No-passing zones on all undivided two-way roadways shall be
identified with signs and centerline markings. Markings shall remain clearly visible580
during the day and night for a minimum of 200 ft ahead of a vehicle. All temporary
markings shall be maintained and replaced until they are no longer applicable.
Where possible, when non-removable temporary markings are used on a final
surface, such markings shall be placed at the same location where permanent markings
will later be affixed or parallel to and within 12 in. of the permanent marking pattern.
Where temporary pavement markings are to be placed on a pavement which has
existing markings, the existing markings which conflict with the temporary markings
shall be removed in accordance with 808.10. On asphalt pavement, black temporary590
tape Type I, may be used to cover conflicting markings. The black temporary tape
shall extend at least 1/2 in. beyond the edges of the marking to be covered. Overlapping
of temporary tape will not be allowed.
801.12
880
When working under traffic, the temporary pavement markings shall be placed
before opening the lane to traffic. This shall include, but not be limited to, the marking
patterns of gore areas, outside edge line of deceleration and acceleration lanes, narrow
bridge markings, lane reduction transitions, lane lines, centerlines, and transverse
markings as appropriate.
600
Temporary pavement markings which are to be in service from December 1
through the following March 31 shall be painted markings. Such markings shall be
placed in the standard pavement marking pattern and applied prior to the suspension
of the work, or within seven work days after the Contractor is directed to place the
markings. Adjustments to these dates to accommodate actual seasonal suspension and
continuance of work are subject to approval by the Engineer upon written request.
The prismatic reflectors shall be removed from snowplowable raised pavement
markers which conflict with the temporary traffic marking pattern. Snowplowable
raised pavement marker castings damaged by the removal of the reflector shall be610
replaced in accordance with 808.11. New prismatic reflectors shall be mounted on
existing castings in accordance with 808.11 when the final traffic pattern is
established.
Removal of temporary pavement markings shall be in accordance with 808.10.
Pavement markings shall be installed in accordance with 808.07 except that
measurement of retro-reflectivity is not required by the Contractor and quality
adjustments in accordance with 808.07 will not apply. All other performance measures620
shall apply.
Temporary edge lines shall be painted markings. When traffic is in the final
pattern, the temporary edge lines shall be placed at the same location as the permanent
markings.
Temporary pavement marking tape shall be applied in accordance with the
manufacturer’s recommendations. Temporary marking tape shall be new Type I or630
Type II material.
All temporary pavement marking tape shall be removed prior to placing the next
pavement course, prior to placing an overlay, prior to recycling the pavement, or prior
to placing the final pavement markings, except as otherwise described herein.
Type I tape is a removable material. It may be used for longitudinal and transverse
markings.
801.12
881
640
Type I tape shall be removed without the use of solvents, grinding, abrasive
blasting, or other methods which may damage the pavement. All visible adhesive
residue shall be removed without use of solvents or grinding.
Type II tape is a non-removable material. It may be used on PCCP to be removed
or on PCCP to be overlaid with an HMA course greater than 165 lb/sq yd. Type II tape
placed on HMA pavement shall be removed prior to placing the next pavement course.
If it is necessary to remove Type II tape, it shall be removed without the use of650
solvents. All damage to the pavement shall be repaired.
The temporary raised pavement marker shall be grade 1 or grade 2. When used, it
shall be a supplement to other temporary pavement markings. The color of the reflector
shall be in accordance with the other temporary pavement marking. The color of the
shell of the grade 1 marker shall be in accordance with the color of the other temporary
pavement marking.
Temporary raised pavement markers shall be removed before the next layer of660
pavement is placed and before the final pavement markings are applied. All damage
to the pavement shall be repaired.
Temporary buzz strips shall be a set of transverse markings constructed of
removable or durable marking material. Durable marking material shall be used in
accordance with 808.07(b).
670
801.13Temporary Illumination
The temporary highway illumination shall be in accordance with applicable
requirements of 807 except as modified herein.
The electric energy necessary to power the luminaires on a continuous basis is the
responsibility of the Contractor.
At completion of the contract work, the temporary illumination shall be removed
and shall remain the property of the Contractor. After removal of the temporary
illumination equipment, all holes and trenches shall be backfilled with B borrow.680
801.14Construction Warning Lights
Construction warning lights shall be portable, lens directed, enclosed lights that
emit an amber color. All warning lights shall be mounted a minimum of 36 in. above
the traveled way to the bottom of the lens, unless otherwise directed. Lights not
801.14
882
working shall be repaired or replaced immediately. For each day that more than 5% of
the required warning lights are not operating, a sum equal to $4.00 per non-working
light will be deducted from the monies due the Contractor.
Type A lights shall be low intensity flashing warning lights. These lights shall be
visible on a clear night from a minimum distance of 3,000 ft when there is no external
illumination directly on or in the immediate vicinity of the light. They shall operate
from dusk to dawn or when conditions exist which tend to obscure vision. Traffic
control devices used for maintaining traffic will not require Type A warning lights
during unobscured daylight hours.
Type B lights shall be high intensity, flashing, warning lights. These lights shall
be visible on a sunny day from a minimum distance of 1,000 ft when viewed without700
the sun directly on or behind the light.
Type C lights shall be steady burning warning lights. These lights shall be visible
on a clear night from a minimum distance of 3,000 ft when there is no external
illumination directly on or in the immediate vicinity of the light. They shall operate
from dusk to dawn or when conditions exist which tend to obscure vision.
Vehicle warning lights shall be amber and shall be a strobe light or a flashing,710
oscillating, or rotating directed beam light. They shall be visible to all approaching
traffic for a distance of 1,000 ft.
801.15Electronic Devices
Where specified, a flashing arrow sign shall be furnished, installed, and
maintained. It shall be operated continuously, when necessary, to divert traffic.
The flashing arrow sign may be of the solar power assisted type only in stationary720
operations when the horizontal or vertical curvature in the road is such that motorists
do not drive into and out of the beam width of the lighted arrow while within sight of
the sign.
This shall consist of furnishing, installing, and maintaining a trailer-mounted,
portable sign upon which varying electronically generated messages will be displayed
to traffic. The message being relayed to traffic shall be legible and easily understood
for a minimum distance of 650 ft.
730
801.15
883
The messages shall be as shown on the plans or as approved or directed by the
Engineer. Messages shall be formatted in accordance with the Department’s
Guidelines for Portable Changeable Message Signs. Only upper case letters shall be
used. Each message phase shall be displayed for at least 2 s. Display time for an entire
message shall not exceed 8 s.
Placement of PCMSs shall be as shown on the plans or as directed by the
Engineer. A minimum clearance of 7 ft from pavement to the bottom of the PCMS
shall be provided. Units shall be level and PCMSs shall be turned away from traffic,
placed in stand-by mode, or left blank until there is a valid message to be displayed.740
When in use PCMSs shall be turned approximately 3° from perpendicular towards
oncoming traffic to minimize glare. A drum shall be placed immediately in front of
the PCMS trailer at both corners for delineation.
This shall consist of furnishing and placing portable speed limit signs as shown
on the plans or as directed in areas of work activity. When used, the worksite speed
limit flashing strobe lights shall be activated when the worksite speed limit is in effect.
This shall be only where and while work is actually in progress and workers are
present. Each strobe light shall be visible through a range of 120° when viewed facing750
the sign and shall be visible from a distance of 750 ft.
Wherever a permanent speed limit sign exists within the limits controlled by the
worksite speed limit sign assemblies, additional worksite speed limit sign assemblies
shall be placed at the permanent signs. The permanent signs shall be covered or
removed during continuous worksite speed limit use.
A worksite speed limit authorized for intermittent use shall only be activated when
workers are present at the site. The intermittent worksite speed limit shall only be used
in the area of work. A worksite speed limit authorized for continuous use shall not760
include the flashing strobe lights or the S4-4 “WHEN FLASHING” plaque.
The worksite speed zone signage shall be placed and maintained by the
Contractor. The worksite speed limit will be as shown on the plans or as directed by
the Engineer and at least 10 mph below the posted speed limit for the roadway under
construction.
A worksite reduced speed advance warning sign assembly shall be placed in
advance of the first worksite speed limit sign assembly when the reduction in speed
limit is greater than 10 mph.770
This work shall consist of furnishing, installing, and maintaining temporary traffic
signals in accordance with 805 except as modified herein.
801.15
884
Except as shown on the plans, all materials not furnished by the Department shall
remain the property of the Contractor after work is completed and the equipment is
removed.
The traffic signal equipment shall be as specified, but may be either new or used.780
Used equipment shall be in satisfactory working condition and will be subject to
approval prior to use.
Two signal heads shall be displayed for each approach. Signal cable may be
extended across bridges through conduit which shall be attached to the underside of
the coping. Type and spacing of clamps will be subject to approval prior to installation.
Conduit shall be steel or plastic. Flexible conduit will be an acceptable alternate
for use as ground rod entry, magnetometer, or microloop installations.
790
Fixed temporary signals shall be displayed overhead on a span, catenary, and
tether utilizing an aircraft cable, unless otherwise directed.
Electric energy necessary to power the fixed temporary signal is the responsibility
of the Contractor. Prior to the start of construction, the schedule of activities shall be
coordinated with the power company.
The Contractor shall obtain permits from local officials, companies, or individuals
for the use of poles, right-of-way, or other property incidental to the installation of800
fixed temporary signals. Although entering into the contract implies permission and
authority to install conduit under pavement, sidewalks, and alleys, all damage to
underground utilities or interruption of such service shall be the responsibility of the
Contractor.
The location, spacing, and timing of fixed temporary signals will be determined
by the Engineer.
An IMSA certified level II Traffic Signal Construction Technician or a level II
Traffic Signal Field Technician shall be available 24 h a day to respond within 2 h for810
the maintenance of the traffic signal equipment.
The controller shall be traffic actuated solid state digital. For used controllers, the
model selected shall be from a manufacturer with a controller on the QPL of Traffic
Signal and ITS Devices.
Vehicle detection shall be provided and shall be either inductive loop or wireless
unless otherwise noted on the plans.
Portable signals shall be selected from the QPL of Portable Traffic Signals. Prior
801.15
885
to the activation, the Contractor shall provide a completed inspection checklist to the
Engineer certifying that the portable signal is functioning properly.
The portable signal shall be equipped with remote monitoring. Unless otherwise
shown on the plans, Microwave or Doppler vehicle detection as shown on the QPL of
Portable Traffic Signals shall be provided. A minimum of three drums shall be placed
immediately in front of the portable signal trailer for delineation.
A technician certified by the manufacturer shall be available 24 h a day to respond830
within 2 h for the maintenance of the traffic signal equipment. Copy of the certification
shall be provided to the Engineer prior to the placement of the portable signals.
Maintenance of the portable signal includes adjustments to the phasing or timing as
indicated on the plans or directed by the Engineer. The Contractor shall replace
portable signals that cannot be returned to normal operation or that fail two times
during the contract.
The Contractor shall provide a record of any modifications to the signal timing
plan, failures, and all maintenance issues, to the Engineer prior to final acceptance and
when otherwise requested. The report shall indicate the date, time, and nature of each840
event.
An Automated Flagger Assistance Device, AFAD, may be used to control a single
lane of approaching traffic on a two-lane highway for flagging operations.
Only qualified flaggers who have been trained on the operation of the AFAD shall
operate the AFAD. AFAD operators shall provide written proof that they have been
trained by the AFAD manufacturer. Two trained flaggers shall be available on-site to
provide flagging in case of an AFAD malfunction. The flagger operating the AFAD850
shall be positioned to have an unobstructed line of sight to approaching traffic and the
AFAD. A single flagger may be used to control both approaches to the work site if
adequate unobstructed sight distance exists between the AFAD operator and both
approaching directions of traffic and both AFADs.
The flagger operating the AFAD shall not leave the device unattended at any time
while the AFAD is in use. The operating flagger shall be positioned at such point to
be in full view of oncoming traffic and the AFAD at all times the AFAD is in use. The
flagger operator shall keep a backup handheld remote readily available at all times
when the device is being operated.860
The AFAD shall be positioned so that the end of the gate arm, if used, shall extend
at least to the center of the lane being controlled but shy of the roadway centerline.
A drum shall be placed immediately in front of the AFAD trailer at both corners
for delineation.
801.15
886
801.16Temporary Traffic Control Zone
A temporary traffic control zone is a work zone with frequently changing
operation, a maximum duration of seven calendar days; mobile operation; or a870
temporary traffic stoppage.
Daytime lane closures on two-lane two-way roads shall be limited in length to a
maximum of 1 mi or the length of a half day’s operation, whichever is less, or as shown
on an approved alternate traffic control plan.
When the vertical mounting height for TTCS is between 12 in. and 18 in. to the
bottom of the sign, tripod supports may be used. Temporary mounted construction
signs, which are mounted on portable supports such as sign stands and tripods may be880
used for the construction signs in a temporary traffic control zone. The bottom of a
temporary mounted construction sign shall be at least 12 in. above the traveled way.
Signs on tripod supports shall be installed so that the angle from vertical does not
exceed 30°.
Roll-up materials will only be allowed for mobile, short duration, or short-term
stationary work which will not exceed one daytime period. Roll-up materials shall be
selected from the QPL of Reflective Sheeting. Roll-up sign supports shall be ballasted
in accordance with the manufacturer’s recommendations.
890
Signs, flagging, flashing arrow signs, and other required traffic control devices
shall be furnished in accordance with the details shown on the plans or as directed.
The Engineer reserves the right to stop work at any time to relieve traffic congestion.
Flagging operations shall be conducted under the supervision of either the
designated CWTS or a flagger certified by ATSSA or approved equal certifying
organization. The person supervising the flagging operation shall ensure that the
flaggers are trained in proper flagging procedures and that the flagging operation is in
accordance with 107.12, the standard drawings, and the applicable sections of the900
MUTCD.
Traffic shall not be allowed to pass directly beneath personnel or equipment
working on an overhead structure. Traffic stoppage during an overhead operation shall
not exceed 20 minutes at one time. There shall be enough time between consecutive
stoppages to allow traffic to return to normal flow.
Three working days prior to commencing work which necessitates temporary
stoppage of traffic, written notice shall be given to the Department and the Indiana910
State Police that highway traffic shall be stopped temporarily at a specific location,
time, and date to accomplish specified work. Traffic shall be safely controlled during
the stoppage. The following minimum requirements shall be met.
801.16
887
Advance warning signs shall be located as specified or as otherwise directed. For
each direction of road closure two flaggers shall be located at the site of the work and
a minimum of two additional flaggers shall be used to warn approaching traffic.
Advance warning signs shall be located as specified or as otherwise directed. For
each direction of road closure, one flagger shall be located at the site of the work and
a minimum of one additional flagger shall be used to warn approaching traffic.
801.17Method of Measurement
Construction signs, detour route marker assemblies, detour route marker
assemblies-multiple routes, temporary worksite speed limit sign assemblies, road
closure sign assemblies, portable changeable message signs, and temporary raised
pavement markers will be measured by the number of units installed, maintained, and
removed.930
Temporary panel signs will be measured by the square foot. Temporary panel sign
supports, when required, will be measured by the linear foot, complete and in place.
Type III-A, Type III-B, and permanent Type III barricades will be measured by
the linear foot of the width of closure.
Temporary traffic barrier will be measured by the linear foot per the type
specified. Anchored traffic barrier will be measured by the linear foot, separately from
unanchored temporary concrete barrier per the type specified. End treatments, other940
than construction zone energy absorbing terminals, CZ, used on Type 1, Type 2, or
Type 3 temporary traffic barrier will be measured by the linear foot as part of the
barrier. All end treatments used on Type 4 temporary traffic barrier will be measured
by the linear foot as part of the barrier.
Construction zone energy absorbing terminals, CZ, used on Type 1, or Type 2, or
Type 3 temporary traffic barriers will be measured by the number of terminals placed.
Temporary crossovers Type A and Type B will be measured per each crossover.
The refurbishing of temporary crossovers will be measured per each type of crossover950
refurbished. HMA mixtures for temporary crossovers will be measured by the ton in
accordance with 109.01(b). Initial resurfacing and initial patching of refurbished
crossovers will be measured in accordance with 402.19. Temporary drainage pipe for
temporary crossovers will be measured by the linear foot. Seeding and sodding placed
due to the construction and removal or refurbishing and closing of temporary
crossovers, will be measured in accordance with 621.13. Removal and subsequent
replacement of permanent pavement markings and snowplowable raised pavement
markers for temporary crossovers will be measured in accordance with 808.12.
801.17
888
Removal and resetting of guardrail, if required for temporary crossovers, will be
measured in accordance with 601.13.960
Flashing arrow signs will be measured by the number of calendar days each unit
is operated.
Patroller will be measured by the number of calendar days during the phase or
phases of traffic control, as shown on the plans or as otherwise directed, that require
the patroller’s presence. Each portion of a day will be measured as a whole day.
Temporary pavement message markings will be measured by the number of each
type placed. Longitudinal and transverse temporary pavement markings will be970
measured by the linear foot of material actually placed. Temporary buzz strips will be
measured by the linear foot for each 8 in. strip placed, without regard to the number
of passes required to attain the specified height.
Removal, when necessary, of any type of non-removable temporary pavement
markings will be measured in accordance with 808.12. Removal of removable
temporary pavement markings will not be measured for payment.
Where temporary pavement markings are to be placed on a pavement which has
existing markings, removal of existing markings which conflict with the temporary980
markings will be measured in accordance with 808.12. Where conflicting markings
are covered with black temporary tape Type I, the black temporary tape will be
measured by the linear foot of markings covered.
The removal and replacement of prismatic reflectors on existing snowplowable
raised pavement markers will be measured in accordance with 808.12.
Compacted aggregate No. 73 used for shoulder material will be measured in
accordance with 303.09. Excavation of the existing earth shoulder will not be
measured for payment.990
Cones and tubular markers will not be measured for payment. Permanent tubular
markers will be measured per each.
Temporary illumination, fixed temporary signals, portable signals, and
maintaining traffic will not be measured for payment.
801.18Basis of Payment
The accepted quantities of construction signs, detour route marker assemblies,
detour route marker assemblies-multiple routes, temporary worksite speed limit sign1000
assemblies, road closure sign assemblies, permanent road closure sign assemblies and
temporary raised pavement markers will be paid for at the contract unit price per each.
Payment for temporary worksite speed limit assemblies, and PCMS will be made for
the maximum number of such assemblies in place at any one time during the life of
801.18
889
the contract. Type III-A, Type III-B, and permanent Type III barricades will be paid
for at the contract unit price per linear foot.
Temporary traffic barrier and anchored temporary traffic barrier will be paid for
at the contract unit price per linear foot per the type specified. Payment will be made
only once, regardless of the number of times the barrier is moved within each project.1010
Payment will be made for Temporary Traffic Barrier placed in, or relocated to, a
separate project.
End treatments, other than construction zone energy absorbing terminal, CZ, used
on Type 1, Type 2, or Type 3 will be paid for on a linear basis as part of the barrier.
All end treatments used on Type 4 temporary traffic barrier will be paid for on a linear
basis as part of the barrier.
Construction zone energy absorbing terminal, CZ, used with Type 1, or Type 2,
or Type 3 temporary traffic barriers will be paid for at the contract unit price per each1020
for energy absorbing terminal, CZ, of the test level placed. Each unit will be paid for
only once regardless of how many times it is moved within each project. Payment will
be made for construction zone energy absorbing terminal, CZ placed in, or relocated
to, a separate project. Back-up units will be paid for as energy absorbing terminal, CZ,
of the test level placed, if they are placed in service due to non-repairable damage to
the units already in service.
The accepted quantities of temporary crossovers will be paid for at the contract
unit price per each for the type specified. The accepted quantities of refurbishing
existing temporary crossovers will be paid for at the contract unit price per each for1030
the type specified. The accepted quantities of HMA for temporary crossovers will be
paid for as HMA for temporary pavement at the contract unit price per ton in
accordance with 402.20. Temporary drainage pipe for temporary crossovers will be
paid for at the contract unit price per linear foot. Sodding and seeding for temporary
crossovers will be paid for in accordance with 621.14. Removal and subsequent
replacement of permanent pavement markings and snowplowable raised pavement
markers for temporary crossovers will be paid for in accordance with 808.13. Removal
and resetting of guardrail, if required for temporary crossovers, will be paid for in
accordance with 601.14.
1040
If more than one construction sign is mounted on a common support with the
messages facing opposite directions, the largest sign will be paid for at the contract
unit price of the sign, and each additional sign will be paid for at half the unit price of
the sign if it had been erected independently.
Temporary panel signs will be paid for at the contract unit price per square foot
as shown on the plans. Temporary panel sign supports will be paid for at the contract
unit price per linear foot, complete and in place.
801.18
890
Flashing arrow signs and patrollers will be paid for at the contract unit price per1050
day per each.
Temporary pavement message markings placed will be paid for at the contract
unit price per each, for the message specified. Longitudinal and transverse temporary
pavement markings and temporary buzz strips, will be paid for at the contract unit
price per linear foot of material, complete in place.
Removal, when necessary, of non-removable temporary pavement lines and
message markings will be paid for in accordance with 808.13. The cost of removal of
removable temporary pavement markings shall be included in the cost of the pay item1060
for placement of the markings.
Where temporary pavement markings are to be placed on a pavement which has
existing markings, removal of the existing markings which conflict with the temporary
markings will be paid for in accordance with 808.13. Where conflicting markings are
covered with black temporary tape Type I, the specified width of black temporary tape
will be paid for at the contract unit price per linear foot of temporary pavement
marking, removable.
Permanent tubular markers and permanent drums will be paid for at the contract1070
unit price per each.
Compacted aggregate used for shoulder material will be paid for as compacted
aggregate No. 73 in accordance with 303.10.
The removal and replacement of reflectors on existing snowplowable raised
pavement markers will be paid for in accordance with 808.13.
Temporary illumination will be paid for at the contract lump sum price.
1080
All temporary traffic control devices which are specified as separate pay items
and used for maintenance of traffic will be paid for as set out in the Schedule of Pay
Items. The furnishing, placing, moving, removal, and maintenance of all other
temporary traffic control devices will be paid for at the contract lump sum price for
maintaining traffic.
The accepted fixed temporary and portable signals, complete in place and later
removed as specified, will be paid for at the contract lump sum price.
Payment will be made under:1090
Pay Item Pay Unit Symbol
Barricade, _____ ....................................................................... LFT
type
801.18
891
Barricade, III, Permanent .......................................................... LFT
Barrier, Direction Indicator ....................................................... EACH
Construction Sign, _____ .......................................................... EACH
type
Detour Route Marker Assembly ................................................ EACH1100
Detour Route Marker Assembly, Multiple Routes .................... EACH
Drum, Permanent....................................................................... EACH
Energy Absorbing Terminal, CZ, TL - _____ ........................... EACH
test level
Fixed Temporary Signal ............................................................ LS
Flashing Arrow Sign.................................................................. DAY
Maintaining Traffic ................................................................... LS
Patroller ..................................................................................... DAY
Portable Changeable Message Sign ........................................... EACH
Portable Signal .......................................................................... LS1110
Road Closure Sign Assembly .................................................... EACH
Road Closure Sign Assembly, Permanent ................................. EACH
Temporary Buzz Strips .............................................................. LFT
Temporary Crossover Drainage Pipe......................................... LFT
Temporary Crossover, _____ .................................................... EACH
type
Temporary Crossover, _____, Refurbish................................... EACH
type
Temporary Illumination............................................................. LS
Temporary Panel Sign Supports ................................................ LFT1120
Temporary Panel Signs.............................................................. SFT
Temporary Pavement Marking, _____ in. ................................. LFT
width
Temporary Pavement Marking, Removable, _____ in. ............. LFT
width
Temporary Pavement Message Marking, _____ ....................... EACH
description
Temporary Pavement Message Marking,
Removable, _____ .............................................................. EACH
description1130
Temporary Raised Pavement Marker, _____ ............................ EACH
grade
Temporary Traffic Barrier, _____ ............................................. LFT
type
Temporary Traffic Barrier, Anchored, _____ ........................... LFT
type
Temporary Transverse Pavement Marking, _____ in................ LFT
width
Temporary Transverse Pavement Marking,
Removable, _____ in. ......................................................... LFT1140
width
801.18
892
Temporary Worksite Speed Limit Sign Assembly, _____ ........ EACH
type
Tubular Marker, Permanent....................................................... EACH
Each construction sign, barricade, temporary worksite speed limit sign assembly,
road closure sign assembly, or flashing arrow sign will be paid for only once regardless
of how many times each is moved, replaced, or how many times each is altered to
change the sign message within each project. Payment will be made for signs placed
in, or relocated to, a separate project. Payment will not be made for signs or barricades1150
used for the convenience of the Contractor.
If a temporary worksite speed limit sign assembly, for intermittent use is not
flashing when required beginning 2 h after work begins, or if such assembly is flashing
when no work has been taking place for 2 h or longer, $200.00 will be deducted from
payment for such work for each 4 h period or part thereof, beginning after the 2 h grace
period.
Temporary mounted construction signs will not be paid for.
1160
Replacement of snowplowable raised pavement marker castings damaged due to
removing reflectors will not be paid for.
Electric energy necessary to power luminaires and fixed temporary signals will
not be paid for.
The cost of furnishing all materials, erection, maintenance, removal, and
necessary incidentals shall be included in the cost of barricades.
The cost of furnishing, installing, maintaining, and subsequent removal of the1170
detour marker, route marker, or street or road name sign, cardinal directional marker,
directional arrow marker, posts which support the assembly, and all necessary
hardware shall be included in the cost of detour route marker assembly or detour route
marker assembly, multiple routes.
The cost of all materials, equipment, labor, and incidentals necessary to install,
maintain, repair, and to remove the unit shall be included in the cost of energy
absorbing terminal, CZ. The cost of stockpiling standby terminals and terminal
materials, whether incorporated into the work or not, shall be included in the cost of
energy absorbing terminal, CZ. All units shall remain the property of the Contractor1180
upon completion of the contract.
The cost of the excavation required for placement of compacted aggregate
shoulders No. 73 will be included in the pay item maintaining traffic.
If the compacted aggregate No. 73 required for shoulders is removed, the cost of
such removal shall be included in the cost of the compacted aggregate.
801.18
893
If the Contractor elects to use more than two simultaneous operations during the
installation of snowplowable pavement markers or reflectors, the cost of required1190
traffic protection devices for additional operations shall be included in the cost of
maintaining traffic.
The cost of necessary flaggers; automated flagger assistance devices; protection
of traffic at structure foundations; and furnishing, erecting, placing, maintaining,
relocating, and removing lights, cones, flexible channelizers, tubular markers, drums,
delineators, or other devices as directed shall be included in the cost of maintaining
traffic.
The cost of furnishing and placing cones or tubular markers in accordance with1200
and drums in accordance with 801.09, the watcher in accordance with 107.12,
repair or replacement of damaged or inoperative traffic control devices, and traffic
maintenance in accordance with 104.04 shall be included in the cost of maintaining
traffic.
Additional materials necessary to place the portable changeable message sign in
a secure and level manner for site conditions shall be included in the cost of the pay
item. All costs to furnish, install, program, activate, deactivate, change messages,
move, replace, and maintain the PCMS shall be included in the cost of the pay item.
The cost of IP cellular phone service shall be included in the cost of the pay item.1210
The cost of the vehicle detection, solar panel, battery cabinet, program timing
module, signal heads, wiring, trailer, and all hardware required shall be included in the
cost of the portable signal.
The cost of installing, maintaining, and subsequent removal of signs, construction
warning lights, assembly supports, and all necessary hardware shall be included in the
cost of road closure sign assembly.
The cost of installation, maintenance, and removal or closure of the temporary1220
crossover, including excavation, compaction, subgrade preparation, and reshaping
damaged median area shall be included in the cost of temporary crossover.
The cost of removal of earth cover, removal of drums, reshaping damaged median
areas, and closure or removal of temporary crossover shall be included in the cost of
temporary crossover, refurbish.
The cost of placement, maintenance and replacement of temporary pavement
markings shall be included in the cost of the markings.
1230
The cost of cleaning existing pavement and removal of buzz strips shall be
included in the cost of buzz strips. Damage to the pavement caused by removal of buzz
801.18
894
strips and temporary pavement markings shall be repaired as directed with no
additional payment.
No payment will be made for temporary pavement markings which are in the
standard pavement marking pattern, and which are to be in service from December 1
through the following March 31 due to the Contractor’s failure to complete the work
as scheduled. However, payment will be made for these markings if the failure to
complete the work as scheduled is due to conditions beyond the Contractor’s control.1240
The cost of furnishing, installing, maintaining, and subsequent removal of
temporary raised pavement marker shall be included in the cost of temporary raised
pavement marker.
The cost of delineation of temporary traffic barrier shall be included in the cost of
temporary traffic barrier.
Damage done to pavement by removal of temporary traffic barriers and anchors
shall be repaired with no additional payment.1250