B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Calculators
All Calculators
Permits
Permit Fee
Egress
Occupant Load & Egress
Structural
Beam SpanConcrete VolumeExcavationDeck Footings
Electrical
Electrical LoadWire Size
Mechanical
HVAC Load
Fire Safety
Fire Resistance
General
Stair Layout
Elsewhere
Code LibraryDiagramsAssembliesChecklistsNeed a custom calculation? →
PricingLog in
Home / Calculators / Building Permit Fee Calculator

Joliet, Illinois Building Permit Cost Calculator

Estimates permit cost in Joliet from the city's own published fee schedule — not a national average. Every figure is computed from a rule quoted verbatim from that document, and rules that cannot be computed honestly are shown as the published text instead of a number.

217 jurisdictions with fee schedules on file

Total cost of work, labor and materials

Used by cities that price per square foot

Fences and retaining walls

Electrical permits priced by the ampere

Building Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Project cost up to $7,000
Flat fee $65.00
$65.00
Project cost above $7,000
$65 plus an additional $10.00 per $1,000.00 of project cost above $7,000.00
see rule
How this jurisdiction calculates the fee

The permit fee is $65 for up to $7,000 worth of work, with an additional $10.00 per $1,000.00 of project cost above $7,000.00.

Source: published fee schedule · Verified 9/15/2026

Deck Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Project cost up to $7,000
Flat fee $65.00
$65.00
Project cost above $7,000
$65 plus an additional $10.00 per $1,000.00 of project cost above $7,000.00
see rule
How this jurisdiction calculates the fee

The permit fee is $65 for up to $7,000 worth of work, with an additional $10.00 per $1,000.00 of project cost above $7,000.00.

Source: published fee schedule · Verified 9/15/2026

Fence Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Project cost up to $7,000
Flat fee $65.00
$65.00
Project cost above $7,000
$65 plus an additional $10.00 per $1,000.00 of project cost above $7,000.00
see rule
How this jurisdiction calculates the fee

The permit fee is $65 for up to $7,000 worth of work, with an additional $10.00 per $1,000.00 of project cost above $7,000.00.

Source: published fee schedule · Verified 9/15/2026

Reroof Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Project cost up to $7,000
Flat fee $65.00
$65.00
Project cost above $7,000
$65 plus an additional $10.00 per $1,000.00 of project cost above $7,000.00
see rule
How this jurisdiction calculates the fee

The permit fee is $65 for up to $7,000 worth of work, with an additional $10.00 per $1,000.00 of project cost above $7,000.00.

Source: published fee schedule · Verified 9/15/2026

Shed Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Project cost up to $7,000
Flat fee $65.00
$65.00
Project cost above $7,000
$65 plus an additional $10.00 per $1,000.00 of project cost above $7,000.00
see rule
How this jurisdiction calculates the fee

The permit fee is $65 for up to $7,000 worth of work, with an additional $10.00 per $1,000.00 of project cost above $7,000.00.

Source: published fee schedule · Verified 9/15/2026

Water Heater Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Base remodel fee, all plumbing applications
Flat fee $23.50
$23.50
○Water heater, per item
Flat fee $8.50
$8.50
○Water softener, per item
Flat fee $8.50
$8.50
○Gas meter, per item
Flat fee $12.50
$12.50
How this jurisdiction calculates the fee

Every plumbing application carries a base remodel fee, with per-item fees added for the work performed as itemized on the Plumbing Application.

Source: published fee schedule · Verified 9/15/2026

See the full write-up: Joliet building permit cost

Estimate only.Fee schedules change, and building departments set the final valuation and decide which fees apply to your scope. Confirm with the jurisdiction before budgeting. Lines marked “see rule” could not be computed from the published wording and are shown verbatim rather than guessed.