Home / Calculators / Building Permit Fee Calculator

Boston, Massachusetts Building Permit Cost Calculator

Estimates permit cost in Boston from the city's own published fee schedule — not a national average. Every figure is computed from a rule quoted verbatim from that document, and rules that cannot be computed honestly are shown as the published text instead of a number.

217 jurisdictions with fee schedules on file

Total cost of work, labor and materials

Used by cities that price per square foot

Fences and retaining walls

Electrical permits priced by the ampere

Building Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

Long-Form Permit
$50 application fee and $10 per every $1,000 of the work estimate
see rule
How this jurisdiction calculates the fee

A Long-Form Permit costs a flat application fee plus a charge tied to the estimated cost of the work. SCOPE NOTE: the ISD fee schedule scopes the Long Form Building permit to one-to-three-family major alterations. This row's figures should not be applied to four-family or commercial work.

Source: published fee schedule · Verified 11/10/2026

Deck Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

Short Form Building
$20.00 Primary fee plus $10.00 per $1,000 of the estimated cost of work
see rule
Long Form Building
$50.00 Primary fee plus $10.00 per $1,000.00 of the estimated cost of work
see rule
How this jurisdiction calculates the fee

Short Form and Long Form Building Permits each cost a primary fee plus a charge per $1,000 of the estimated cost of work.

Source: published fee schedule · Verified 10/29/2026

Electrical Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

Upgrading service or installing new service, up to 240 volts
$20 application fee plus $.25 amp up to 240 Volts
see rule
Upgrading service or installing new service, over 480 volts
$20 application fee plus $.75 amp over 480 volts
see rule
No change in service
$20 application fee plus $1 each for each fixture, plug, or outlet and $5 for each approved meter
see rule
When none of the above apply
$20 application fee plus $10 per $1,000 of the estimated cost
see rule
All state of Massachusetts buildings
$20 application fee plus $10 per $1,000 of the estimated cost
see rule
How this jurisdiction calculates the fee

Electrical permit fees are a $20 application fee plus a charge that depends on whether the service is being changed, calculated per amp, per device, or per $1,000 of estimated cost. CONFLICT NOTE: two City sources disagree on the top voltage band. The Electrical Permits page (the figure stored here) reads "$.75 amp over 480 volts", while the ISD Building Division fee schedule reads "$.75 amp up to 480 Volts". The schedule's wording forms a complete ladder from the "up to 240 Volts" band; the permit page's wording leaves 241 to 480 volts unpriced. The page figure is retained as stored because it is what the City currently publishes to applicants, but the band is unresolved and should be confirmed with ISD before relying on it.

Source: published fee schedule · Verified 11/10/2026

Reroof Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

Short-Form Permit
$20 application fee and $10 per every $1,000 of the work estimate
see rule
How this jurisdiction calculates the fee

A Short-Form Permit costs a flat application fee plus a charge tied to the estimated cost of the work.

Source: published fee schedule · Verified 11/13/2026

Shed Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

Use of Premises
$50.00 Primary fee
see rule
How this jurisdiction calculates the fee

A Use of Premises Permit costs a flat primary fee.

Source: published fee schedule · Verified 10/30/2026

Water Heater Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

Plumbing Permit
$20 application fee plus $5 for each fixture
see rule
How this jurisdiction calculates the fee

A Plumbing Permit costs a $20 application fee plus $5 for each fixture, such as toilets and sinks.

Source: published fee schedule · Verified 10/29/2026

See the full write-up: Boston building permit cost

Estimate only.Fee schedules change, and building departments set the final valuation and decide which fees apply to your scope. Confirm with the jurisdiction before budgeting. Lines marked “see rule” could not be computed from the published wording and are shown verbatim rather than guessed.