Worcester, Massachusetts Building Permit Cost Calculator
Estimates permit cost in Worcester from the city's own published fee schedule — not a national average. Every figure is computed from a rule quoted verbatim from that document, and rules that cannot be computed honestly are shown as the published text instead of a number.
217 jurisdictions with fee schedules on file
Total cost of work, labor and materials
Used by cities that price per square foot
Fences and retaining walls
Electrical permits priced by the ampere
Building Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Per $1,000.00 of construction value, or fraction thereof Flat fee $12.00 | $12.00 |
○Per $1,000.00 of construction value above $1,000,000 Flat fee $9.00 | $9.00 |
○Minimum building permit fee Flat fee $100.00 | $100.00 |
○Paper application processing fee Flat fee $50.00 | $50.00 |
○Certificate of Use and Occupancy Flat fee $100.00 | $100.00 |
How this jurisdiction calculates the fee
The Worcester Department of Inspectional Services charges building permits at $12.00 per $1,000.00 of construction value or fraction thereof, dropping to $9.00 per $1,000.00 for value above $1,000,000, subject to a $100.00 minimum, under its Schedule of Fees adopted pursuant to M.G.L. c. 40 s. 22F. A $50.00 processing fee is added to paper applications, while online applications carry no processing fee, and a Certificate of Use and Occupancy is $100.00. The fee is entirely a City charge: 780 CMR 109.2 and R109.2 leave municipal building permit fees to the municipality and direct state building permit fees to 801 CMR 4.02, which the Commonwealth applies to state-owned buildings, so no state surcharge is added to a Worcester permit. Working without a required permit carries a penalty of triple the original permit fee, with a minimum of $500.00 for residential or $1,000.00 for commercial properties.
Source: published fee schedule · Verified 11/2/2026
Deck Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Per $1,000.00 of construction value, or fraction thereof Flat fee $12.00 | $12.00 |
○Minimum building permit fee Flat fee $100.00 | $100.00 |
○Paper application processing fee Flat fee $50.00 | $50.00 |
How this jurisdiction calculates the fee
Worcester publishes no deck-specific permit fee, so a deck falls under the general building permit rate in the Department of Inspectional Services Schedule of Fees: $12.00 per $1,000.00 of construction value or fraction thereof, subject to a $100.00 minimum. Because of that minimum, a deck valued at $8,000 computes to $96.00 and is billed the $100.00 minimum instead. A $50.00 processing fee is added to paper applications; online applications are free of it. The charge is wholly municipal under M.G.L. c. 40 s. 22F, since 780 CMR 109.2 and R109.2 leave municipal permit fees to the municipality and reserve the state building permit fee under 801 CMR 4.02 for state-owned buildings.
Source: published fee schedule · Verified 11/16/2026
Electrical Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Single Family Detached Home (w/ overhead service) Flat fee $180.00 | $180.00 |
○Single Family Attached and Multi Family Home (w/ overhead service) Flat fee $180.00 | $180.00 |
○Underground Utilities (for service, PLUS Single/ Multifamily fee) Flat fee $100.00 | $100.00 |
○Single Family detached Additions, renovations, alterations, demolition Flat fee $100.00 | $100.00 |
○Single Family detached Additions, renovations, alterations, demolition, with Service upgrade Flat fee $170.00 | $170.00 |
○Single Family Attached and Multi Family Home Flat fee $100.00 | $100.00 |
Single Family Attached and Multi Family Home, With Service Upgrade $85.00 first meter, $30.00 each additional | see rule |
○Boilers, HVAC units, Water Heaters Flat fee $85.00 | $85.00 |
○Security Alarms, Audio Visual, Data Flat fee $85.00 | $85.00 |
○Smoke/ CO Detectors Installations Flat fee $85.00 | $85.00 |
Service Upgrade, repairs, grounding $85.00 1st meter | see rule |
○Service Upgrade, repairs, grounding, additional meters Flat fee $30.00 | $30.00 |
○Pools (Above Ground) Flat fee $85.00 | $85.00 |
○Pools (In Ground) Flat fee $85.00 | $85.00 |
○Residential Solar Wiring Flat fee $250.00 | $250.00 |
○Residential Generator Wiring Flat fee $150.00 | $150.00 |
○Temporary Service Flat fee $110.00 | $110.00 |
○Re-inspection Fee Flat fee $100.00 | $100.00 |
How this jurisdiction calculates the fee
Residential electrical permit fees are flat amounts set by the type of work, and work in multi-family structures is calculated per unit.
Source: published fee schedule · Verified 11/11/2026
Fence Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Zoning Determination Flat fee $100.00 | $100.00 |
○Per $1,000.00 of construction value, or fraction thereof Flat fee $12.00 | $12.00 |
○Minimum building permit fee Flat fee $100.00 | $100.00 |
○Paper application processing fee Flat fee $50.00 | $50.00 |
How this jurisdiction calculates the fee
A fence seven feet or less in height needs no building permit, so no permit fee applies, though a fence over six feet may require zoning relief and the Worcester Schedule of Fees charges $100.00 for a Zoning Determination. A fence that does require a building permit is charged at the general building permit rate of $12.00 per $1,000.00 of construction value or fraction thereof with a $100.00 minimum, since the City publishes no fence-specific fee. A $50.00 processing fee is added to paper applications. The charges are wholly municipal under M.G.L. c. 40 s. 22F, since 780 CMR 109.2 and R109.2 leave municipal permit fees to the municipality and reserve the state building permit fee under 801 CMR 4.02 for state-owned buildings.
Source: published fee schedule · Verified 11/16/2026
Reroof Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Per $1,000.00 of construction value, or fraction thereof Flat fee $12.00 | $12.00 |
○Minimum building permit fee Flat fee $100.00 | $100.00 |
○Paper application processing fee Flat fee $50.00 | $50.00 |
How this jurisdiction calculates the fee
Worcester publishes no roofing-specific permit fee, so a re-roof is charged at the general building permit rate in the Department of Inspectional Services Schedule of Fees: $12.00 per $1,000.00 of construction value or fraction thereof, subject to a $100.00 minimum. The minimum governs only where declared value is $8,000.00 or less, which computes to $96.00; above that the per-$1,000 rate applies, so a $15,000.00 re-roof is $180.00. A $50.00 processing fee is added to paper applications. The charge is wholly municipal under M.G.L. c. 40 s. 22F, since 780 CMR 109.2 and R109.2 leave municipal permit fees to the municipality and reserve the state building permit fee under 801 CMR 4.02 for state-owned buildings.
Source: published fee schedule · Verified 11/16/2026
Retaining Wall Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Per $1,000.00 of construction value, or fraction thereof Flat fee $12.00 | $12.00 |
○Minimum building permit fee Flat fee $100.00 | $100.00 |
○Paper application processing fee Flat fee $50.00 | $50.00 |
How this jurisdiction calculates the fee
A retaining wall not over four feet in height, measured from the bottom of the footing to the top of the wall, needs no building permit and therefore no fee, unless it supports a surcharge. A wall that does require a permit is charged at the general building permit rate in the Worcester Schedule of Fees, $12.00 per $1,000.00 of construction value or fraction thereof with a $100.00 minimum, as the City publishes no retaining-wall-specific fee. A $50.00 processing fee is added to paper applications. The charge is wholly municipal under M.G.L. c. 40 s. 22F, since 780 CMR 109.2 and R109.2 leave municipal permit fees to the municipality and reserve the state building permit fee under 801 CMR 4.02 for state-owned buildings.
Source: published fee schedule · Verified 10/30/2026
Shed Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Per $1,000.00 of construction value, or fraction thereof Flat fee $12.00 | $12.00 |
○Minimum building permit fee Flat fee $100.00 | $100.00 |
○Paper application processing fee Flat fee $50.00 | $50.00 |
How this jurisdiction calculates the fee
A shed of 200 square feet or less accessory to a one- or two-family dwelling is exempt from a building permit, so no permit fee applies; note the exemption threshold is 120 square feet for sheds accessory to buildings under the base volume of 780 CMR rather than the residential volume. A shed that does need a permit is charged at the general building permit rate in the Worcester Schedule of Fees, $12.00 per $1,000.00 of construction value or fraction thereof with a $100.00 minimum, as the City publishes no shed-specific fee. A $50.00 processing fee is added to paper applications. The charge is wholly municipal under M.G.L. c. 40 s. 22F, since 780 CMR 109.2 and R109.2 leave municipal permit fees to the municipality and reserve the state building permit fee under 801 CMR 4.02 for state-owned buildings.
Source: published fee schedule · Verified 11/16/2026
Water Heater Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
Plumbing, residential: Hot water tank new construction (+$15.00 each tank) $100.00 + $15.00 | see rule |
Plumbing, residential: Miscellaneous repairs or piping (+$15.00 each device) $100.00 + $15.00 | see rule |
Gas, residential: First fixture +$15.00 each additional fixture $100.00 + $15.00 | see rule |
Plumbing, commercial: Replacement hot water tanks including gas fitting per water heater $125.00+$15.00 | see rule |
○Electrical, residential: Boilers, HVAC units, Water Heaters Flat fee $85.00 | $85.00 |
○Re-inspection fee (defective or non-complying work), residential Flat fee $100.00 | $100.00 |
How this jurisdiction calculates the fee
Water heater work is priced under the plumbing, gas and electrical permit fees, with residential rates covering all residential buildings up to 3 dwelling units and commercial rates covering residential structures with more than 3 dwelling units.
Source: published fee schedule · Verified 11/11/2026
See the full write-up: Worcester building permit cost