Cleveland, Ohio Building Permit Cost Calculator
Estimates permit cost in Cleveland from the city's own published fee schedule — not a national average. Every figure is computed from a rule quoted verbatim from that document, and rules that cannot be computed honestly are shown as the published text instead of a number.
217 jurisdictions with fee schedules on file
Total cost of work, labor and materials
Used by cities that price per square foot
Fences and retaining walls
Electrical permits priced by the ampere
Building Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○One-, two- or three-family dwelling house, new buildings and additions $10.00 x 250 = $2,500.00 | $2,500.00 |
○One-, two- or three-family dwelling house, alterations and repairs $5.00 x 250 = $1,250.00 | $1,250.00 |
○Building regulated by the Ohio Building Code - new building, addition or first tenant space buildout, estimated cost under $1,000,000 $12.00 x 250 = $3,000.00 | $3,000.00 |
○Building regulated by the Ohio Building Code - new building, addition or first tenant space buildout, estimated cost $1,000,001 and up $12,000.00 base plus $7.00 x 250 = $13,750.00 | $13,750.00 |
○Building regulated by the Ohio Building Code - alterations or repairs, estimated cost under $1,000,000 $15.00 x 250 = $3,750.00 | $3,750.00 |
○Building regulated by the Ohio Building Code - alterations or repairs, estimated cost $1,000,001 and up $15,000.00 base plus $11.00 x 250 = $17,750.00 | $17,750.00 |
○Plan examination fee (Sec. 3105.28), payable when plans are submitted $0.02 x 2,000 = $40.00 | $40.00 |
○Site development review (Sec. 3105.28) Flat fee $250.00 | $250.00 |
○Zoning fee added to the building permit - commercial, multi-family and parking lots Flat fee $150.00 | $150.00 |
○Zoning fee added to the building permit - temporary uses Flat fee $30.00 | $30.00 |
○Certificate of occupancy on completion, enlargement or alteration of a building (Sec. 3105.27) Flat fee $60.00 | $60.00 |
State of Ohio surcharge added to the permit fee - one-, two- and three-family dwelling units · add-on 1% of the permit fee — select the permit fee line above to calculate | see rule |
State of Ohio surcharge added to the permit fee - Ohio Building Code regulated buildings · add-on 3% of the permit fee — select the permit fee line above to calculate | see rule |
Late fee where work is started prior to permit issuance, notified within 72 hours Minimum $100.00 plus 25% of the required permit fee | see rule |
Late fee where work is started prior to permit issuance, notified after 72 hours Minimum $200.00 plus 25% of the required permit fee | see rule |
How this jurisdiction calculates the fee
Cleveland codifies its permit fees in Codified Ordinances Sec. 3105.25. Building permit fees are calculated from the estimated cost of the work - which the section requires to include structural, electrical, plumbing and HVAC work, interior finish, normal site preparation, overhead and profit - at one rate for one-, two- and three-family dwelling houses and a higher rate for buildings regulated by the Ohio Building Code, with separate rates and minimums for new construction/additions versus alterations and repairs, and a reduced marginal rate above $1,000,000 of estimated cost. A plan examination fee based on floor area is charged up front when plans are submitted and again on revised plans (Sec. 3105.28), zoning fees are added to the applicable building permit, a certificate of occupancy fee applies on completion (Sec. 3105.27), a State of Ohio surcharge is added to the calculated permit fee, and late fees apply where work begins before the permit is issued. | DISCREPANCY CHECKED AND RESOLVED IN FAVOR OF THE STORED FIGURE, 2026-09-12 (lane B run 814): the City of Cleveland web page clevelandohio.gov/city-hall/departments/building-housing/divisions/construction-permitting/permit-fee-schedule, which describes itself as "a user-friendly recreation" of the schedule "effective January 2, 2014", lists Site Development Reviews at $200.00. Codified Ordinances Sec. 3105.28(c), read directly, states "A fee of two hundred and fifty dollars ($250.00) shall be charged for all site development reviews" (Ord. No. 708-10, passed 8-18-10, eff. 8-20-10). The code is the authority and matches our stored $250.00; the City page recreation is the erroneous one. No figure changed. Every other stored amount on this row verifies against both Sec. 3105.25/3105.27/3105.28 and the City page.
Source: published fee schedule · Verified 9/15/2026
Deck Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Miscellaneous buildings/structures - private garages, tool sheds, residential antennas and other accessory structures or buildings Flat fee $50.00 | $50.00 |
○One-, two- or three-family dwelling house, new buildings and additions (where the deck is permitted as an addition) $10.00 x 250 = $2,500.00 | $2,500.00 |
○One-, two- or three-family dwelling house, alterations and repairs (where the deck is permitted as an alteration) $5.00 x 250 = $1,250.00 | $1,250.00 |
○Plan examination fee (Sec. 3105.28), payable when plans are submitted $0.02 x 2,000 = $40.00 | $40.00 |
State of Ohio surcharge added to the permit fee - one-, two- and three-family dwelling units · add-on 1% of the permit fee — select the permit fee line above to calculate | see rule |
Late fee where work is started prior to permit issuance, notified within 72 hours Minimum $100.00 plus 25% of the required permit fee | see rule |
Late fee where work is started prior to permit issuance, notified after 72 hours Minimum $200.00 plus 25% of the required permit fee | see rule |
How this jurisdiction calculates the fee
Cleveland Codified Ordinances Sec. 3105.25 contains no deck line item. The Division of Construction Permitting groups decks with garages, sheds, pools, awnings, canopies, fences and parking lots as accessory structures and outdoor installations that require a permit, and directs applicants to the general fee schedule, where miscellaneous accessory structures carry a flat charge. Where the work is instead an addition to or an alteration of the dwelling itself, the dwelling-house rates in Sec. 3105.25(a) govern and are computed from the estimated cost of the work. A floor-area-based plan examination fee is paid when plans are submitted (Sec. 3105.28), and the State of Ohio surcharge is added to the calculated permit fee. Late fees apply where work begins before the permit issues.
Source: published fee schedule · Verified 9/15/2026
Electrical Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Minimum fee for any permit Flat fee $50.00 | $50.00 |
○New construction additions, alterations to existing buildings, for each 1,000 square feet or part thereof Flat fee $50.00 | $50.00 |
○Repairs to existing electrical fixtures and/or systems Flat fee $50.00 | $50.00 |
○Blanket electrical permit, for each year for each premises Flat fee $200.00 | $200.00 |
○Inspection where the work is not found ready or the address given in the application is faulty or inaccurate, each such inspection Flat fee $40.00 | $40.00 |
○Inspection required outside of regular working hours Flat fee $100.00 | $100.00 |
Late fee if work is started prior to permit issuance, within 72 hours of notification Minimum $100.00 + 25% of required permit fee | see rule |
Late fee if work is started prior to permit issuance, after 72 hours Minimum $200.00 + 25% of required permit fee | see rule |
How this jurisdiction calculates the fee
Electrical permit fees are calculated either by floor area for new construction, additions and alterations to existing buildings, or per item, subject to a minimum fee for any permit. | 2026-09-25 (lane B run 1754) RE-VERIFIED VERBATIM FROM TWO INDEPENDENT OFFICIAL SOURCES, NOTHING CHANGED. The cited 2023-06 ElectricalAppandFeeSchedule.pdf is image-only (pdftotext returns 0 bytes); it was rendered at 300 dpi and OCR'd in full rather than trusted as empty, and all eight stored figures read verbatim. Separately, the City now publishes a web fee schedule at clevelandohio.gov .../construction-permitting/permit-fee-schedule, described as "a user-friendly recreation of the City of Cleveland Department of Building and Housing Plan Examination and Permit Fee Schedule, effective January 2, 2014"; its Electrical Fee Schedule accordion agrees with the PDF and with our stored figures line for line. NOT STORED, worth knowing: that page also sets a State of Ohio surcharge added to the calculated permit fee - 1% for 1, 2 and 3 family dwelling units and 3% for OBC regulated buildings.
Source: published fee schedule · Verified 9/25/2026
Fence Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Fences, guardrails or barriers for one-, two- and three-family dwelling units Flat fee $50.00 | $50.00 |
○Fences, guardrails or barriers for commercial buildings $15.00 x 250 = $3,750.00 | $3,750.00 |
○Zoning fee added to the building permit - signs, fences and appurtenant structures Flat fee $20.00 | $20.00 |
○Plan examination minimum for a project with no floor area, such as a fence (Sec. 3105.28) Flat fee $20.00 | $20.00 |
State of Ohio surcharge added to the permit fee - one-, two- and three-family dwelling units · add-on 1% of the permit fee — select the permit fee line above to calculate | see rule |
State of Ohio surcharge added to the permit fee - Ohio Building Code regulated buildings · add-on 3% of the permit fee — select the permit fee line above to calculate | see rule |
Late fee where work is started prior to permit issuance, notified within 72 hours Minimum $100.00 plus 25% of the required permit fee | see rule |
Late fee where work is started prior to permit issuance, notified after 72 hours Minimum $200.00 plus 25% of the required permit fee | see rule |
How this jurisdiction calculates the fee
Fences are a named line in Cleveland Codified Ordinances Sec. 3105.25(c). A fence, guardrail or barrier serving a one-, two- or three-family dwelling unit is a flat charge; a fence for a commercial building is instead calculated from the estimated cost of the work subject to a minimum. A zoning fee for signs, fences and appurtenant structures is added to the building permit. Because a fence has no floor area, the plan examination minimum applies rather than the per-1,000-square-foot rate (Sec. 3105.28 names fences among the projects with no floor area). The State of Ohio surcharge is added to the calculated permit fee, and late fees apply where work begins before the permit issues. A permit application must be filed with four copies of a scaled site plan showing property lines, all buildings and fences, fence material and fence height.
Source: published fee schedule · Verified 9/15/2026
Reroof Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○One-, two- or three-family dwelling house, alterations and repairs $5.00 x 250 = $1,250.00 | $1,250.00 |
○Building regulated by the Ohio Building Code - alterations or repairs, estimated cost under $1,000,000 $15.00 x 250 = $3,750.00 | $3,750.00 |
○Building regulated by the Ohio Building Code - alterations or repairs, estimated cost $1,000,001 and up $15,000.00 base plus $11.00 x 250 = $17,750.00 | $17,750.00 |
○Plan examination minimum for a project with no floor area, such as a roof (Sec. 3105.28) Flat fee $20.00 | $20.00 |
State of Ohio surcharge added to the permit fee - one-, two- and three-family dwelling units · add-on 1% of the permit fee — select the permit fee line above to calculate | see rule |
State of Ohio surcharge added to the permit fee - Ohio Building Code regulated buildings · add-on 3% of the permit fee — select the permit fee line above to calculate | see rule |
Late fee where work is started prior to permit issuance, notified within 72 hours Minimum $100.00 plus 25% of the required permit fee | see rule |
Late fee where work is started prior to permit issuance, notified after 72 hours Minimum $200.00 plus 25% of the required permit fee | see rule |
How this jurisdiction calculates the fee
Cleveland requires a permit to replace a roof - the Division of Construction Permitting lists replacement of an existing building component, giving roof replacement as its example, among the projects that require a permit. Codified Ordinances Sec. 3105.25 has no roofing line item, so a reroof is priced under the alterations and repairs category: the dwelling-house rate for one-, two- and three-family houses and the higher Ohio Building Code rate for all other buildings, each computed per $1,000 of estimated cost subject to a minimum, with a reduced marginal rate above $1,000,000. Estimated cost must include normal site preparation, overhead and profit. Because a roof carries no floor area, the plan examination minimum applies rather than the per-1,000-square-foot rate. The State of Ohio surcharge is added to the calculated permit fee, and late fees apply where work begins before the permit issues.
Source: published fee schedule · Verified 10/2/2026
Shed Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
Permit fee - Miscellaneous Buildings/Structures: private garages, tool sheds, residential antennas and other accessory structures or buildings $50.00 minimum | see rule |
○Plan examination fee, per area examined $0.02 x 2,000 = $40.00 | $40.00 |
○Plan examination minimum fee (projects under 1,000 sq ft, or without floor area) Flat fee $20.00 | $20.00 |
○Zoning fee, residential (added to the building fee) Flat fee $20.00 | $20.00 |
State of Ohio surcharge, 1, 2 and 3 family dwelling units · add-on 1% of the permit fee — select the permit fee line above to calculate | see rule |
State of Ohio surcharge, buildings regulated by the Ohio Building Code · add-on 3% of the permit fee — select the permit fee line above to calculate | see rule |
○Demolition or removal of a 1, 2 or 3 family dwelling or accessory structure $0.01 x 2,000 = $20.00, raised to the $50.00 minimum | $50.00 |
Late fee - work started before permit issuance, City notified within 72 hours $100.00 plus 25% of the required permit fee | see rule |
Late fee - work started before permit issuance, City notified after 72 hours $200.00 plus 25% of the required permit fee | see rule |
How this jurisdiction calculates the fee
A shed is charged under the Miscellaneous Buildings/Structures line of the City of Cleveland Plan Examination and Permit Fee Schedule (Codified Ordinances Section 3105.25), which covers private garages, tool sheds, residential antennas and other accessory structures or buildings. The permit fee is subject to a minimum. A separate, non-refundable plan examination fee is payable when plans are submitted, and an applicable zoning fee and the State of Ohio surcharge are added to the permit fee.
Source: published fee schedule · Verified 11/5/2026
Water Heater Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Minimum fee for any permit Flat fee $50.00 | $50.00 |
○Each plumbing fixture, appliance or device, including hot water heating devices Flat fee $8.00 | $8.00 |
○Water distribution piping, for each 100 lineal feet or fraction thereof Flat fee $13.00 | $13.00 |
○Gas piping, for each 100 lineal feet or fraction thereof Flat fee $13.00 | $13.00 |
○Repairs to existing plumbing fixtures and/or systems Flat fee $50.00 | $50.00 |
Late fee if work is started prior to permit issuance, within 72 hours of notification Minimum $100.00 + 25% of required permit fee | see rule |
Late fee if work is started prior to permit issuance, after 72 hours Minimum $200.00 + 25% of required permit fee | see rule |
How this jurisdiction calculates the fee
Plumbing permit fees are charged for each fixture, appliance or device and by lineal footage of piping, subject to a minimum fee for any permit. | 2026-09-25 (lane B run 1754) RE-VERIFIED VERBATIM, NOTHING CHANGED. The cited 2023-06 PlumbingAppandFeeSchedule.pdf is image-only and was OCR'd at 300 dpi in full; all seven stored figures read verbatim, including "hot water heating devices ... $8.00" and the $13.00 per-100-lineal-feet piping lines. Cross-checked against the City's live web fee schedule (effective January 2, 2014), which agrees. A 1% (1-3 family) / 3% (OBC) State of Ohio surcharge applies on top and is not stored.
Source: published fee schedule · Verified 9/25/2026
See the full write-up: Cleveland building permit cost
Estimate only.Fee schedules change, and building departments set the final valuation and decide which fees apply to your scope. Confirm with the jurisdiction before budgeting. Lines marked “see rule” could not be computed from the published wording and are shown verbatim rather than guessed.