B.Projects without Railroad Involvement. Prepare and provide Engineered Drawings listed in this section as follows: Have competent individuals prepare , check and initial each Engineered Drawing. The preparer and checker shall be different individuals. Provide, on the cover sheet or submittal letter, the first name, last name and initials of each preparer and checker performing work on the Engineered Drawings. Have an Ohio Registered Engineer prepare, sign, seal and date the cover sheet or submittal letter according to ORC 4733 and OAC 4733 -35. If multiple preparers or multiple checkers created the drawing, then the cover sheet or submittal letter shall clearly indicate the portions for which each pe rson is responsible. Schedule an Engineered Drawing meeting to be held within 14 days of the work. Submit Engineered Drawings to the Engineer at least 7 days prior to the meeting. The signatory Engineer responsible for the design, QCR if designated), the Superintendent, the E ngineer and the Inspector will participate in the meeting in person, via conference call or via video conference. The superintendent or other on- site personnel and the QCR may be the same person. The Engineer will invite the designer of the contract Plans for assistance. The purpose of the meeting shall be to review the drawings; resolve all issues to the Engineer’s satisfaction and ensure all parties are in agreement with the work to commence. At the conclusion of the meeting, the Engineer will provide a w ritten response to the submittal in accordance with C&MS 105.02. Do not begin work until the Engineer’s acceptance has been received. 501.05 314 Perform all work in accordance with the accepted Engineered Drawings. The Signatory Engineer sh all be available during the work to confirm that all work and equipment is in accordance with the Engineered Drawings. Alternatively, the Signatory Engineer may designate an on -site QCR with the authority to confirm the work and equipment as authorized is in accordance with the Engineered Drawings. The limits of the QCR’s authority will be determined by the Signatory Engineer and put into writing prior to proceeding with associated work. The Signatory Engineer or the QCR shall respond in writing to all clarifications of plan conformance requested by the Engineer or Inspector during the progress of the work. The Department will consider a failure to respond to a clarification request as a deviation to the accepted Engineered Drawings. Immediately cease all operations that deviate from the accepted Engineered Drawings . If a deviation is necessary, prepare revised Engineered Drawings as noted above and furnish the Engineer a copy of revised Engineered Drawings . Schedule an Engineered Drawing meeting as noted above to be held 24 hours , or less at the discretion of the Engineer, after submitting the revised drawings. At the conclusion of the meeting, the Engineer will provide a written response to the submittal in accordance with C&MS 105.02. Do not begin work until the Engineer’s acceptance has been received. The Department will consider delays resulting from Engineered Drawings deviations as non -excusable in accordance with 108. 06.E. This section applies to Engineered Drawings for the following:
1.Cofferdams and Excavation Bracing . If a complete design is not provided in the plans , provide Engineered Drawings for excavations when the edge line of a roadway used to maintain traffic is l ocated within a distance of one -half times the excavation height or for excavations that expose any side of an excavation to a height exceeding eight feet. The Contractor may construct the design(s) shown on the plans without an Engineered Drawing submitt al or prepare an alternate design. Submit Engineered Drawings for all alternate Cofferdam and Excavation Bracing designs. Perform all Work as specified below:
a.Locate Cofferdams and Excavation Bracing according to the contract, if shown.
b.Maintain temp orary horizontal and vertical clearances according to the contract.
c.Include the effects of AASHTO live , dead and temporary construction load surcharges as necessary.
d.Design Cofferdams and Excavation Bracing to support the sides and bottom of an e xcavation for all phases of work in accordance with the latest AASHTO Guide Design Specifications for Bridge Temporary Works, Section 4 and the latest edition of either the AASHTO LRFD Bridge Design Specifications or the AASHTO Standard Specifications for Highway Bridges. 501.05 315 2. Demolition of Bridges or portions of Bridges in which the work endangers the public welfare, or life, health or property . Perform all Work as specified below:
a.Provide temporary devices or structures necessary to protect traffic during all demolition activities. Provide traffic protection when demolition is located less than 12' horizontally from active traffic on structures of less th an 25' vertical clearance. Increase the 12' minimum horizontal distance 1 foot for each 2 feet of additional height greater than 25'.
b.Never lift the portions of structure being removed over active traffic. Before releasing traffic make the remaining str ucture stable.
c.Design traffic protection devices or structures when over live traffic, for a minimum load of 50 pounds per square foot plus the weight of equipment, debris and any other load to be carried. Include any portion of the deck that cantilever s beyond the fascia beams or girders.
d.In lieu of temporary devices or structures required in “a .” above, provide a vertical barrier. Design the vertical barrier with rigid or flexible materials specifically designed for demolition containment. Extend t he enclosure up to the bottom of the deck and down to the ground. Maintain all materials free of tears, cuts and holes.
e.Maintain temporary horizontal and vertical clearances according to the contract.
f.Locate structural members to be reused before performing any removal operations.
g.Do not damage structural members being reused during any removal operation.
h.Perform Work so that all members are stable during all operation and loading conditions.
i.Provide the method and sequence of the removal operations. Include the type and location of equipment to be used during the demolition.
j.Perform Work according to 501.05.B.6.
3.Falsework for cast -in-place concrete slab bridges. Perform all work according to 508 and as specified below:
a.Provide a camber table to account for the deflection of the falsework loaded with its self weight and the weight of wet concrete. Also include in the table, the specified camber to compensate for slab defle ction after the falsework is released.
b.Maintain temporary horizontal and vertical clearances according to the contract.
c.As a minimum design falsework over waterways for a five year flood or with 75 percent of the effective waterway opening of the pro posed structure. The Contractor is responsible for any damages caused by upstream flooding due to 501.05 316 insufficient temporary structure size or the accumulation of debris or sediment in the channel.
d.Support falsework foundations located within the ten year flood limits on rock, shale or piles driven to a minimum depth of 15 feet, and to sufficient penetration to carry superimposed loads or until refusal on rock.
e.The incorporation of structural steel shapes, used as temporary support members, into a finish ed concrete slab superstructure is prohibited.
f.Design falsework in accordance with the latest AASHTO Guide Design Specifications for Bridge Temporary Works, Section 2.
4.Erection of steel or precast concrete structural members as specified below:
a.Never lift structural members over active traffic. Before releasing traffic make structural members stable
b.Supply any temporary supports or braces necessary to maintain structural stability and prevent lateral movement until completion of all const ruction activities.
c.Perform Work according to 501.05.B.6, 513 or 515.
d.Do not field weld temporary members to permanent steel members.
e.Maintain temporary horizontal and vertical clearances according to the contract.
f.Provide drawings with at lea st the following information:
1.Site Plan of the work area showing permanent support structures (piers and abutments); roads; railroad tracks; waterways; overhead and underground utilities; and other information pertinent to erection.
2.Erection sequen ce for all members, noting any temporary support conditions, such as holding crane positions, temporary supports, falsework etc. Member reference marks, when reflected on the erection plans, should be the same used on the shop drawings.
3.Primary member delivery location and orientation.
4.Maintenance of Traffic during erection operations.
5.Location of each crane for each primary member pick, showing radius and crane support (barges, mats, etc.).
6.Capacity chart , Counter Weights, Make and Model for each possible lifting equipment configuration and boom length used in the work.
7.Center of gravity locations for primary member.
8.Rigging weights, capacity and arrangement for primary member picks.
9.Lifting weight of primary member picks, including all rigging and pre -attached elements. 501.05 317 (10) Details of any temporary lifting devices to be bolted or welded to permanent members, including method and time (shop or field) of attachment; capacity; and method, time, and responsibility for removal.
11.Blocking details for bridge bearings.
12.24 Hour Contact Phone Number of the Signatory Engineer and QCR (if designated) .
5.Jacking and support of existing structures as specified below:
a.Support the structure on temporary supports and brace as necessary to maintain structural stability and prevent lateral movement until completion of the permanent supports. Do not rely on jacks lifting system alone,(e.g. hydraulic system), to support the structure except during the actual jacking operation. Remove all temporary supports upon completion of the jacking procedure.
b.Maintain a maximum differential jacking heigh t of 1/4 inch between any adjacent beam lines.
c.Maintain a maximum differential jacking height of 1 inch between any adjacent abutments or piers.
d.Place jacks and any load plates at least 2 inches from the edges of any concrete substructure seats.
e.Do not field weld temporary members to permanent steel members.
f.Maintain temporary horizontal and vertical clearances according to the contract.
6.When the total load applied to a structure during construction, (new or structure being rehabilitated), e xceeds 75 percent of the legal limit, (The Legal Limit is 80,000 lbs. or percentage thereof if posted), the load effects on the structure shall be analyzed based on the operating level calculated by the Load Factor Rating Method as given in the AASHTO Manu al for Bridge Evaluation.
7.Structures for maintaining traffic in accordance with Item 502.
a.For structures located over or within 14 feet of railroad tracks, submit plans in accordance with 501.05.A.
b.Perform Work according to 501.05.B.6 .
C.Corrective Work . Unless otherwise noted, before performing corrective work on structure items, 507,511,513,515,516,517 and 524, prepare a Corrective Work Plan (CWP ). Submit three copies of the CWP to the Engineer for acceptance 30 days, or less at the discretion of the Engineer before construction begins. Have an Ohio Registered Engineer prepare, sign, seal and date each CWP. Obtain Department acceptance before beginning corrective work Perform all Work in accordance with the accepted CWP. Immediately cease all operations that deviated from the accepted CWP. If a deviation is necessary, furnish the Engineer three copies of a revised CWP. The revised CWP shall be signed, sealed and dated by an Ohio Registered Engineer. Obtain Department acceptance of revised CWP prior to performi ng corrective work. 501.06 318 Perform all corrective work, including the preparation of the CWP and revisions at no expense to the Department. The Contractor shall reimburse the Department for all CWP review costs of the Designer of Record. The Department will cons ider delays resulting from all corrective work as non -excusable in accordance with 108.06E .