ITEM 511 CONCRETE FOR STRUCTURES
511.01 Description. This work consists of providing falsework and forming, furnishing, placing,
consolidating, finishing, and curing portland cement concrete. This work also includes diamond saw cutting longitudinal grooves into the surface of superstructure concrete. Construct falsework and forms as required in Item 508.
511.02 Materials. Furnish materials conforming to 499.02, except as modified below.
Use the same kind and color of aggregate for all concrete above the ground line in a given substructure unit and for all concrete in a given superstructure. Use high molecular weight methacrylate resin sealer conforming to 705.15. Use curing materials conforming to 705.05; 705.06 (white opaque); or 705.07;Type 1 or 1D. Use 1/4 -inch (6 mm) gray sponge joint filler conforming to 711.28, or use preformed filler conforming to 705.03. Use preformed elastomeric compression joint seals conforming to 705.11.
511.03 Concrete. Provide concrete for structures according to 499.03, using Class QC 1, QC 2, QC
3, or QC 4 or QC 5 as specified in the Contract. Mix concrete according to 499.08. At least 10 days before placing concrete, submit, in writing, the Department accepted Job Mix Formula (JMF) to the Engineer. The Engineer will review the mix design for conformance to contract requirements; otherwise the mix design is for the Engineer’s information.
511.04 Quality Control Requirements. When the concrete bid item requires QC/QA, develop and
submit a Quality Control plan (QCP) for the work and perform quality control testing of the concrete conforming to Item 455. When the concrete bid item requires QC/QA, The Engineer will perform Quality Assurance conforming to Item 455. When the concrete bid item does not require QC/QA, the Engineer will make at least one set of acceptance test cylinders for each 50 cubic yards of concrete. With any 511 concrete bid item provide and maintain a Concrete Cylinder Curing Box (CCCB) capable of holding at least twelve 4 × 8 inch cylinders at a temperature of 60 to 80 F degrees no matter what the ambient temperature. Provide a max -min thermometer with each CCCB to ensure these temperature requirements are met. The box will have a sealed lid. If the project has numerous 511 concrete bid items, one CCCB may be used for multiple items of work. Locate the CCCB at a site that is convenient to the concrete work and will eliminate handling damage to both the Contractor QC or QA cylinders and the Department Cylinders . Move the CCCB as needed during the project when the distance from the concrete work increases the possibility of cylinder handling damage.
511.05 Mass Concrete Requirements. For concrete components with a minimum dimension of
5-ft or greater, develop a concrete mix design QC-4 for mass concrete according to 499.03. Develop a Thermal Control Plan (TCP) to control placement of the mass concrete so that the highest maximum internal temperature of the placed concrete is not greater than 160 F and the maximum differential concrete temperature does not exceed 36 F over 28 days from time of placement. For drilled shafts with a dimension of 7-ft diameter or greater, develop a concrete mix design QC-4 for mass concrete, QC 4 according to 499.03. Develop a TCP to control placement of the mass concrete so that the highest maximum internal temperature of the placed concrete is not greater than 160 F. Submit the TCP to the Engineer for acceptance at least 10 calendar days prior to placement along with the approved JMF (s). As a minimum, the TCP shall include the following information:
511.06 Slump. Within the slump ranges specified in 499.03, provide a slump that produces concrete
that is workable in the required position, flows around reinforcing steel, and coats individual particles of coarse aggregate with mortar containing the proportionate amount of sand.
511.07 Placing Concrete. Submit to the Engineer a description of proposed placing procedures and
notify the Engineer at least 24 hours in advance of placing concrete. If the concrete bid item requires QC/QA, include the submittal as part of the QCP. Place and finish concrete to the lines and grades shown in the plans. Provide coverage over or around reinforcing steel as described in 509.04. Conform to the following tolerances from plan dimensions: TABLE 511.07-1 - PLACEMENT TOLERANCES Deviation from plumb for exposed surfaces ± ¾ inch (19 mm) Vertical alignment (Deviation from a line parallel to the grade line) ± ½ inch in 20 feet (13 mm in 6 m) Max. ±1 inch (25 mm) Longitudinal alignment (Deviation from a line parallel to the centerline or baseline) ±½ inch in 20 feet (13 mm in 6 m) Max. ±1 inch (25 mm) Width dimensions of walls for exposed surfaces ±½ inch (13 mm) Bridge Slab thickness ±¼ inch (6 mm) Elevations of beam seats ±1/8 inch (3 mm) Slope, Vertical Deviation from Plane ±0.2% Slope, Horizontal Deviation from Plane ±0.4% Until discharged in the work, ensure the temperature of bridge deck concrete does not exceed 85 F (30 C) and ensure that the temperature of all other concrete does not exceed 95 F (35 C). When placing superstructure and approach slab concrete assure the ambient air temperature is 85 °F (30 °C) or less and not predicted to go above 85 °F (30 °C) during the concrete placement; and evaporation rates, determined according to Figure 1 in ACI 308-81, do not exceed 0.1 lbs/ft2/hour (0.5 kg/m2/hour). Determine and document the ambient air temperature, concrete temperature, deck surface temperature, relative humidity, and wind velocity, subject to verification by the Engineer. Measure data required in Figure 1 from within 10 feet (3 m) of the area where the superstructure concrete is placed. Figure 1 does not apply to substructure items and formed parapets. Figure 1 applies to slip -formed parapets and approach slabs. To meet favorable atmospheric conditions, ODOT may require the Contractor to place concrete at night. At least 24 hours before placing concrete at night, submit a lighting plan for the work area to the Engineer. Obtain the Engineer’s approval of the lighting plan before placing the concrete. Direct lights so that approaching traffic is not affected or distracted. Before placing a concrete deck on continuous steel beams or girders, complete all of the main beam or girder splices at least two piers beyond the pier or piers supporting the concrete. Before placing concrete for backwalls above the approach slab seat with steel expansion joints, backfill the abutments to within 2 -feet (0.6 m) of the bridge seat elevation, erect structural steel or prestressed concrete beams and place superstructure conc rete in the adjacent span. Use the steel expansion joint as a template for the top of the backwall. If temporary bolts are used to support the backwall portion of an expansion device during the placing of the backwall concrete, remove the bolts after the c oncrete has taken its initial set and before a change in temperature causes superstructure movement sufficient to damage the backwall. Before placing concrete, assure the Engineer of an adequate and uniform source of supply of concrete to allow proper placing and finishing, and of the availability of coverings to protect the concrete from rain. Do not add or apply water to the concrete after it has left the truck and before applying curing materials according to 511.13. Before placing concrete, thoroughly clean all forms and structural steel that contact the concrete and ensure that the space to be occupied by the concrete is free of laitance, silt, dirt, shavings, sawdust, loose and built-up rust, and other debris. Deposit concrete using methods that ensure reinforcing steel is completely enveloped in concrete mortar and that allow inspection of concrete enveloping the reinforcing steel. Use a method or device to convey the concrete from the mixer to the work that pr events coarse aggregate separating from the mortar. If depositing concrete in shallow members, such as slabs, place it with as short a vertical drop as possible. Place the concrete over a section to maintain a practically horizontal surface. If using a chute, slope the chute to allow concrete to flow without segregation. Place concrete as near as possible to its final position. Drop concrete into the forms with a free-fall distance of 5 feet (1.5 m) or less. As necessary, use drop chutes to limit the free fall to 5 feet (1.5 m) and to ensure the delivery ends as vertical as possible. For concrete delivered to the point of placement by means of pumping equipment, ensure the air content at the point of placement is within the specified parameters of Table 499.03-1. Adjust the pumping pressure, boom angles and use pumping aids to lower the friction in the piping to meet the specified parameters. Provide a hose at the end of the line that is at least 0.5 inch (12 mm) smaller in diameter than the line on the boom to minimize free-fall and maintain a continuous flow of concrete in the pipe lines and boom during discharge. Deliver and distribute the concrete at a uniform and adequate rate no more than 10 feet (3 m) directly in front of the finishing machine by suitable mechanical equipment. For structures with a skew angle greater than fifteen (15) degrees, Orient the finishing machine according to 511.16. For structures with a skew angle greater than fifteen (15) degrees and up to fifty (50) degrees, load the concrete at the skew angle. For structures with a skew angle greater than fifty (50) degrees, load the concrete as close to the skew angle of the structure as possible, but do not allow the leading edge of the concrete placement to exceed twenty (20) feet (6.1 m) ahead of the finishing machine. Place concrete in structures using vibration. Furnish and use sufficient vibration equipment of the type and size approved by the Engineer to properly compact the concrete immediately after it is placed in the forms. The vibrators shall generally be of a type that is applied directly to the concrete and have a frequency of at least 4500 impulses per minute. If the concrete is inaccessible fo r this method of vibration, apply the vibrators to the outside of the forms. Do not move concrete using a vibrator. Vibrate freshly deposited concrete at the point deposited. Slowly insert and withdraw the vibrators vertically into the concrete until the concrete is thoroughly compacted but not segregated. During vibration, do not disturb partially hardened concrete. As necessary, spade along form surfaces, in corners, and in locations impossible to reach with vibrators to ensure smooth surfaces and dense concrete. Closely observe the results obtained on the first concrete placed, and, if necessary, modify the mix according to this specification to secure the best results. FIGURE 1 ACI 308-81
511.08 Slipform Construction of Bridge Railing. If slipforming, provide finished concrete
conforming to the following tolerances from plan dimensions: TABLE 511.08-1 SLIPFORMED BRIDGE RAILING TOLERANCES Reinforcing steel cover -1/2 inch, +1/2 inch (-13 mm, +13 mm) Top width dimension -0, +1/4 inch (+6 mm) Bottom width dimension -0, +1/2 inch (+13 mm) Surface flatness 1/4 inch in 10 feet (6 mm in 3 m) Vertical alignment (Deviation from a line parallel to the grade line) 1/2 inch in 20 feet (13 mm in 6 m) Max. ±1 inch (25 mm) Tie all joints and splices in bridge railing reinforcing steel. Before placing concrete, perform a slipforming dry run to verify reinforcing clearance and rigidity of the reinforcing cages. Adjust and stabilize the cage as necessary to establish the required clearances and to ensure the cage will not move during slipforming. The Contractor may add any additional diagonal reinforcing steel between the front and rear vertical reinforcing faces to establish the required rigidity. Repair or patch honeycombing, cracking, tearing, and other defects immediately after concrete exits the slipform equipment. Completely fill defects with concrete without using water to smooth or close the surface. If the slipforming exhibits more than infrequent defects, stop work and make adjustments to produce a slipformed surface that does not require repairs. Do not broom finish the surface of the bridge railings. After the concrete initially sets, but before any shrinkage cracks develop, saw control joints 1 1/4 inches (32 mm) deep into the perimeter of the parapet. Generally, initial set is within 6 hours of batching of the concrete. Ensure that all control joints are sawed within 24 hours of placement. Saw control joints using an edge guide, fence, or jig to ensure that the joint is straight, true, and aligned on all faces of the parapet. The joint width shall be the width of the saw blade, a nominal 1/4 inch (6 m m). After the concrete curing period specified in Item 511.13 has been reached, before applying construction loads on the deck (excluding personnel, hand operated equipment and manually powered vehicles) and before allowing vehicle traffic in the lane immediately adjacent to median bridge railing saw cut each control joint at least 4 inches deep around the perimeter of the front face, top and back face of the top portion of parapet, no lower than 12 and ½ inches above the top of the concrete deck slab. Caulk the control joints with a polyurethane or polymeric material conforming to ASTM C920, Type S. Slip formed concrete requires different slumps than those listed in Item 499 or other plan specified concrete. Provide a slump such that the concrete exiting the slipform does not pull but is stiff enough to prevent waviness and sags in the finished surfaces. Cure slipform concrete according 511.13, Method
511.09 Construction Joints. A construction joint is a plane separating concrete placements that
reach initial set at different times. Place construction joints in the locations shown in the plans. Construction joints shall have a non -finished surface, a formed finish surface or a roughened finish surface. Provide a non -finished surface on horizontal joints and a formed finished on vertical joints unless otherwise specified. A non -finished surface shall have uniformly exposed aggregate, no loose aggregate and all laitance removed. When placing concrete against an existing surface, placed in a previous project, the Department will consider the construction joint created to be a formed finish surface unless otherwise specified in the plans. All construction joint form work and bulkheads shall be in accordance with Item 508. Do not use an edger on construction joint edges. Cure the construction joints according to 511.13. A roughened construction joint surface, when specified in the plans, shall be as follows:
511.10 Work Stoppage. If the work is unexpectedly interrupted by breakdowns, storms, delays or
other causes which will result in an initial set of the placed concrete, rearrange the freshly deposited concrete to provide a straight and non-wavy construction joint per 511.09. If the Engineer determines that this construction joint adversely affects the structure capacity, the Engineer will require a corrective action plan per 501.05.C.
511.11 Depositing Concrete Under Water. Except for cofferdam seals and drilled shafts, do not
place concrete under water.
511.12 Depositing and Curing Concrete During Cold Weather . If placing concrete when the
atmospheric temperature is below 36 °F (2 °C), or if weather forecasts predict these temperatures during the curing period, follow the procedures of this subsection. Heat the water or aggregate, or both, as necessary to produce concrete with a temperature when placed of at least 50 °F (10 °C) but not greater than 70 °F (21 °C). Place concrete against materials with a temperature of greater than 32 °F (0 °C). If necessary, heat the forms, reinforcing steel, and foundation materials before placing the concrete. Maintain the concrete surface temperature between 50 and 100 °F (10 and 38 °C) for a period of not less than 5 days, except as modified in 511.12.C. After the minimum cure period of 5 days, reduce the concrete surface temperature at a rate not to exceed 20 °F (11 °C) in 24 hours until the concrete surface temperature is within 20 °F (11 °C) of atmospheric temperature. Install sufficient high-low thermometers to readily determine the concrete surface temperature. For deck slabs, install high-low thermometers to measure deck bottom surfaces, deck fascia surfaces, and deck top surfaces. Maintain the concrete curing temperature using a heated enclosure, insulated forms, or by flooding, except cure deck slabs less than 10 inches (250 mm) thick using more than just insulated forms when temperatures are predicted to fall below 33 °F (0.5 °C). Remove falsework and open cold weather concrete to traffic according to 511.14.
511.13 Curing. Cure concrete as follows:
TABLE 511.13-1, CURING REQUIREMENTS Location Curing Method [1] Superstructure concrete Method A Concrete to which sealer is applied Method A Construction joints Method A Top surface of concrete deck superstructure concrete Method A followed by Method B Concrete with waterproofing Method A or Method B All other concrete Method A or Method B [1] Method A is water curing. Method B is membrane curing. If using Method B on areas to be waterproofed, remove the curing membrane. Concrete curing methods are as follows:
511.14 Application of External Loads to New Concrete, Removal of Forms, Removal of
Falsework and Opening to Traffic.
511.15 Surface Finish. For concrete that is to be sealed with Epoxy-Urethane according to 512.03,
perform surface profiling and surface finish according to 512.03.F. For all others, finish the concrete surface as detailed below:
511.16 Roadway Finish. Finish and test concrete deck slabs according to 451.13. Do not groove or
broom finish a strip of surface 9 to 12 inches (220 to 300 mm) wide adjacent to curbs and barriers. Provide a broom drag finish on concrete deck slabs in the longitudinal or transverse direction. The Engineer will approve the finishing machine. Provide a self-propelled machine with forward and reverse drive mechanisms that enable precise control of machine velocity in both directions. The machine shall have two rotating rollers, leveling augers, and either a vibrating pan or vibrating rollers. Field verify that the vibrating frequency of the pans or rollers are from 1500 to 5000 pulses per minute. Do not use vibrating rollers that have fins protruding more then 1/4 inch (6 mm) from the roller. Use a finishing machine capable of finishing transversely while traveling in both directions across the deck. Provide screeds capable of rising above the concrete surface. Provide a finishing machine capable of finishing the full width of the decks between curbs or parapet walls. The wheels of the finishing machine shall run on temporary riding rails adequately supported on the structural steel or falsework of the deck. Make the rail and rail supports of steel and arrange the rail and rail supports so that the weight of the finishing machine and the operator cause zero vertical deflection while traveling across the deck. Ensure the rail is straight, with no sections exceeding a tolerance of 1/8 inch in 10 feet (3 mm in 3 m) in any direction. Elevate support rails a sufficient distance above the slab to allow the simultaneous hand finishing of areas not machine finished. Fabricate and install rail supports to allow removal to at least 2 inches (50 mm) below the top of the slab. Fill holes formed by the removal of rail supports during the final finishing of the slab. For structures with a skew angle greater than fifteen (15) degrees and up to fifty (50) degrees, place the finishing machine within 5°of the skew angle of the structure. For structures with a skew angle greater than fifty (50) degrees, place the finishing machine at fifty (50) degrees.
511.17 Bridge Deck Grooving. After water curing the concrete and either before applying curing
compound or some period after applying curing compound and before opening the bridge to traffic, saw longitudinal grooves into the deck, unless specified otherwise in the plans. If sawing grooves after applying the curing compound and the concrete deck is less than 30 days old, reapply the curing compound after removing standing water, within 12 hours after sawing grooves in the deck. Use diamond blades mounted on a multi -blade arbor on self-propelled machines that were built for grooving of concrete surfaces. The groove machines shall have depth control devices that detect variations in the pavement surface and adjust the cutting head height to maintain the specified depth of the groove. The grooving machines shall have devices to control alignment. Do not use flailing or impact type grooving equipment. More than one size grooving machine may be required in order to saw the grooves as specified. Maintain a minimum of ¾ inch (19 mm) to a maximum of 2 ¼ inches (56 mm) transverse distance between adjacent passes of the grooving machine head. Provide an experienced technician to supervise the location, alignment, layout, dimension, and grooving of the surface. Saw grooves parallel to the bridge centerline in a continuous pattern across the surface. Begin and end sawing 9 to 12 inches (220 to 300 mm) from any device in place in a bridge deck, such as scuppers or expansion joints. Stop sawing a minimum of 2 inches (50 mm) to a maximum of 24 inches (600 mm) from skewed expansion joints. Maintain a clearance of a minimum of 2 inches (50 mm) and a maximum of 4 inches (100 mm) from the grooves to longitudinal joints in the deck. Maintain a minimum clearance of 9 inches (220 mm) to a maximum of 30 inches (750 mm) clearance between the grooves and the curb or parapet toe. However, at no point shall un -grooved portions of deck extend beyond edge line and into the temporary or permanent travelled lanes. Saw grooves in a uniform pattern spaced at 3/4 inch minus 1/4 inch or plus 0 (19 mm minus 6 mm or plus 0). Saw grooves approximately 0.15 inches (4 mm) deep and 0.10 inches (3 mm) wide. For staged, or phase bridge deck work, saw the grooves parallel to the final, permanent bridge centerline. If the different stages or phases of the bridge deck work occur within one construction season, any stage opened to traffic shall receive an interim coarse broom finish during placement, then saw the longitudinal grooves after the final stage. The interim broom finish will not be allowed as a surface texture when opened to traffic over a winter season. Saw longitudinal grooves in the deck prior to opening to traffic for a winter season. For bridge decks that widen from one end to the other, saw the longitudinal grooves parallel to the centerline of the roadway. On the side of the bridge that widens, saw the longitudinal grooves to follow the edge line. Saw longitudinal grooves in the gore areas, avoiding the overlapping of grooves. At the beginning of each work shift, furnish a full complement of grooving blades with each saw that are capable of cutting grooves of the specified width, depth, and spacing. If during the work, a single grooving blade on a machine becomes incapable of cutting a groove, continue work for the remainder of the work shift. The Contractor is not required to cut the groove omitted because of the failed blade. Should two or more grooving blades on a machine become incapable of cutting grooves, cease operating the machine until it is repaired. Continuously remove all slurry and remaining residue from the grooving operation and leave the deck surface in a clean condition. Prevent residue from grooving operations from flowing across shoulders or across lanes occupied by public traffic or from flow ing into gutters or other drainage facilities. Remove solid residue before the residue is blown by passing traffic or by wind. Provide water as necessary to saw grooves according to this subsection.
511.18 Sidewalk Finish. After placing, strike off the concrete with a template and finish the concrete
with a float to produce a sandy texture.
511.19 Joints, Cracks, Scaling and Spalls.
511.20 Compressive Strength. Sample and test concrete strength according to 511.04.
499.03 and 511.04. Pay factors under 511.22 for these low strength sublots will be based on the original
reported cylinder strengths.
511.21 Air Content . For concrete that requires QC/QA, test the air content of the concrete
according to Item 455. When QC/QA concrete is not required, the Department will test the air content as directed by the Engineer.
499.03 1 that is placed into the structure is unacceptable material according to item 106.07. The amount
of unacceptable material will be the amount represented by the test result. Reevaluate the unacceptable material at no cost to the Department as follows:
499.03 1 that is placed into the structure is unacceptable material, according to item 106.07. The
amount of unacceptable material will be the amount represented by the test result. Reevaluate the unacceptable material at no cost to the Department as follows:
511.22 Pay Factors. Apply pay factors as follows:
511.23 Method of Measurement. The Department will measure the appropriate concrete item by
the number of cubic yards (cubic meters) determined by calculations from plan dimensions, in place, completed and accepted. The Department will make deductions for portions of primary structural members embedded in concrete. The Department will not make deductions for the volume of reinforcing steel, conduits or embedded piles. Superstructure concrete includes the concrete in deflective parapets not having a metallic railing. The Department may measure deck concrete by either volume or area using plan dimensions. The Department will calculate separate quantities of concrete due to unacceptable compressive strength, 511.21 and air content, 511.22.
511.24 Basis of Payment. The Department will pay for accepted quantities of concrete as follows.
Work necessary to adjust seat elevations and deck haunches for prestressed beam members is incidental to the affected structural concrete items. The Department will pay for final quantities as measured and field verified. The Department will not pay for additional reinforcing steel required to adequately stabilize the cages. The Department will not pay for repairs to horizontal cracks by epoxy injection or, if a concrete sealer was applied, for repairs to the sealer after the completing the epoxy injection. The Department will not pay extra for any type of surface finish specified in 511.15, the cost being considered as included in the price bid for concrete. If the Contractor elects to saw the deck after applying the curing compound, the Department will not pay to reapply the curing compound. All costs for sealing as specified in 511.19 .A are incidental to the appropriate concrete item. The Department will not pay separately for the concrete cylinder curing box (CCCB). The Department will not pay for the re-evaluation of low strength test results, 511.20.A. The Department will initially pay the full bid price to the Contractor upon completing the work. The Department will calculate the final adjusted payment for each item as follows: PF1 - The final adjusted pay per cubic yard (cubic meter) or square yard (square meter), for accepted quantities of concrete: PF1 = (Contract Bid Price) x PFC PF2 - The final adjusted pay per cubic yard (cubic meter) or square yard (square meter) for unacceptable quantities of concrete due to compressive strength or low air content and allowed to stay in place, according to 511.20 or 511.21. PF2 = (Contract Bid Price) x 0.75 Calculate the adjusted price per bid item by multiplying PF1 or PF2 by the appropriate quantities of concrete, then sum the values. Subtract the full bid price paid to the Contractor from the adjusted price to determine the difference. The Department will execute final adjustments by change order upon receipt of all test data. The Department will pay for accepted quantities at the contract prices as follows: Item Unit Description 511 Cubic Yard Class ___ Concrete, _____ (Cubic Meter) 511 Cubic Yard Class ___ Concrete, _____ with QC/QA (Cubic Meter) 511 Cubic Yard Class QC 1 Concrete, Substructure (Cubic Meter) 511 Cubic Yard Class QC 1 Concrete, Substructure with (Cubic Meter) QC/QA 511 Cubic Yard Class QC 2 Concrete, Bridge Deck (Cubic Meter) Square Yard (Square Meter) 511 Cubic Yard Class QC 2 Concrete, Bridge Deck with (Cubic Meter) QC/QA Square Yard (Square Meter) 511 Cubic Yard Class QC 2 Concrete, Bridge Deck (Parapet) (Cubic Meter) 511 Cubic Yard Class QC 2 Concrete, Bridge Deck (Parapet) (Cubic Meter) with QC/QA 511 Cubic Yard Class QC 3 Concrete, _____ with QC/QA (Cubic Meter) 511 Cubic Yard Class QC 4 Mass Concrete, Substructure with (Cubic Meter) QC/QA
Concrete for Structures in other states
Get an email when 511 changes
Ohio revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.