B
HomeLibrariesCopilotSearchProjectsBookmarks
FeedbackHelp Desk
Libraries
Building Codes
Code LibraryIBC — BuildingIRC — ResidentialIFC — FireIPC — PlumbingIMC — MechanicalIFGC — Fuel GasIECC — EnergyNEC — ElectricalModel Codes
Specifications
CSI SpecificationsDOT SpecsTransit SpecsUSACE
Standards
TransportationRailroadFire SafetyAccessibilityStructural
Tools & References
DiagramsAssembliesProductsCalculatorsChecklistsPermits
PricingLog in
Structures (500-599)

511CONCRETE FOR STRUCTURES

OH · 2019 Standard SpecificationsBook pages 00View official source ↗

511.01 ITEM 511 CONCRETE FOR STR UCTURES

511.01 Description

511.02 Materials

511.03 Concrete

511.04 Quality Control Requirements and Mass Concrete

511.0 5 Mixing of Concrete 511.0 6 Slump

511.07 Placing Concrete

511.08 Slipform Construction of Bridge Railing

511.09 Construction Joints

511.1 0 Work Stoppage 511.1 1 Depositing Concrete Under Water 511.1 2 Depositing and Curing Concrete During Cold Weather 511.1 3 Removal of Forms 511.1 4 Curing and Loading 511.1 5 Surface Finish 511.1 6 Roadway Finish

511.17 Bridge Deck Groo ving

511.18 Sidewalk Finish

511.19 Joints , Cracks , Scaling and Spalls

511.2 0 Compressive Strength

511.21 Air Content

511.22 Pay Factors

511.2 3 Method of Measurement 511.2 4 Basis of Payment

511.01 Description. This work consists of providing fa lsework and forming,

furnishing, placing, consolidating, finishing, and curing portland cement concrete. This work also includes diamond saw cutting longitudinal grooves into the surface of superstructure concrete. Construct falsework and forms as required in Item 508.

511.02 Materials. Furnish materials conforming to 499.02, except as modified

below. Use the same kind and color of aggregate for all concrete above the ground line in a given substructure unit and for all concrete in a given superstructure. Use high molecular weight methacrylate resin sealer conforming to 705.15. Use curing materials conforming to 705.05; 705.06 (white opaque); or 705.07;Type 1 or 1D. Use 1/4 -inch (6 mm) gray sponge joint filler conforming to 711.28, or use preformed filler c onforming to 705.03. Use preformed elastomeric compression joint seals conforming to 705.11. 511.03 343 511.03 Concrete . Provide concrete for structures according to 499.03, using Class QC 1, QC 2, QC 3 or QC 4 as specified in the Contract. At least 10 days before placing concrete , submit, in writing, the Department accepted Job Mix Formula (JMF) to the Engineer. The Engineer will review the mix design for conformance to contract requirements; otherwise the mix design is for the Engineer’s information.

511.04 Quality Control Requirements and Mass Concrete . When the concrete

bid item requires QC/QA, develop and submit a Quality Control plan (QCP) for the work and perform quality control testing of the concrete conforming to Item 455. When the concrete bi d item requires QC/QA, The Engineer will perform Quality Assurance conforming to 455. When the concrete bid item does not require QC/QA, the Engineer will make acceptance test cylinders as follows: Structures of 20 -foot (6.1 m) span or less. At least one set of test cylinders for each 50 cubic yards (35 m³) of concrete. Structures over 20 -foot (6.1 m) span. A set of test cylinders from each 200 cubic yards (150 m³) of concrete, or fraction thereof that is incorporated into the work each day. With any 511 concrete bid item provide and maintain a Concrete Cylinder Curing Box (CCCB) capable of holding at least twelve 4 × 8 inch (1 00 × 200 mm) cylinders at a temperature of 60 to 80 F (15 to 27 C) degrees no matter what the ambient temperature . The box will have a sealed lid. If the project has numerous 511 concrete bid items CCCB are not required for each bid item. Locate the CCCB at a site that is convenient to the concrete work and will eliminate handling damage to both the Contractor QC or QA cylinde rs and the Department Cylinders. Move the CCCB as needed during the project when the distance from the concrete work increases the possibility of cylinder handling damage.

A.Mass Concrete Requirements . For concrete components with a minimum dimension of 5-ft (1.5 -m) or greater, develop a concrete mix design QC -4 for mass concrete according to 499.03. Develop a Thermal Control Plan (TCP) to control placement of the mass concrete so that the highest maximum internal temperature of the placed concrete is no t greater than 160 F (71 C) and the maximum differential concrete temperature does not exceed 36 F (20 C) over 28 days from time of placement. For drilled shafts with a dimension of 7 -ft (2.1 -m) diameter or greater, develop a concrete mix desig n QC -4 for mass concrete, QC 4 according to

499.03 Develop a TCP to control placement of the mass concrete so that the

highest maximum internal temperature of the placed concrete is not greater than 160 F (71 C). Submit the TCP to the Enginee r for acceptance at least 10 calendar days prior to placement along with the approved JMF (s). As a minimum, the TCP shall include the following information: 511.05 344 1. Duration and method of curing.

2.Procedures to control concrete temperature at the time of placement. The mix shall contain no frozen pieces of ice after blending and mixing components.
3.Methods and equipment used for controlling temperature differentials.
4.Temperature sensor types, locations and installation details. As a minimum, concret e temperatures shall be monitored at the calculated hottest location, on at least 2 outer faces, 2 corners, and top surfaces.
5.Temperature monitoring and recording system; operation plan; recording and reporting plan with example output; and a remedial action plan.
6.Criteria for form removal to control the maximum temperature differential. As an alternative to the maximum differential concrete temperature specified above, the Contractor may propose maximum differential temperature limits based on stre ngth gain with time. The TCP for the alternative proposal shall include the methods used to determine the temperature and supporting data and design to support the accuracy of the method chosen. Provide complete calculations and basis for increasing the ma ximum differential temperature specification. The TCP for the alternative proposal shall also provide the Engineer with tables that define ambient temperatures for acceptable concrete placement, the required temperature of the concrete for the ambient air temperature, the maximum predicted concrete temperature, the maximum predicted differential temperature, the time for removal of forms, the allowable air temperature for form removal, and the predicted maximum and differential temperature from placement to age of 28 days. The Department will consider all cracking of a mass concrete placement where the differential temperature exceeded 36 F (20 C) the responsibility of the Contractor. Upon the Engineer’s acceptance of the TCP, continuously monitor all temperature sensors over the required age of the concrete. If the maximum limit or differential temperature limits are exceeded at any time, immediately take action to retard and reduce the out -of-specification temperatures. If a mass concrete placemen t temperature exceeds the specification limits of the currently accepted TCP, re -engineer, revise and resubmit the TCP. Do not place additional mass concrete until the revised TCP is accepted. The Department will consider in -place mass concrete that exceed s the temperature limits or that cracked, as defective and resulting delays as non - excusable. Determine the extent and effect of the damage and submit a proposed repair plan to the Engineer to return the concrete to acceptable quality. The Department will determine if the proposed repair methods are acceptable or if removal is required. 511.0 5 Mixing of Concrete. Mix concrete according to 499. 08. 511.0 6 Slump. Within the slump ranges specified in 499.03, provide a slump that produces concrete that is workab le in the required position, flows around reinforcing steel, and coats individual particles of coarse aggregate with mortar containing the proportionate amount of sand . 511.07 345 511.07 Placing Concrete. Submit to the Engineer a description of proposed placing proce dures and notify the Engineer at least 24 hours in advance of placing concrete. If the concrete bid item requires QC/QA, include the submittal as part of the QCP. Place and finish concrete to the lines and grades shown in the plans. Unless otherwise noted, the proposed beam seat elevations shown in the plans for prestressed beam superstructures are based on the design midspan camber for prestressed beams which are 30 days old (D 30). Adjust each beam seat elevation using measured midspan camber data provided by the fabricator if available. In the absence of measured midspan camber, adjust each beam seat elevation using the following: ΔY = D t – D30 ≥ 0 Where: ΔY = Distance that each seat elevation shall be lowered from plan elevation to account for midspan cam ber growth rounded to the nearest 1/8 -inch Dt = (1 + ψ) D 0 D30 = Design Midspan Camber at Day 30 provided in the plans; inch D0 = Design Midspan Camber at Day 0 provided in the plans; inch ψ = 1.97 K S KF KTD KS = 1.45 – 0.13 (V/S) ≥ 1.0 V/S = Ratio of the prestressed concrete member’s volume -to-surface area exposed to the atmosphere. For each of the standard I -beam sections, this ratio is provided on PSID -1-13; inch KF = 5/(1 + f′ ci) f′ci = Compressive strength of prestressed concrete at release prov ided in the plans; ksi KTD = t/(61 - 4 f′ ci + t) t = Age of prestressed concrete measured between release of prestressing force ( eg. 0.75 days) and time of deck placement; days Provide the Engineer with revised plan sheets and Design Camber calculations or measured camber data signed, sealed and dated by an Ohio Registered Professional Engineer at least 7 days prior to constructing the beam seats. The revised plan sheets shall include the measured camber data (if available), Design Camber (D t) and beam age (t) assumed for establishing the revised elevations. Provide haunch reinforcement for prestressed I -beam members according to the ODOT Bridge Design Manual, Figure 302.5.2.3 -2 as necessary to extend the beam’s composite reinforcement at least two inches in to the deck thickness. All revisions resulting from adjusted beam seat elevations shall be clearly marked as revised. Do not begin work until the Engineer approves the revised plan. Provide coverage over or around reinforcing steel as described in 509.04. 511.07 346 Conform to the following tolerances from plan dimensions: TABLE 511.07 -1 PLACEMENT TOLERANCES Deviation from plumb for exposed surfaces ± ¾ inch (19 mm) Vertical alignment (Deviation from a line parallel to the grade line) ± ½ inch in 20 feet (13 mm in 6 m) Max. ±1 inch (25 mm) Longitudinal alignment (Deviation from a line parallel to the centerline or baseline) ±½ inch in 20 feet (13 mm in 6 m) Max. ±1 inch (25 mm) Width dimensions of walls for exposed surfaces ±½ inch (13 mm) Bridge Slab thickness ±¼ inch (6 mm) Elevations of beam seats ±1/8 inch (3 mm) Slope, Vertical Deviation from Plane ±0.2% Slope, Horizontal Deviation from Plane ±0.4% Until discharged in the work, ensure that the temperature of all concrete does not exceed 95 F (35 C). When placing superstructure and approach slab concrete assure the ambient air temperature is 85 °F (30 °C) or less and not predicted to go above 85 °F (30 °C) during the concrete placement; and evaporation rates, determined according to Figure 1 in ACI 308 -81, do not exceed 0.1 lbs/ft2/hour (0.5 kg/m2/hour) . Determine and document the ambient air temperature, concrete temperature, deck surface temperature, relative humidity, and wind velocity, subject to verification by the Engineer. Meas ure data required in Figure 1 from within 10 feet (3 m) of the area where the superstructure concrete is placed. Figure 1 does not apply to substructure items and formed parapets. Figure 1 applies to slip -formed parapets and approach slabs . To meet favora ble atmospheric conditions, ODOT may require the Contractor to place concrete at night. At least 24 hours before placing concrete at night, submit a lighting plan for the work area to the Engineer. Obtain the Engineer’s approval of the lighting plan before placing the concrete. Direct lights so that approaching traffic is not affected or distracted. Before placing a concrete deck on continuous steel beams or girders, complete all of the main beam or girder splices at least two piers beyond the pier or piers supporting the concrete. Before placing concrete for backwalls above the approach slab seat with steel expansion joints, backfill the abutments to within 2 -feet (0.6 m) of the bridge seat elevation, erect structural steel or prestressed concrete beams and place superstructure concrete in the adjacent span . Use the steel expansion joint as a template for the top of the backwall. If temporary bolts are used to support the backwall portion of an expansion device during the placing of the backwall concrete, remove the bolts after the concrete has taken its initial set and before a change in temperature causes superstructure movement sufficient to damage the backwall. 511.07 347 Before placing concrete, assure the Engineer of an adequate and uniform source of supply of c oncrete to allow proper placing and finishing, and of the availability of coverings to protect the concrete from rain. Do not add or apply water to the concrete after it has left the truck and before applying curing materials according to 511.14. Before pl acing concrete, thoroughly clean all forms and structural steel that contact the concrete and ensure that the space to be occupied by the concrete is free of laitance, silt, dirt, shavings, sawdust, loose and built -up rust, and other debris. Deposit concre te using methods that ensure reinforcing steel is completely enveloped in concrete mortar and that allow inspection of concrete enveloping the reinforcing steel. Use a method or device to convey the concrete from the mixer to the work that prevents coarse aggregate separating from the mortar. If depositing concrete in shallow members, such as slabs, place it with as short a vertical drop as possible. Place the concrete over a section to maintain a practically horizontal surface. If using a chute, slope the chute to allow concrete to flow without segregation. Place concrete as near as possible to its final position. Drop concrete into the forms with a free -fall distance of 5 feet (1.5 m) or less. As necessary, use drop chutes to limit the free fall to 5 feet (1.5 m) and to ensure the delivery ends as vertical as possible. For concrete delivered to the point of placement by means of pumping equipment, ensure the air content at the point of placement is within the specified parameters of Table 499.03 -1. Adjust t he pumping pressure, boom angles and use pumping aids to lower the friction in the piping to meet the specified parameters. Provide a hose at the end of the line that is at least 0.5 inch (12 mm) smaller in diameter than the line on the boom to minimize fr ee-fall and maintain a continuous flow of concrete in the pipe lines and boom during discharge. Deliver and distribute the concrete at a uniform and adequate rate no more than 10 feet (3 m) directly in front of the finishing machine by suitable mechanical equipment. For structures with a skew angle greater than fifteen (15) degrees, Orient the finishing machine according to 511 .16. For structures with a skew angle greater than fifteen (15) degrees and up to fifty (50) degrees, load the concrete at the skew angle. For structures with a skew angle greater than fifty (50) degrees, load the concrete as close to the skew angle of the structure as possible, but do not allow the leading edge of the concrete placement to exceed twenty (20) feet (6.1 m) ahead of the finishing machine. Place concrete in structures using vibration. Furnish and use sufficient vibration equipment of the type and size approved by the Engineer to properly compact the concrete immediately after it is placed in the forms. The vibrators shall generally be of a type that is applied directly to the concrete and have a frequency of at least 4500 impulses per minute. If the concrete is inaccessible for this method of vibration, apply the vibrators to the outside of the forms. Do not move concrete using a vibrator. Vibrate freshly deposited concrete at the point deposited. Slowly insert and withdraw the vibrators vertically into the concrete until the concrete is thoroughly compacted but not segregated. During vibration, do not disturb partially har dened concrete. 511.08 348 As necessary, spade along form surfaces, in corners, and in locations impossible to reach with vibrators to ensure smooth surfaces and dense concrete. Closely observe the results obtained on the first concrete placed, and, if necessary, mod ify the mix according to this specification to secure the best results. FIGURE 1 ACI 308 -81

511.08 Slipform Construction of Bridge Railing. If slipforming, provide

finished concrete conforming to the following tolerances from plan dimensions: 511.08 349 TABLE 511. 08-1 SLIPFORMED BRIDGE RA ILING TOLERANCES Reinforcing steel cover -1/2 inch, +1/2 inch ( -13 mm, +13 mm) Top width dimension -0, +1/4 inch (+6 mm) Bottom width dimension -0, +1/2 inch (+13 mm) Surface flatness 1/4 inch in 10 feet (6 mm in 3 m) Vertical alignment (Deviation from a line parallel to the grade line) 1/2 inch in 20 feet (13 mm in 6 m) Max. ±1 inch (25 mm) Tie all joints and splices in bridge railing reinforcing steel. Before placing concrete, perform a slipforming dry run to ver ify reinforcing clearance and rigidity of the reinforcing cages. Adjust and stabilize the cage as necessary to establish the required clearances and to ensure the cage will not move during slipforming. The Contractor may add any additional diagonal reinfor cing steel between the front and rear vertical reinforcing faces to establish the required rigidity. Repair or patch honeycombing, cracking, tearing, and other defects immediately after concrete exits the slipform equipment. Completely fill defects with co ncrete without using water to smooth or close the surface . If the slipforming exhibits more than infrequent defects, stop work and make adjustments to produce a slipformed surface that does not require repairs. Do not broom finish the surface of the bridge railings. After the concrete initially sets, but before any shrinkage cracks develop, saw control joints 1 1/4 inches (32 mm) deep into the perimeter of the parapet. Generally, initial set is within 6 hours of batching of the concrete. Ensure that all control joints are sawed within 24 hours of placement. Saw control joints using an edge guide, fence, or jig to ensure that the joint is straight, true, and aligned on all faces of the parapet. The joint width shall be the width of the saw blade, a nominal 1 /4 inch (6 mm). After the concrete curing period specified in Item 511.14 has been reached, before applying construction loads on the deck (excluding personnel, hand operated equipment and manually powered vehicles) and before allowing vehicle traffi c in the lane immediately adjacent to median bridge railingsawcut each control joint at least 4 inches (100 mm) deep around the perimeter of the front face, top and back face of the top portion of parapet, no lower than 12 and ½ inches (313 mm) above the top of the concrete deck slab. Caulk the control joints with a polyurethane or polymeric material conforming to ASTM C 920, Type S. Slip formed concrete requires different slumps than those listed in Item 499 or other plan specified concrete. Provide a slump such that the concrete exiting the slipform does not pull but is stiff enough to prevent waviness and sags in the finished surfaces. Cure slipform concrete according 511.1 4, Method A. Because slipformed concrete has a low water -cement ratio, timely a pplication of the water cure is critical in helping control shrinkage cracks. Furnish platforms as necessary to protect traffic passing under the bridge from falling debris during the slipforming operation, to allow access for completing the finishing oper ation, and to allow the Engineer access to the outside of the parapet. 511.09 350 The Engineer will inspect the slipformed surface for horizontal cracking no earlier than 21 days after completion of the slipforming operation. Repair all horizontal cracks by epoxy inj ection. If a concrete sealer was applied, repair damage to the sealer after completing the epoxy injection.

511.09 Construction Joints. If construction joints are shown on the plans, place

all concrete between consecutive joints in a continuous operation. Follow the requirements of 511.14 when placing concrete against a construction joint. Obtain the Director’s approval before placing any construction joint not shown on the plans or required by 511. 07. Before placing concrete, determine the location where t he day’s concrete placing ends. If practical, end placing the day’s concrete perpendicular to the lines of principal stress and in regions of small shear. Do not install horizontal joints in concrete girders and beams. Form construction joints using bulkhe ads with keyways. Locate keyways clear of exposed surfaces by approximately one -third the thickness of the joint. Construct transverse or longitudinal construction joints in deck slabs with keys located between the reinforcing mats and having a depth of ¾ inch (19 mm). Where practical, avoid horizontal joints in piers, abutments, and retaining walls, otherwise locate horizontal joints 2 feet (0.6 m) or more above the normal water level. For construction joints not shown on the plans and above ordinary low w ater, in abutments, and in retaining walls that retain earth fills, install a 36 -inch (1 m) strip of Type 2 membrane waterproofing according to Item 512 to the back of the joint. Avoid joints in cantilevered members. Dampen the surface of the concrete of t he horizontal construction joints immediately before placing adjoining concrete. Place and protect horizontal construction joints between bridge slabs and superimposed curbs, parapets, sidewalks, and median strips in the same manner as the remainder of the slab. Cure the construction joints according to 511. 14. Avoid disturbing the bond between protruding reinforcing steel and the deck concrete. If using the curb areas to place the deck, tie and brace the reinforcing steel to prevent its movement. Where walls or columns support slabs or beams, place concrete in wall or column to the bottom of the slab or beam and allow the concrete to settle for at least 2 hours before placing concrete in the slab or beam.

511.10 Work Stoppage. If the work is unexpectedly interrupted by breakdowns,

storms, or other causes, rearrange the freshly deposited concrete to provide a suitable construction joint. If this joint occurs at a section with shear stress, prevent a plane of weakness by providing an adequate mechanical bon d across the joint by forming a keyway, inserting reinforcing steel, or by some other means satisfactory to the Engineer. 511.11 351 511.11 Depositing Concrete Under Water. Except for cofferdam seals and drilled shafts, do not place concrete under water.

511.12 Depos iting and Curing Concrete During Cold Weather . If placing

concrete when the atmospheric temperature is 32 °F (0 °C) or less, or if weather forecasts predict these temperatures during the curing period, follow the procedures of this subsection. Heat the wat er or aggregate, or both, as necessary to produce concrete with a temperature when placed of at least 50 °F (10 °C) but not greater than 70 °F (21 °C). Place concrete against materials with a temperature of greater than 32 °F (0 °C). If necessary, heat the forms, reinforcing steel, and foundation materials before placing the concrete. Maintain the concrete surface temperature between 50 and 100 °F (10 and 38 °C) for a period of not less than 5 days, except as modified in 511.1 2.C. After the minimum cure per iod of 5 days, reduce the concrete surface temperature at a rate not to exceed 20 °F (11 °C) in 24 hours until the concrete surface temperature is within 20 °F (11 °C) of atmospheric temperature. Install sufficient high -low thermometers to readily determin e the concrete surface temperature. For deck slabs, install high -low thermometers to measure deck bottom surfaces, deck fascia surfaces, and deck top surfaces. Maintain the concrete curing temperature using a heated enclosure, insulated forms, or by floodi ng, except cure deck slabs less than 10 inches (250 mm) thick using more than just insulated forms. Remove falsework and open cold weather concrete to traffic according to 511.1 4.

A.Heated Enclosure. Construct the heated enclosure to surround the top, sid es, and bottom of the concrete. Construct strong and wind proof enclosures that contain adequate space to allow free circulation of air around the forms and concrete. Before placing concrete, construct the enclosure and heating devices to the extent allowe d by the concrete operation. As the concreting operation progresses and as soon as possible after placing concrete, complete construction of the enclosures and apply heat. Supply heat by a method that continuously maintains a reasonably uniform temperature throughout the enclosures and does not discolor the concrete. Vent combustion -type heating devices outside the enclosure. If dry heat, other than free steam, maintains the enclosure temperature, immediately cover exposed concrete with two thicknesses of b urlap. Continuously wet the burlap and, except for required rubbing of the concrete, do not remove the burlap during the heating period. If wood forms without liners are left in place more than 2 days after the placing of concrete, thoroughly wet the forms at least once each day for the remainder of the heating period. If forms are removed during the heating period, thoroughly drench the concrete with water and, for the remainder of the heating period, cover and wet the concrete with burlap as specified abo ve. 511.13 352 B. Insulation. Install sufficient thermometers to readily determine the concrete surface temperature. If the surface temperature approaches 100 °F (38 °C), loosen or otherwise vent the forms or insulation to keep the surface temperature within the limits specified above. If insulation does not maintain the minimum required temperature, promptly enclose the concrete as specified in 511.1 2.A or flood the concrete as specified in 511.1 2.C. Use a wind and water resistant insulating material. Ensure edge s, corners, and other points of extreme exposure are adequately insulated. Place a tarpaulin or other Engineer approved waterproof cover over the insulation to protect the concrete top surface.
C.Flooding with Water. The Contractor may flood the concrete with water provided flooding does not damage the concrete. Heat the water to a temperature from 50 to 100 °F (10 to 38 °C). The Contractor may stop using heated water after 48 hours if the concrete remains flooded to a depth of 1 foot (0.3 m) above its hig hest elevation for at least the next 120 hours. 511.1 3 Removal of Forms. To facilitate finishing, remove forms from vertical surfaces that receive a rubbed surface finish as soon as the concrete has hardened sufficiently that rubbing will not damage it.

511.14 Curing and Loading. Remove falsework and open structures to traffic

only after the concrete has reached the strength specified by Table 511.1 4-1A for concrete bid items requiring QC/QA. Use Table 511.14.1B for concrete items not requiring QC/QA . Do not shorten the minimum required Method A curing time regardless of strength test results. TABLE 511.14 -1A LOADING REQUIREMENTS FOR CONCRETE REQUIR ING QC/QA Span[1] Required Strength [2] Removing Falsework Any Span Compressive Strength ≥ 0.85% f’c or Flexural Strength (Center point) ≥ 650 psi (4.5 Mpa) All pier caps Traffic Any [1] Span is defined as the horizontal distance between faces of the supporting elements when measured parallel to the primary reinforcement. [2] Field cured samples. The maturity curve method may be used for determining the strength according to Supplement 1098 in lieu of field curing samples 511.14 353 TABLE 511.1 4-1B LOADING REQUIREMENTS FOR CONCRETE NOT REQUIRING QC/QA Span[1] Age of Concrete in Days No Beam Test Beam Test [2] Removing Falsework Over 10 feet (3 m) 14 5 10 feet (3 m) or less and all pier caps 7 3 Traffic Any 14 7 [1] Span is defined as the horizontal distance between faces of the supporting elements when measured parallel to the primary reinforcement. [2] Applicable only when the average modulus of rupture for two tests is not less than 650 psi (4.5 MPa). Take enough specimens to verify compliance with the strength requirements of Table 511.14 -1A. Obtain samples from the first and last sublots of continuously placed concrete for quantities of 500 yd3 or less, and one extra set of specimens for each additional 500 yd3 or fraction thereof. Obtain samples in equally spaced increments throughout the placement as directed by the Engineer. De lays in placements of more than 4 hours are not considered continuously placed and are to be treated as separate placements. If the air temperature surrounding the concrete is maintained between 32 and 50 °F (0 and 10 °C), and if the provisions of 511.12 d o not apply, maintain the concrete above 32 °F (0 °C) for 7 days or until a successful strength test conforming to Table

511.14 1A, except this time shall not be less than 5 days .

Do not apply external loads to or perform work on new concrete until workers and construction materials will not damage the concrete or interfere with its curing. Allow at least 36 hours and until the field cured compressive strength cylinders or maturity results reach 85% f’c ; or if using flexural beams, the average of two beam tests is greater than 650 psi (4.5 MPa) before loading new concrete. 511.14 354 Cure concrete as follows: TABLE 511.14 -2, CURING REQUIREMENTS Location Curing Method [1] Superstructure concrete Method A Concrete to which sealer is applied Method A Construction joints Method A Top surface of concrete deck superstructure concrete Method A followed by Method B Concrete with waterproofing Method A or Method B All other concrete Method A or Method B [1] Method A is water curing. Method B is membrane curing. If using Method B on areas to be waterproofed, remove the curing membrane. Concrete curing methods are as follows:

A.Method A, Water Curing. With the exception of the top surface of deck superstructure concrete, protect surfaces not covered by forms immediately after final finishing with two thicknesses of wet burlap. Keep burlap wet for at least 7 days by the continuous application of water. If forms a re removed before 7 days, immediately drench the exposed concrete with water and cover it with burlap. Continuously apply water to the burlap for the remainder of the curing period. Instead of continuous application of water, with the exception of the top surface of deck superstructure concrete, the Contractor may cover the wet burlap with white polyethylene sheeting or plastic coated burlap blankets conforming to

705.06 Place plastic coated burlap blankets wet and with the burlap side against the

previous layer of wet burlap. Sufficiently lap and secure adjoining plastic coated blankets or polyethylene sheets at the laps and edges to form a seal that maintains the concrete wet at laps and edges. Cover white polyethylene sheeting or plastic coated blankets containing holes or tears with an additional covering of plastic sheeting or blankets as directed by the Engineer. Cover the top surface of deck superstructure concrete with a single layer of clean wet burlap after it is bull floated if necessary and fini shed. Keep the burlap wet by a continuous flow of water through soaker hoses and cover the hoses with a 4 mils (100 m) white opaque polyethylene film for 7 days. After 7 days, allow the surface of the deck to dry. After curing the top surface of the deck superstructure concrete for 7 days, remove the burlap and standing water. Within 12 hours after removing the burlap, apply a curing membrane and cure the concrete according to Method B.

B.Method B, Membrane Curing. Immediately after the free water has disappeared on surfaces not protected by forms, apply curing material conforming to 705.07, Type 1 or 1D. If forms are removed before the end of the 7 -day curing period, apply curing material on the concrete exposed by removing the forms. Thoroughly mix curing material immediately before use. Apply the membrane curing material at the rate of at least 1 gallon per 200 square feet (1 L/5 m2) of surface and in a fine mist to provide a continuous, uniform, and water impermeable film without marring the concr ete surface 511.15 355 Do not allow workers, materials, and equipment on the concrete during the curing period, unless adequately protecting the membrane curing material from damage. . If the film is broken or damaged during the specified curing period, reapply curing material as specified above to the damaged or affected areas. 511.1 5 Surface Finish. For concrete that is to be sealed according to 512.03,, perform surface profiling according to 512.03.F., i mmediately after removing forms . Clean, dampen, and fill wit h mortar all cavities produced by form ties, honeycomb spots, broken corners or edges, and other defects. Use a mortar of the same proportions used in the concrete being finished. Finish other contiguous exposed surfaces on the structure in a similar manne r and to the extent required to produce a uniform appearance. On all exposed surfaces, remove fins and irregular projections with a stone or power grinder, taking care to avoid contrasting surface textures.
A.Grout Cleaning. If grout cleaning is shown on the plans or necessary for corrective work, wet the concrete surface and then uniformly cover the concrete with a grout consisting of one part cement, 1 1/2 parts fine sand conforming to 703.03, and sufficient water to produce a mortar with the consistency of thick paint. Use white portland cement in the grout in the quantity determined by the Engineer necessary to match the color of the concrete . Uniformly apply the grout with brushes or spray guns, completely filling air bubbles and holes. Immediately aft er applying the grout, vigorously scour the concrete surface with a cork or other suitable float. While the grout is still in a plastic condition and while the grout does not pull from the holes or depressions, finish the surface with a sponge rubber or ot her suitable float, removing excess grout. After the grout thoroughly dries, vigorously rub the surface with dry burlap, removing dried grout until there is no visible film of grout remaining on the surface. Perform the entire cleaning operation of each ar ea on the same day. Remove dark spots or streaks that remain after the cleaning operation using a fine grained silicon carbide stone. Stop rubbing with the silicon carbide stone before the surface texture changes. Unless otherwise directed by the Engineer, perform grout cleaning during the final project clean up.
B.Rubbed Finish. If a rubbed finish is shown on the plans, if possible, remove forms within 2 days after placing concrete. Finish the surface as specified above to correct defects. After the morta r used for finishing is thoroughly set, and for a minimum of 2 hours before starting the rubbed finish, thoroughly saturate the concrete with water. Rub surfaces to be finished with a medium coarse silicon carbide stone until all form marks, projections, a nd irregularities are removed, all voids are filled, and a uniform surface is obtained. Leave the paste produced by rubbing in place. Other than water, do not apply additional material to the surface. After placing concrete above the finishing area, obtain the final finish by rubbing the concrete with a fine silicon carbide stone and water until the entire surface is of a smooth texture and uniform in color. Protect surfaces with a rubbed finish from damage caused by subsequent construction operations. If damaged, clean and refinish the surface as specified above. 511.16 356 511.16 Roadway Finish. Finish and test concrete deck slabs according to 451.13. Do not groove or broom finish a strip of surface 9 to 12 inches (220 to 300 mm) wide adjacent to curbs and barriers. Provide a broom drag finish on concrete deck slabs in the longitudinal or transverse direction. The Engineer will approve the finishing machine. Provide a self -propelled machine with forward and reverse drive mechanisms that enable precise control of machi ne velocity in both directions. The machine shall have two rotating rollers, leveling augers, and either a vibrating pan or vibrating rollers. Field verify that the vibrating frequency of the pans or rollers are from 1500 to 5000 pulses per minute. Do not use vibrating rollers that have fins protruding more then 1/4 inch (6 mm) from the roller. Use a finishing machine capable of finishing transversely while traveling in both directions across the deck. Provide screeds capable of rising above the concrete su rface. Provide a finishing machine capable of finishing the full width of the decks between curbs or parapet walls. The wheels of the finishing machine shall run on temporary riding rails adequately supported on the structural steel or falsework of the dec k. Make the rail and rail supports of steel and arrange the rail and rail supports so that the weight of the finishing machine and the operator cause zero vertical deflection while traveling across the deck. Ensure the rail is straight, with no sections ex ceeding a tolerance of 1/8 inch in 10 feet (3 mm in 3 m) in any direction. Elevate support rails a sufficient distance above the slab to allow the simultaneous hand finishing of areas not machine finished. Fabricate and install rail supports to allow remov al to at least 2 inches (50 mm) below the top of the slab. Fill holes formed by the removal of rail supports during the final finishing of the slab. For structures with a skew angle greater than fifteen (15) degrees and up to fifty
50.degrees, place the finishing machine within 5°of the skew angle of the structure. For structures with a skew angle greater than fifty (50) degrees, place the finishing machine at fifty (50) degrees.

511.17 Bridge Deck Grooving. After water curing the concrete and either bef ore

applying curing compound or some period after applying curing compound and before opening the bridge to traffic, saw longitudinal grooves into the deck, unless specified otherwise in the plans . If sawing grooves after applying the curing compo und and the concrete deck is less than 30 days old, reapply the curing compound after removing standing water, within 12 hours after sawing grooves in the deck. Use diamond blades mounted on a multi -blade arbor on self -propelled machines that were built fo r grooving of concrete surfaces. The groove machines shall have depth control devices that detect variations in the pavement surface and adjust the cutting head height to maintain the specified depth of the groove. The grooving machines shall have devices to control alignment. Do not use flailing or impact type grooving equipment. More than one size grooving machine may be required in order to saw the grooves as specified. Maintain a minimum of ¾ inch (19 mm) to a maximum of 2 ¼ inches (56 mm) transverse di stance between adjacent passes of the grooving machine head. Provide an experienced technician to supervise the location, alignment, layout, dimension, and grooving of the surface. 511.18 357 Saw grooves parallel to the bridge centerline in a continuous pattern acros s the surface. Begin and end sawing 9 to 12 inches (220 to 300 mm) from any device in place in a bridge deck, such as scuppers or expansion joints. Stop sawing a minimum of 2 inches (50 mm) to a maximum of 24 inches (600 mm) from skewed expansion joints. Maintain a clearance of a minimum of 2 inches (50 mm) and a maximum of 4 inches (100 mm) from the grooves to longitudinal joints in the deck. Maintain a minimum clearance of 9 inches (220 mm) to a maximum of 30 inches (750 mm) clearance between the grooves and the curb or parapet toe. However, at no point shall un -grooved portions of deck extend beyond edge line and into the temporary or permanent travelled lanes. Saw grooves in a uniform pattern spaced at 3/4 inch minus 1/4 inch or plus 0 (19 mm minus 6 mm or plus 0). Saw grooves approximately 0.15 inches (4 mm) deep and 0.10 inches (3 mm) wide. For staged, or phase bridge deck work, saw the grooves parallel to the final, permanent bridge centerline. If the different stages or phases of the bridge deck work occur within one construction season, any stage opened to traffic shall receive an interim coarse broom finish during placement, then saw the longitudinal grooves after the final stage. The interim broom finish will not be allowed as a surface texture when opened to traffic over a winter season. Saw longitudinal grooves in the deck prior to opening to traffic for a winter season. For bridge decks that widen from one end to the other, saw the longitudinal grooves parallel to the centerline of the roadway. On the side of the bridge that widens, saw the longitudinal grooves to follow the edge line. Saw longitudinal grooves in the gore areas, avoiding the overlapping of grooves. At the beginning of each work shift, furnish a full complement of grooving blades with each saw that are capable of cutting grooves of the specified width, depth, and spacing. If during the work, a single grooving blade on a machine becomes incapable of cutting a groove, continue work for the remainder of the work shift. The Contractor is not required to cut the groove omitted because of the failed blade. Should two or more grooving blades on a machine become incapable of cutting grooves, cease operating the machine until it is repaired. Continuously remove all slurry and remaining residu e from the grooving operation and leave the deck surface in a clean condition. Prevent residue from grooving operations from flowing across shoulders or across lanes occupied by public traffic or from flowing into gutters or other drainage facilities. Remo ve solid residue before the residue is blown by passing traffic or by wind. Provide water as necessary to saw grooves according to this subsection.

511.18 Sidewalk Finish. After placing, strike off the concrete with a template

and finish the concrete with a float to produce a sandy texture.

511.19 Joints , Cracks , Scaling and Spalls . After completing all curing

operations and allowing the deck to thoroughly dry, seal the following areas with a high molecular weight methacrylate (HMWM) sealer. Flood the areas and squeegee off the excess material as specified in Item 512 before opening the deck to traffic:

A.Transverse joints in the deck. 511.20 358 B. Joints between the concrete deck and steel end dams.
C.Longitudinal joints in the deck.
D.Longitudinal joints between the deck and safety curb, barriers, and parapets, etc.
E.Cracks discovered in the deck of the top and bottom surfaces be fore opening the deck to traffic, that are 10 mils or 0.010 inches (0.254 mm) or less in width. For deck cracking on the top and bottom surface area, on more than 20% of the surface area, or that is 10 mils or 0.010 inches (0.254 mm) or more in width, or deck scaling that is greater than 0.250 inches (6.25 mm) deep, or on more than 20% of the deck surface area, or deck spalling on more than one area, or an area greater than 32 square yards (26.76 square meters), an investigation will be performed by O MM and proceed according to 108.02 to resolve the issue.

511.20 Compressive Strength . Sample and test concrete strength according to

511.04.

A.Concrete Requiring QC/QA. When the bid item requires QC/QA, the Engineer will evaluate the QC compressive test sublot results according to Supplement 1127 and as follows: If a single reported compressive strength test result for a sublot of concrete is less than 88% f’c reevaluate the in place concrete as follows . The Engineer will determine the location for evaluating the strength of the sublot represented by the low compressive strength concrete. Evaluate using either nondestructive testing or cores. The Engineer will accept the concrete if the reported nondestructive test results are greater than the specified f’c. The Department will use the original cylinder results for calculating the compressive strength pay factor (PFc) if non destructive testing is used. If cores are tested the core results will be used in place of the original cylinder results for pay factor determination. If the nondestructive test results are less than the specified f’c , the Department will require the concrete to be cored. Th e Engineer will determine the locations for the required concrete cores. Provide all concrete cores to the Engineer for testing by the Department. Patch core holes with approved patching material. If the core results are above 88% f’c, the Department will use the core strength results for calculating the compressive strength pay factor (PFc). If the core results indicate that the compressive strength of the concrete is below 88% f’c, submit a plan for corrective action to the Engineer for approval. If the corrective plan is not approved, the Engineer will require the Contractor to:
1.Remove and replace the unacceptable sublot and retest the new sublot at no cost to the Department or
2.Leave the unacceptable material in place and pay for the sublot with a pay factor of 0.75. If three or more sublot compressive strength acceptance test results are less than f’c but greater than 88% f’c the Engineer will require an investigation of the reasons for the consistent low strengths. Until the investigation is completed to the satisfaction of the Engineer no additional placements of the concrete JMF will be 511.21 359 made. Investigations should include all facets of the concrete operation including batchin g, mixing, delivery, clean up, sampling, testing, quality control plan, etc. If the Engineer is unsatisfied with the results of the investigation , the JMF and the quality control plan will become not approved. Develop and submit a new JMF and quality contr ol plan conforming to the requirements of 499.03 and 511.04 . Pay factors under 511.22 for the se low strength sublots will be based on the original report ed cylinder strengths.
B.Concrete Not Requiring QC/QA. When the bid item does not require QC/QA, the Engineer will evaluate the strength results following the requirements of Table 511.22 -2 and as follows: If a single compressive strength test result is less than f’c the material will be considered unacceptable material and the Department will determine a cceptance according to Item 106.07 . If three or more compressive strength test results are less than f’c the Engineer will require an investigation of the reasons for the consistent low strengths. Until the investigation is completed to the satisfaction o f the Engineer no additional placements of the concrete JMF will be made. Investigations should include all facets of the concrete operation including batching, mixing, delivery, clean up, sampling, testing, etc. If the Engineer is unsatisfied with the res ults of the investigation , the JMF will become not approved. Develop and submit a new JMF conforming to the requirements of 499.03 .

511.21 Air Content . For concrete that requires QC/QA, test the air content of

the concrete according to Item 455. When QC/Q A concrete is not required, the Department will test the air content as directed by the Engineer.

A.Concrete Requiring QC/QA. Any concrete with air results outside the requirements of Table 499.03 -1 that is placed into the structure is unacceptable mater ial according to item 106.07. The amount of unacceptable material will be the amount represented by the test result. Reevaluate the unacceptable material at no cost to the Department as follows:
1.Core the location containing the unacceptable concrete. Patch the core hole with approved material.
a.For c oncrete with high air content, test a core for compressive strength. Concrete with a minimum strength of f’c may be left in place.
b.For concrete with low air content , test the core to d etermine the i n- place hardened air content , specific surface and spacing factor according to ASTM C 457. Remove and replace unacceptable materials with specific surface results less than 600 in-1 (25 mm-1) or spacing factor results are more than 0.008 in (0.20 mm). Hire an independent laboratory acceptable to the D epartment to perform the testing.
B.Concrete Not Requiring QC/QA. Any concrete with air results outside the requirements of Table 499.03 -1 that is placed into the structure is unacceptable material, accordi ng to item 106.07. The amount of unacceptable material will be the amount represented by the test result. Reevaluate the unacceptable material at no cost to the Department as follows: 511.22 360 1. The Department will core the location containing the unacceptable concrete. Patch the core hole with approved materials.
a.For c oncrete with high air content, the Department will test a core for compressive strength. Concrete with a strength of f’c may be left in place.
b.For concrete with low air content the Departme nt will d etermine the in -place hardened air content , specific surface and spacing factor according to ASTM C 457. Remove and replace unacceptable materials with specific surface results less than 600 in-1 (25 mm-1) or spacing factor results of more than 0. 008 in (0.20 mm).

511.22 Pay Factors. Apply pay factors as follows:

A.Concrete Requiring QC/QA The Department will use pay factors based on the percent within limits (PWL) to establish a final adjusted price . The PWL will be established per lot (s) accepted in the QCP for each bid item quantity of concrete. The Department will calculate a PWL according to Supplement 1 127 using either the Contractor’s verified QC compressive test results or core results when the QC could not be verified . The compressi ve strength pay factor (PF C) from Table 511.22 -1for the lot will be applied to each bid item represented in the lot. The Department will combine approach slab and deck concrete test results in the same lot to determine final pay factors. TABLE 511.22 -1, PAY FACTORS FOR CONCRE TE REQUIRING QC/QA PWL PFC 85 % – 100 % 1.00 84% 0.995 83% 0.990 82% 0.985 81% 0.980 80% 0.975 79% 0.970 78% 0.965 77% 0.960 76% 0.955 75% 0.950 < 75% See below If the PWL value determined for the lot of concrete is below 75%, submit a plan for corrective action to the Engineer for approval. If the corrective plan is not approved, the Engineer will require the Contractor to:
1.Remove and replace the lot of unac ceptable material at no cost to the Department, or 2 Leave the unacceptable material in place and pay for the lot of with a pay factor of 0.75.
B.Concrete Not Requiring QC/QA For concrete items that the Department performs compression testing, the Department will use pay factors based on the individual compressive strength results 511.23 361 for the quantity represented by the test results to establish an adjusted price to the items. The pay factors from Table 511.22 -2 will be applied to items represented by the tests. TABLE 511.22 -2, PAY FACTORS FOR CONC RETE NOT REQUIRING QC/QA Individual Test Results Pay Factor (PF C) ≥ f’c 1.00 < f’c Follow 106.07 511.2 3 Method of Measurement. The Department will measure the appropriate concrete item by the number of cubic yards (cubic meters) determined by calculations from plan dimensions, in place, completed and accepted. The Department will make deductions for portions of primary structural memb ers embedded in concrete. The Department will not make deductions for the volume of reinforcing steel, conduits or embedded piles. Superstructure concrete includes the concrete in deflective parapets not having a metallic railing. The Department may measur e deck concrete by either volume or area using plan dimensions. The Department will calculate separate quantities of concrete due to unacceptable compressive strength, 511.21 and air content, 511.22. 511.2 4 Basis of Payment. The Department will pay for accepted quantities of concrete as follows . Work necessary to adjust seat elevations and deck haunches for prestressed beam members is incidental to the affected structural concrete items. The Department will pay for final quantities as measured and field verified. The Department will not pay for additional reinforcing steel required to adequately stabilize the cages. The Department will not pay for repairs to horizontal cracks by epoxy injection or, if a concrete sealer was applied, for repairs to the seal er after the completing the epoxy injection. The Department will not pay extra for any type of surface finish specified in 511.15, the cost being considered as included in the price bid for concrete. If the Contractor elects to saw the deck after applying the curing compound, the Department will not pay to reapply the curing compound. All costs for sealing as specified in 511. 19 are incidental to the appropriate concrete item. The Department will not make separate payment for sealing. The Department will no t pay separately for the concrete cylinder curing box (CCCB). The Department will not pay for the re -evaluation of low strength test results,

511.20 A . 511.24

362 The Department will initially pay the full bid price to the Contractor upon completing the work. The Dep artment will calculate the final adjusted payment for each item as follows: PF1 - The final adjusted pay per cubic yard ( cubic meter) or square yard ( square meter), for accepted quantities of concrete : PF1 = (Contract Bid Price) x PF C PF2 - The final adj usted pay per cubic yard ( cubic meter) or square yard ( square meter) for unacceptable quantit ies of concrete due to compressive strength or low air content and allowed to stay in place, according to 511.20 or 511.21 . PF2 = (Contract Bid Price) x 0.75 Calculate the adjusted price per bid item by multiplying PF1 or PF2 by the appropriate quantities of concrete, then sum the values. Subtract the full bid price paid to the Contractor from the adjusted price to determine the difference. The Department will exec ute final adjustments by change order upon receipt of all test data. The Department will pay for accepted quantities at the contract prices as follows: Item Unit Description 511 Cubic Yard Class ___ Concrete, _____ (Cubic Meter) 511 Cubic Yard Class ___ Concrete, _____ with QC/QA (Cubic Meter) 511 Cubic Yard Class QC 1 Concrete, Substructure (Cubic Meter) 511 Cubic Yard Class QC 1 Concrete, Substructure with (Cubic Meter) QC/QA 511 Cubic Yard Class QC 2 Concrete, Bridge Deck (Cubic Meter) Square Yard (Square Meter) 511 Cubic Yard Class QC 2 Concrete, Bridge Deck with (Cubic Meter) QC/QA Square Yard (Square Meter) 511 Cubic Yard Class QC 2 Concrete, Bridge Deck (Parapet) (Cubic Meter) 511 Cubic Yard Class QC 2 Concrete, Bridge Deck (Parapet) (Cubic Meter) with QC/QA 511 Cubic Yard Class QC 3 Concrete, _____ with QC/QA (Cubic Meter) 511 Cubic Yard Class QC 4 Mass Concrete, Substructure with (Cubic Meter) QC/QA 512.01 363 ITEM 512 TREATING CONCRETE

512.01 Description

512.02 Materials

512.03 Sealing of Concrete Surfaces

512.04 Sealing Concrete Bridge Decks with HMWM Resin

512.05 Soluble Reactive Silicate (SRS) Concrete Treatment

512.06 Treating Concrete Bridge Decks with Gravity -Fed Resin

512.07 Sealing Cracks by Epoxy Injection

512.08 Waterproofing

512.09 Method of Measurement

512.10 Basis of Payment

512.01 Description. This work consists of sealing and treating concrete

surfaces, sealing cracks in concrete, and applying waterproofing to structures.

512.02 Materials. Furnish materials conforming to:

Asphalt cement ................................ .. 702.01 (PG 64 - 22) Asphalt primer for .................. 702.02 (RC -70 or RC -250), waterproofing ................................ ..................... 702.05 HMWM Resin ................................ ........................ 705.15 Epoxy -Urethane Sealer ................................ ....... 705.23.A Non-epoxy Sealer ................................ ............... 705.23.B Soluble Reactive Silicate (S RS) .............................. 705.24 Gravity Fed Resin ................................ ................... 705.25 Epoxy injection Materials ................................ ....... 705.26 Sand ....................... 703 with the following exceptions: Maximum moisture content of 0.5 of the percent of absorption when treated according to California Test 226. Gradation: Sieve Size Total Percent Passing No. 4 (4.75 mm) 100 No. 8 (2.36 mm) 90 to 100 No. 20 (850 µm) 5 to 15 No. 50 (300 µm) 0 to 5 Emulsified asphalt primer, ................ 702.04 (MS -2, SS -1) Asphalt for waterproofing ................................ ....... 702.06 Hot applied joint sealer ................................ ........... 705.04 Type 3 membrane primer ................................ ........ 705.04 Waterproofing fabric ................................ ............... 711.24 Sheet Type 2 membrane waterproofing .................. 711.25 Sheet Type 3 membrane waterproofing .................. 711.29

512.03 Sealing of Concrete Surfaces . This work consists of applying an

approved sealer on existing and new concrete surface areas after the concrete is cured and repairs completed and cured. Apply the sealer to locations described in the plans. Apply the sealer listed in the pay item description. Choose a type of sealer if no sealer is listed in the pay item description. 512.03 364 A. Equipment. Use appl ication equipment recommended by the sealer manufacturer. Use spray equipment, tanks, hoses, brooms, rollers, coaters, squeegees, etc., that are clean, free of foreign matter, oil residue and water.

B.Mixing. Mix the sealer according to the manufacturer ’s recommended procedures. Furnish the Engineer with the manufacturer’s application instructions. Do not mix or apply the sealer until the manufacturer’s written recommendations are supplied to the Engineer. Mix and maintain materials at a uniform consistenc y during application.
C.Storage. Store all sealer components in tightly sealed containers, in a dry location, and as recommended by the manufacturer. Deliver unopened drums or containers of the sealer or sealer components to the job site with the manufact urer's numbered seal intact.
D.Application submittals. At least five (5) days before sealing, provide the Engineer the sealer manufacturer’s written requirements for application equipment, mixing equipment, mixing procedures, mixing time, storage requirem ents, recoat times and temperatures, and SDS sheets.
E.Surface Condition . Apply sealers only to surfaces which are dry, free from dust, dirt, oil, wax, curing compounds, efflorescence, laitance, coatings and other foreign materials. Visually inspect a ll surfaces before applying sealer. Remove all structurally unsound surfaces and weak sections. Perform all concrete patching prior to surface profiling. Perform concrete patching on areas identified by the Engineer according to 519. Cure repaired areas for at least seven (7) days. Air dry all concrete surfaces for at least ten (10) days after completion of required curing. For accelerated cure of precast concrete, obtain the required 28 day strength and air dry the surfaces at least ten (10) days after co mpleting accelerated cure.
F.Surface Preparation and Profiling . Remove dust, dirt, oil, wax, curing compounds, efflorescence, laitance, coatings and other foreign material s from surfaces to be sealed. For Epoxy -Urethane sealers, u se one or both of the following methods to produce a surface profile that feels and looks like 100 grit sandpaper or coarser. Provide the Engineer sandpaper for comparison. Perform the ASTM D7682 -12, Method B, Standard Test Method for Replication and Measurement of Concrete Surface Profile Using Replica Putty to obtain a replica coupon of the prepared concrete surface on a flat, test section, on the first day of production, and as requested by the Engineer. With a micrometer, measure the surface profile obtained on the coupon, a nd provide the coupon to the Engineer.
1.Water blast at 7,000 psi (48 MPa) minimum, or
2.Abrasive blast, followed by air brooming or power sweeping, to remove dust and sand from the surface and opened pores.
3.or use a combination of water blast and a brasive blast. 512.03 365 Install suitable traps, filters, drip pans and other separation devices in the cleaning equipment so oil and other foreign material are not deposited on the surface. If the concrete surface had curing compound applied, acid test the surface after blasting to see if the curing compound was removed. Perform the acid test for every 500 square feet (47 square meters). Use a 30%, by weight, solution of hydrochloric acid. Apply 4 to 5 drops to the conc rete surface. If foaming/fizzing occurs the curing compound is removed. Rinse the tested location with an ammonia solution to neutralize the concrete area tested (1 cup ammonia to 5 gallons water) . (NOTE : Muriatic acid and ammonia can be bought in a har dware store. Muriatic acid is used to clean masonry. Only dilute by pouring the acid into the water. DO NOT po ur the water into the acid.) When surfaces show intermittent or no foaming, use chemicals or other cleaning compounds to remove the curing compoun ds. Only use products approved by the sealer manufacturer. Furnish the Engineer documentation of the sealer manufacturer’s approval and method to test if materials are removed. Ensure that all wastes generated by the surface preparation operation are mana ged in accordance with 107.19.
G.Application and Coverage . Apply the sealer between twelve and (12) hours and 48 hours after surface preparation by water blasting methods. Apply the sealer within 48 hours after surface preparation by abrasive blasting me thods Do not apply sealer if rain is anticipated within six (6) hours after application. Clearly mark where the sealer application stops if not continuous.
1.Epoxy -Urethane sealers
a.Apply the epoxy coat of the epoxy -urethane sealer at the coverage rate of 120 square feet per gallon (2.9 square meter s per liter). Use a coverage rate of 150 square feet per gallon (3.6 square meter s per liter) when the Laboratory’s qualified products list for the epoxy authorizes it. Apply the urethane coat of the epoxy -urethane sealer at a rate of 200 square feet per gallon (4.8 square meter s per liter). When surfaces are not smooth and flat, adjust the given coverage rates by the following formulas to determine the correct coverage rate.
1.For surfaces using large stone liners and standard concrete = specified coverage rate (sq ft/gal [sq m/l]) × 0.8
2.For surfaces using large stone liners and porous concrete = specified coverage rate (sq ft/gal [sq m/l]) × 0.7
3.For surfaces using fluted liners and standard concrete = specified coverage rate (sq ft/gal [sq m/l]) × 0.5
b.Provide documentation to the Engineer that the ambient, surface and material temperature is 50 ºF (10 ºC) or above, 5 ºF higher than the dew point, and the relative humidity is 80% or below during the application of the sealer.
c.Apply with a brush, squeegee, roller or spraying equipment and as recommended by the manufacturer. 512.03 366 d. Apply one coat of epoxy and one coat of the urethane top coat. Time between coats shall meet the manufacturer ’s written recommendation provided to the Engineer during 512.03.D. Use epoxy and urethane from the same manufacturer. Achieve specified coverage regardless of the number of passes per coat.
e.Tint so the final color is Federal Color Standard No. 17778 - Light Neutr al. Pigment content shall be limited so as not to reduce sealing effectiveness of the second coat. Refer to the plans for colors for specific projects.
f.Sags and runs are not acceptable in the sealer.
g.For sealed sidewalks or other horizontal surfaces with repetitive foot traffic or vehicular traffic, integrate 1 1/2 lbs per square yard (0.8 kg/m ²) of silica sand into the surface of the second coat to produce a nonskid surface satisfactory to the Engineer.
2.Non-epoxy sealer
a.Apply the sealer accordi ng to the manufacturer ’s recommended mode of application and under the observation of the Engineer.
b.Coverage.
1.Surfaces subject to abrasive wear (bridge decks, bridge deck shoulders and sidewalks); Minimum, one gallon (3.875 liter) of sealer for each 100 square feet (9.0 square meters).
2.Curbs, vertical surfaces of beams and deck slabs subject to direct roadway drainage; Minimum, one gallon (3.875 liter) for each 125 square feet (11.5 square meter s).
3.Other surfaces (for example, parapets, abutm ents, pier caps and median dividers); Minimum, one gallon (3.875 liter) for each 150 square feet (14.0 square meters). Stone or fluted formed concrete surfaces may require additional sealer materials for coverage.
c.Apply sealer on horizontal surfaces in a one -pass operation at the required coverage. An acceptable application procedure consists of saturating the surface and waiting a few seconds for the sealer to completely penetrate the concrete surface. Broom in the sealer if recommended by the manufactu rer.
d.Apply sealer on vertical surfaces to saturate the surface. The surface is saturated when runs of 6 to 12 inches develop. Apply additional passes in 10 to 15 minute intervals until the coverage rate is achieved. Apply sealers with brush or roller if recommended by the manufacturer.
e.After 10 to 15 minutes, squeegee off excess material on smooth finished or dense concretes where the required coverage is not absorbed.
f.Tint clear non -epoxy sealers with a vanishing dye that will not damage the concre te. 512.03 367 g. Do not apply sealer if the ambient temperature is below 40 °F (5 °C) or will fall below 32 °F (0 °C) within 12 hours after application .
H.Test Site/Application . Apply epoxy -urethane or non -epoxy sealer to measured coverage areas, both on horizontal and vertical surfaces, and on different concrete types, demonstrating:
1.The project’s visual effects for the epoxy -urethane sealer application at the required coverage rate.
2.Visually, the absorption necessary to achieve the specified coverage rate for the non -epoxy sealer. Use at least 1/2 gallon (2 liter) of sealer, following the manufacturer ’s recommended method of application, for the total of the test surfaces.
3.Apply to the deck, safety curb or sidewalk for the horizontal test surfaces and use an abutment parapet or pier face for the vertical test surface so different textures are tested.
I.Appearance. Epoxy -Urethane sealers : Uniform appearance and the final color shall visually match the test section. Recoating, removal and re -application or other methods recommended by the manufacturer will be required to correct final appearance. Non-Epoxy Sealers : The sealer shall result in a uniform appearance.
J.Traffic. Allow tra ffic on deck shoulder areas after 12 hours of drying time for an epoxy -urethane sealer. Keep traffic off a non -epoxy sealer until the sealer is dry.
K.Safety Precautions. Follow precautions defined on the manufacturer ’s SDS. Prov ide the Engineer a cop y of the SDS sheet for information before any work commences.
L.Protection of Adjoining Surfaces and the Public. Protect the public during all operations, especially when applying sealer to the fascia or the underside portions of a bridge that spa ns an area used by the public. During sealing, mask off, or use other means of protection, for surfaces not being sealed. Protect asphalt and mastic type surfaces from spillage and heavy overspray. Do not apply sealers to joint sealants which have not cured ac cording to the manufacturer ’s instructions. Joint sealants, traffic paints and asphalt overlays may be applied to the treated surfaces 48 hours after the sealer has been applied. Protect nearby steel, aluminum or glass surfaces when non -epoxy overspray cou ld be deposited on those surfaces.
M.Environmental Requirements. Protect plants and vegetation from overspray by covering with drop cloths.
N.Superintendent . In addition to the requirements of 105.06 , the Superintendent must successfully complete a Sealing of Concrete Surfaces training prequalification course offered by the Departm ent. The course must have been completed within the past four years and an individual course certificate must have been received by the Superintendent. Present certificate to the Engineer prior to beginning the sealing of concrete surfaces work. Work will not be permitted to begin until after the Superintendent provides a valid course certificate. 512.04 368 512.04 Sealing Concrete Bridge Decks with HMWM Resin . This work shall consist of preparing and treating the concrete wearing surfaces of bridge decks with a penet rating sealer in accordance with these specifications, in reasonably close conformity with the plans and the manufacturer ’s recommendation and as directed by the Engineer.
A.Limitations. Do not perform this work during the period beginning November 1st an d ending March 31st.
B.Surface Preparation. Remove roadway dirt and debris from the area of the deck to be treated. Sweep, abrasive blast , then with the use of a manual or power broom sweep and blow with compressed air so that the surfaces to whi ch the sealer is to be applied is dry and free of dust and dirt. Use high pressure compressed air to blow all loose material from visible cracks. Fit the cleaning equipment with suitable traps, filters, drip pans, driers and other devices to prevent oil an d other foreign material from being deposited on the surface. Do not allow traffic on the clean surface prior to application of the sealer. Remove existing pavement markings using a method as specified in 614.11.G.1.a. The cost of removal is incidental to the Work. Remove all traces of asphalt or petroleum products and concrete curing seals by abrasive blasting prior to air sweeping.
C.Installation . Provide a compatible promoter/initiator system capable of providing the same physical qualities of the harde ned resin as if promoted/initiated with 2 percent cobalt naphthanate (6 percent ) and 2 percent cumene hydroperoxide. Store materials at 65 to 80 °F (18 to 27 °C). Provide a system that has a resin gel time of not less than 40 minutes to not more than 1 1/2 hours at the time and temperature of application. Adjust the gel time to compensate for the change in temperature throughout the day. The temperature of the surfaces to be treated may range from 50 °F (10 °C) to 120 °F (49 °C). Arrange to have a technical representative on site to provide mixing proportions equipment suitability, and safety advice. Any conflict between these provisions and representative's advice shall be resolved at the job site. The technical representative shall remain at the job site u ntil such time as he and the Engineer agree that the Contractor is qualified in all aspects of the application of the sealer. Do not allow the promoter and initiator, if supplied separate from the resin, to contact each other directly. Do not store contain ers of promoter or initiators together in a manner that will allow leakage or spillage from one to contact the containers or materials of the other. Machine application of the resin may be performed by using a two -part resin system utilizing a promoted re sin for one part and an initiated resin for the other part. This two -part resin system may be combined at a spray bar through positive displacement atomization of the resin. Do not use compre ssed air to produce the spray. Use appropriate cleaning and flush ing of equipment, tools, etc., with an appropriate solvent, as approved by the Engineer, in such a manner to minimize personal and environmental hazards. Advise workman that the resin will soften gum 512.04 369 rubber soles, and a face -mask should be used to protect from accidental splashes. Clothing and leather saturated with resin will harden and become useless. Prior to resin application the surface to be treated shall be visibly dry and its temperature between 50 °F (10 °C) and 120 °F (49 °C). Do not apply the resin within 24 hours after a rain or when rain is forecast within 12 hours or when the ambient air temperature is below 50 °F (10 °C). Pre -mark the deck to control mixed material usage and to provide a rate of application of approximately 100 square feet per gallon (2.45m ²/L). The exact rate shall be determined by the Engineer prior to commencing full -scale deck treatment operations. Before using the material submit to OMM copies of the manufacturer’s certified test data showing that the materi al complies with the requirements of this specification. The test data shall be developed by an independent approved testing laboratory, and shall include the brand name of the material, name of manufacturer, number of the lot tested and date of manufactur e. When the material has been approved by OMM , further testing by the manufacturer will not be required unless the formulation or manufacturing process has been changed, in which case new certified test results will be required. The manufactu rer shall certify that the formulation is the same as that for which data has been submitted. The state reserves the right to sample and test delivered lots for compliance. Flood the deck surfaces resin, allowing penetration into the concrete and filling of all cracks. Limit the initiated mix of promoted resin to 5 gallons (19 L) at a time for manual application. A significant increase in viscosity shall be cause for rejection. Apply the treatment within 5 minutes after complete mixing. Redistribute excess material by squeegee or brooms within 10 minutes after application. Take all steps necessary to prevent the resin from flowing into lanes open to traffic. Broadcast sand over the entire treated area of the bridge deck by mechanical means to affect a unifor m coverage of 0.80 to 1.2 pounds per square yard (0.43 kg/m ² to 0.65 kg/m ²). The sand shall be uniformly graded aggregate conforming to the quality requirements of 703 and shall conform to the following limits for grading: Sieve Size Total Percent Passing No. 4 (4.75 mm) 100 No. 8 (2.36 mm) 90 to 100 No. 20 (850 µm) 5 to 15 No. 50 (300 µm) 0 to 5 It is the intention of the specification to allow the use of commercially available blast sands applied by a common lawn broadcast type seeder/spreader. Place sand between 10 to 15 minutes behind the resin spreading front and before any jelling of the resin occurs. If the surface contains large deep cracks, the low -viscosity liquid could run completely through the concrete slab. Apply a second coat in thes e areas after the first coat has started to cure. Before the monomer hardens, fill imperfections or spalls with standing liquid with commercial quality concrete or sandblast sand, and finished to a uniform surface. The sand shall have a maximum moisture co ntent of 0.5 of the percent of absorption when tested in accordance to a California Test 226. 512.05 370 Do not permit traffic and equipment on the tested deck until it is tack free and a minimum of 6 hours have elapsed since treatment and the sand cover adheres sufficiently to resist brushing by hand. Protect the treatment from moisture for not less than 4 hours after placement.

512.05 Soluble Reactive Silicate (SRS) Concrete Treatment . This item

consist of the necessary labor, materials and equipment to prepare and treat portland cement concrete surfaces with a reactive silicate sealer meeting these specifications.

A.Equipment. Use a pplication equipment that is recommended by the manufacturer. Use spray equipment, tanks, hoses, brooms, rollers, coaters, squeegees, etc., that are thoroughly clean, free of foreign matter, oil residue and water prior to applying the treatment.
B.Cleaning and Surface Preparation. . Do not begin sealing until all concrete repairs have been completed and reached the design strength of th e patch material . Thoroughly clean the surface to remove dust, dirt, oil, wax, curing components, efflorescence, laitance, coatings and other foreign materials. Sweep , abrasive blast, then with the use of a manual or power broom sweep and blow with compr essed air so that the surfaces to which the sealer is to be applied is dry and free of dust and dirt. Use high pressure compressed air to blow all loose material from visible cracks. Obtain the approval of the manufacturer or its representative before the use of chemicals and other cleaning compounds to facilitate the removal of these foreign materials. Apply the treatment within 48 hours following surface preparation. Fit cleaning equipment with suitable traps, filters, drip pans and other devices to preve nt oil and other foreign material from being deposited on the surface.
C.Test Application. Treat a measured test coverage area on horizontal and vertical surfaces of the different components of the structure to be treated for the purpose of demonstrating the desired physical and visual effect of an application or of obtaining a visual illustration of the absorption necessary to achieve the specified coverage rate prior to final application. In the latter case, use at least 1/2 gallon (2 L) of treatment fol lowing the manufacturer ’s recommended method of application for the total of the test surfaces. Locate horizontal test surfaces on the deck and on the safety curb or sidewalk and locate vertical test surfaces on an abutment parapet and pier face so that th e different textures are displayed.
D.Application. Apply t he concrete treatment to concrete surfaces as designated on the plans. Apply the SRS by thoroughly saturating the concrete surfaces at an application rate specified by the manufacturer. Apply the S RS when the concrete surface temperature is above 35 °F (2 °C). Use a surface thermometer on the concrete to establish the temperature of the concrete if the air temperature at the time of application is 45 °F (7 °C) or below. Spread the SRS from puddles t o dry areas. If unable to complete the entire application continuously, note and clearly mark the location where the application was stopped. 512.06 371 E. Protection of Adjoining Surfaces and the Public . Protect by masking off or by other means adjoining surfaces of the structure which are not to be sealed when applying a treatment. Make provision to protect the public when treating the fascia of a bridge and/or portions of the underside of the deck of a bridge that spans an area used by the public. Protect asphalt a nd mastic type surfaces from spillage and heavy overspray. Do not apply joint sealants, traffic paints and asphalt overlays to the treated surfaces until 48 hours after the treatment has been applied. Cover adjoining and nearby surfaces of aluminum or glas s where there is a possibility of the treatment being deposited on the surfaces. Protect plants and vegetation from overspray by covering with drop cloths. Follow precautions as indicated on the manufacturer ’s SDS.
F.Opening to Traffic. Only allow tra ffic on deck after the treated area does not track. If there is any unreacted material on the surface after application(s), flush with fresh water, as recommended by the manufacturer. Contain all waste according to

107.19 .

512.06 Treating Concrete Bridge Decks with Gravity -Fed Resin. This work

shall consist of preparing and treating the concrete bridge deck with a gravity -fed crack welding system in accordance with these specifications in reasonably close conformity with the plans and the manufactur er’s recommendations and as directed by the Engineer.

A.Limitations. Do not perform this work during the period beginning November 1st and ending March 31st. Prior to resin application insure that the surface to be treated is visibly dry with a temperatur e between 40 °F (4 °C) and 100 °F (38 °C). Do not apply the resin within 24 hours after a rain, during rain, when rain is forecast within 12 hours or when the ambient air temperature is below 40 °F (4 °C).
B.Surface Preparation . First remove roadway dirt and debris from the area to be treated. Sweep abrasive blasted surfaces to which the sealer is to be applied, then manual or power broom swept and blown with compressed air so that they are dry and free of dust and dirt. Use high pressure compressed air t o blow all loose material from visible cracks. Use a high pressure water blast followed by an air blast if particles are highly embedded in the cracks, to clean cracks. Fit the cleaning equipment with suitable traps, filters, drip pans, dryers and other de vices to prevent oil and other foreign material from being deposited on the surface. Do not allow traffic on the clean surfaces prior to application of the sealer. Remove existing pavement markings using a method as specified in 614.11.G.1.a. The cost of removal is incidental to the Work. Remove all traces of asphalt or petroleum products and concrete curing by the abrasive blasting prior to air sweeping.
C.Application Pre-mark the deck to control mixed material usage and to provide a rate of application o f approximately 100 to 150 square feet per gallon (2.45 to 3.68 m²/L). The Engineer will determine the exact rate but will not exceed 150 square feet per gallon (3.68 m²/L). Flood the area to be sealed with resin. Allow the resin to penetrate into the conc rete and fill all cracks. Mix the resin to a limit of 5 gallons (19 L) at a time for manual application. Reject resin with a significant increase in 512.07 372 viscosity. Redistribute excess material by a squeegee within 10 minutes after application. Front and back movement with the squeegee is recommended over cracks and patch perimeters to enhance penetration. Take all steps necessary to prevent the resin from flowing into lanes open to traffic. Broadcast sand over the entire sealed area of the bridge deck by mechanical means to effect a uniform coverage of 1 to 2 pounds per square yards (0.54kg/m² to 1.08 kg/m²) . Protect the treatment from moisture for not less than 6 hours after placement.
D.Traffic. Do not permit traffic on the treated deck until the resin is tack free, a minimum of 6 hours has elapsed since treatment, and the sand cover adheres sufficiently to resist brushing off by hand.

512.07 Sealing Cracks by Epoxy Injection . This specification covers the repair

of dry, moist or wet cracks or fractures that are 2 to 100 mils (50 to 2500 µm) in thickness in reinforced concrete members. The repair is by means of an e poxy injection system. This system shall consist of a paste epoxy used to seal the surface cracks and an injection epoxy used under low pressure, 200 psi (1400 kPa) max., to penetrate and fill the cracks and bond the crack surfaces together. Material for e ach epoxy shall consist of a two -component modified resin bonding system. The unmodified resin shall be known as Component A and the hardener as Component B. Arrange to have a manufacturer ’s representative at the job site to familiarize him and the Enginee r with the epoxy materials, application procedures and recommended pressure practice. This representative shall direct at least one complete crack or area injection and be assured prior to his departure from the project that the personnel are adequately in formed to satisfactorily perform the remaining repairs. Furnish the Engineer a copy of the manufacturer ’s comprehensive preparation, mixing and application instructions which have been developed especially for use with the proposed epoxy injection system. Ensure that any significant changes to these instructions which are recommended by the representative for an unanticipated situation have been approved by the Engineer prior to the adoption of such changes. Clean concrete surfaces adjacent to the cracks to be sealed only to the extent necessary to achieve an adequate bond with the paste epoxy, and only by procedures which will not cause abrasive grits or concrete dust to penetrate the cracks. Do not permit the use of solvents or thinners in cracks or on bon ding surfaces. Install injection ports or tees in cracks to be injected. Space injection ports or tees at 6 to 12 inches (150 to 300 mm) vertically and 6 to 18 inches (150 to 450 mm) horizontally but in no case closer together than the thickness of the co ncrete member if full depth penetration is desired unless otherwise specified or directed. Set ports or tees in dust free holes made either with vacuum drills or chipping hammers. Seal all surface cracks in the area to be repaired, after injection ports or tees have been inserted into the holes, with paste epoxy between ports to ensure retention of the pressure injected epoxy within the confines of the member. The Department will allow an alternative procedure of sealing the cracks before the injection hole s have been made. Limit the application of paste epoxy to clean and dry surfaces. Limit substrate temperatures to not less than 45 °F(7 °C) during epoxy applications. 512.08 373 Begin the epoxy injection at the bottom of the fractured area and progress upward using a port or tee filling sequence that will ensure the filling of the lowermost injection ports or tees first. Establish injection procedures and the depths and spacings of holes at injection ports or tees. Use epoxy with flow characteristics and injection pr essure that ensure no further damage will be done to the member being repaired. Ensure that the epoxy will first fill the innermost portion of the cracked concrete and that the potential for creating voids within the crack or epoxy will be minimized. Remo ve the injection ports or tees flush with the concrete surface after the fractured area has been filled and the epoxy has partially cured (24 hours at ambient temperature not less than 60 °F (16 °C), otherwise not less than 48 hours). Roughen the surfaces of the repaired areas to achieve uniform surface texture. Remove any injection epoxy runs or spills from concrete surfaces. Obtain two 4 -inch (100 mm) diameter core samples in the first 100 linear feet (30 m) of crack repaired and one core for each 100 linear feet (30 m) thereafter. Take the core samples from locations determined by the Engineer and for the full crack depth. Cores will be visibly examined by the Engineer to determine the extent of epoxy pene tration. Repair the core holes in the concrete with material specified in 705.21.

512.08 Waterproofing

A.General. Apply an even and uniform coating of asphalt materials using brushes, squeegees, or spray equipment. If using spray equipment, provide porta ble power pressure type spraying equipment capable of being moved to the location of the waterproofing operation. Protect concrete surfaces not covered with waterproofing from overspray, spilling, or otherwise marring of the surface with the asphalt materi als. Ensure that the edge of any exposed application is sharply defined true to line with a uniform exposure. Do not apply waterproofing fabric or membranes over attachments and hardware. Seal the discontinuities in waterproofing with Asphalt, 702.06, or h ot applied joint sealer, 705.04.
B.Preparation of Surface
1.Asphalt Materials. Remove concrete projections. Using wire brushes and clear water, remove dirt and the outside film of cement. Before applying asphalt materials, ensure that the concrete is cle an and dry and the concrete temperature is at least 40 F (4 C).
2.Membranes. Remove protrusions from the concrete. Sweep off dirt and dust, and blow the concrete clean. Fill joints or cracks greater than 3/8 inch (10 mm) wide with portland cement mortar . In addition to the above, remove oil and grease from surfaces for Type 3 membranes using water and a detergent designed to remove oil and grease from concrete. Flush residual detergent from the surface. Do not allow traffic on the cleaned surface. 512.08 374 C. Primer Coat. Apply the primer coat at the rate of 0.10 to 0. 20 gallon (0.50 to 1.00 L) of asphalt material per square yard (square meter). For primer coats applied between June 1 and September 1, use asphalt primer for waterproofing or emulsified asphalt primer conforming to 512.02. For primer coats applied between September 1 and June 1, use asphalt primer for waterproofing conforming to 512.02. If practical, apply asphalt emulsion using spray equipment. If subjected to traffic, spread sand on the primer coat for protection. Broom off excess sand before applying asphalt waterproofing.
D.Type A Waterproofing. This type of waterproofing consists of one primer coat and at least two coats of asphalt material conforming to 702.06 to provide a total of at least 1 gallon (5 L) of asphalt per square yard (m ²) on flat areas and at least 1/2 gallon per square yard (3 L/m ²) on vertical or sloping surfaces. Start applying the waterproofing at the lowest point, and progress to a higher elevation. Uniformly cover the su rface except apply more asphalt in corners and over construction joints. Apply the asphalt material at a temperature from 250 to 350 F (121 to 177 C).
E.Type B Waterproofing. This type of waterproofing consists of one primer coat, three coats of asphalt material conforming to 702.06, and two layers of waterproofing fabric conforming to 711.24 applied as follows:
1.On a clean, dry, and well -primed surface, apply a thorough coating of asphalt at a temperature from 250 to 350 F (121 to 177 C).
2.Apply t he coating at a rate of at least 1/3 gallon per square yard (1.5 L/m²) of surface.
3.While the asphalt is hot enough to penetrate the fabric, lay the fabric according to the following:
a.Surfaces Wider than Normal Fabric Strip. For the first strip, lay a half-width [normally 18 inches (0.5 m) wide] strip of fabric. For the second strip use a full -width strip of fabric, and lap the entire width of the first strip. Lap each succeeding strip 2 inches (50 mm) more than half its full width. Lap the fabric stri ps in the direction of water flow.
b.Surfaces with Same Width as Fabric Strip. For the first strip, lay a full-width strip. For the second strip, lay another full -width strip, covering the first. Lay each strip without wrinkles, folds, or pockets. Thoroug hly coat the strip with asphalt for the full width of the lap before laying the succeeding strip. Each application shall entirely conceal the texture of the fabric.
4.Apply a final coat of asphalt to provide a thorough covering for the fabric.
5.For all three coats, use a total of at least 1 gallon (5 L) of asphalt waterproofing material per square yard (m ²). Lap ends of fabric strips at least 12 inches (0.3 m), and stagger the end joints. 512.08 375 F. Type E Waterproofing. This type of waterproofing consists of a cold applied liquid membrane waterproofing material conforming to 702.08. Apply the coating when the air temperature is 40 ºF ( 4 ºC) or above, on a clean and dry surface, at a rate of 20 to 30 square feet per gallon (0.49 to 0.74 m²/L) to achieve a tota l thickness of 55 to 65 mils (1375 to 1625 μm). Cover after cured according to the manufacturer’s recommendation and within 45 days of application.
G.Type 2 Membrane Waterproofing. This type of waterproofing consists of a rubberized asphalt and peel -and-stick waterproofing membrane 711.25. Follow manufacture r’s written recommendations for application of this product, which shall be provided to the project. After installing the primer coat, if required, remove the membrane’s release liner and place the adhesive side on the prepared concrete surface. Lay the me mbrane smooth and free of wrinkles. Lap joints in membranes by at least 1 inch (25 mm). Store membrane materials indoors at temperatures not to exceed 120 °F (49 °C). For precast concrete three - and four -sided structures, install Type 2 membrane on the exterior vertical and exterior top horizontal surfaces .
H.Type 3 Membrane Waterproofing. This type of waterproofing consists of a primer coat conforming to 705.04 and a waterproofing membrane consisting of a high density asphalt mastic between two layers of polymeric fabric conforming to

711.29 The application of this product shall follow the manufacturer’s written

recommendations, which shall be provided to the project. Keep membrane and primer materials dry before installation. Heat the membrane primer in an oil primer heated, double -jacket kettle. Use a kettle that is clean and free of other materials with any obvious buildup scraped out. The Contractor may use a single -jacket kettle if the primer is capable of being heated in direct fire to the applica tion temperature. Heat primers within the manufacturer’s recommended temperatures. On bridges with curbs, apply the primer and membrane 3 inches (75 mm) up the curb face. On prestressed box beam bridges with no approach slab, apply the primer and membrane 6 inches (150 mm) over the ends of the beams. On prestressed and slab bridges with approach slabs, apply the primer 2 feet (600 mm) out onto the approach slab. If the plans require a Type 3 membrane on the top exterior surface of precast concrete three - or four-sided structures, apply the primer and membrane to overlay the vertical exterior sides of the structure by 12 inches (300 mm). Apply primer no further than 5 feet (1.5 m) in front of the membrane using a squeegee to fill all voids and imperfections. Apply membrane from the low to the high side of the surface. Apply an extra bead of primer at the edge of the membrane. Lap joints in membranes by at least 3 inches (75 mm). After installing the membrane over the entire surface, seal joints in the membrane by applying primer and smoothing with a V -squeegee. If asphalt pavement is to be placed directly over the water proofing membrane, first apply tack coat as specified in 407 without damaging the membrane. 512.09 376 512.09 Method of Measurement. The Department will m easure Waterproofing, of the type specified, by the number of square yards (square meters) or on a lump sum basis. The Department will measure sealing of concrete surfaces by the number of square yards (square meters) of coated area projected to a two -dime nsional surface. The Department will measure the removal of existing coatings from concrete surfaces in square yards (square meters) removed. The Department will measure the sealing of concrete bridge decks with HMWM resin and treating concrete bridge deck s with SRS as the actual area in square yards (square meters ) of surfaces treated. The Department will measure the actual length in linear feet (meters) of crack repaired by epoxy injection.

512.10 Basis of Payment. The Department will pay for accepted quantities at

the contract prices as follows: The Department will consider the cost for the obtaining and repairing the two cores used by the Engineer to determine the extent of the epoxy penetration as incidental to the work of repairing the concrete by e poxy injection. The Department will consider the removal of dust, dirt, oil, wax, curing compounds, efflorescence, laitance, and other foreign materials as incidental to the surface preparation of the concrete surfaces to be sealed. When the surface to be sealed contains an existing coating, the Department will consider all materials, equipment and labor to remove the existing coating as incidental to the removal of existing coatings. Item Unit Description 512 Square Yard Sealing of concrete surfaces (Square Meter) 512 Square Yard Sealing of concrete surfaces (Square Meter) (non-epoxy) 512 Square Yard Sealing of concrete surfaces (Square Meter) (epoxy urethane) 512 Square yard Sealing of concrete bridge (Square Meter) decks with HMWM resin 512 Square yard Treating concrete bridge (Square Meter) decks with SRS 512 Square yard Treating concrete bridge (Square Meter) decks with Gravity -Fed Resin 512 Foot Concrete repair by epoxy injection (Meter) 512 Square Yard Type A Waterproofing (Square Meter) or Lump Sum 512 Square Yard Type B Waterproofing (Square Meter), or Lump Sum 513.01 377 512 Square Yard Type E Waterproofing (Square Meter), or Lump Sum 512 Square Yard Type 2 Waterproofing (Square Meter), or Lump Sum 512 Square Yard Type 3 Waterproofing (Square Meter), or Lump Sum 512 Square Yard Removal of Existing Coatings from Concrete (Square Meter) Surfaces ITEM 513 STRUCTURAL STEEL MEM BERS

513.01 Description

513.02 Fabricator Approval Procedure

513.03 Levels of Fabricator Quali fication

513.04 General

513.05 Fabricator Documentation Responsibility

513.06 Shop Drawings

513.07 Levels 1 through 6, Pre fabrication Meeting

513.08 Materials

513.09 Material Control

513.10 Care of Material

513.11 Workmanship and Straightening

513.12 Finis h

513.13 Stiffeners

513.14 Fillers

513.15 Horizontally Curved Beams and Girders

513.16 Joints and Splices

513.17 Pin Holes

513.18 Pins and Rollers

513.19 Holes for High -Strength and Bearing Bolts

513.20 High -Strength Steel Bolts, Nuts, and Washers

513.21 Welding

513.22 Stud Shear Connectors

513.23 Threads for Bolts and Pins

513.24 Shop Assembly

513.25 Nondestructive Testing

513.26 Shipping, Storage, and Erection

513.27 Shop Coating

513.28 Cleaning ASTM A 709/A 709M, Grade 50W (345W) Steel

513.29 Method of Measurement

513.30 Basis of Payment

513.01 Description. This work consists of preparing shop drawings, furnishing

and fabricating structural steel members, nondestructive testing, fabricator performed quality control, documentation, cleaning, shop coatin g, and erecting 513.02 378 structural steel and other structural metals. Prepare shop drawings and erect structural steel according to Item 501 and the additional requirements below. Shop painting shall conform to Item 514. The work also includes any work to move existing steel structures to the plan location, making necessary repairs and alterations, and connecting or joining new and old construction. The terms “main,” “secondary,” or “detail,” as referred to in Item 513, are defined as follows: “main” refers to mate rial, members, and fasteners that are primarily stressed by live load and structure weight; “secondary” refers to material, members, and fasteners that do not directly support live load or main members; “detail” refers to essential non -structural material, members, and fasteners.

513.02 Fabricator Approval Procedure. Select fabricators that are listed by

the Department before the Contract letting date as evaluated by the Office of Materials Management and prequalified according to Supplement 1078. The Offic e of Materials Management may accept subletting of processes that require specialized machinery or knowledge. Submit written requests for subletting to the Office of Materials Management. The Office of Materials Management will determine if the process is uncommon and will evaluate the qualifications of the proposed sublet fabricator. The fabricator’s quality control staff shall witness and perform quality control of the sublet work.

513.03 Levels of Fabricator Qualification. There are eight levels of fabri cator

qualification. The Office of Materials Management will classify each fabricator at the highest level of fabrication it is qualified to perform. 513.04 379 Level Description of Capabilities SF Standard fabricated members described and paid for as Item 516, 517, and 518 and detailed by standard bridge drawings. Material and fabrication acceptance by certification with random Department audits of the work and documentation. UF Unique fabricated members not covered by standard bridge drawings and not designed to c arry tension live load. Examples include curb plates, bearings, expansion joints, railings, catwalk, inspection access, special drainage, or other products. Examples also include retrofit cross frames, retrofit gusset plates, retrofit lateral bracing, or o ther miscellaneous structural members not included in Levels 1 through 6. Quality assurance of shop drawings, material test reports, and inspection according to Supplement 1078. 1 Single span, straight, rolled beam bridges without stiffeners, Secondary an d Detail materials designed to carry tension live loads such as retrofit moment plates. Case II Loading. Quality assurance of shop drawings, material test reports, and inspection according to Supplement 1078. 2 Multiple span, straight, rolled beam bridges without stiffeners. Case II loading. Quality assurance of shop drawings, material test reports, and inspection according to Supplement 1078. 3 Single or multiple span, straight, dog legged, or curved, rolled beam bridges including stiffeners. Case I or II Loading. Quality assurance of shop drawings, material test reports, and inspection according to Supplement 1078. 4 Straight or bent welded plate girder bridges. Case I or II loading. Quality assurance of shop drawings, material test reports, and inspec tion according to Supplement 1078. 5 Straight, curved, haunched, or tapered welded plate girder bridges. Case I or II loading. Quality assurance of shop drawings, material test reports, and inspection according to Supplement 1078. 6 Truss bridges, fractu re critical bridges, fracture critical members, or fracture critical components new or retrofitted. Case I or II loading. Quality assurance of shop drawings, material test reports, and inspection according to Supplement 1078.

513.04 General.

Perform all steel fabrication including the shop application of coatings in a pre - qualified structural steel fabricating shop consisting of adequately sized permanent buildings with equipment, heat and light, and experienced personnel to satisfactorily perform all ne cessary operations. Perform flame cutting, air carbon -arc gouging, cambering, welding, cleaning, and painting inside permanent buildings that are maintained at the required environmental conditions. The fabricator may perform shop assembly of large pieces for fit -up of field connections outdoors. These provisions will not apply to steel requiring fabrication at the bridge site in the repair, alteration or extension of an existing structure. If repairing, extending, or altering existing structures, take measurements of the existing structure as required to accurately join old and new work. Include these measurements on shop drawings. Measurements shown on the plans that indicate the extent and nature of repair, alterations or extension shall not relieve t he Contractor of this responsibility. 513.05 380 At least two weeks before starting shop fabrication, the fabricator shall notify the Office of Materials Management and furnish a proposed fabrication schedule for the work. Unless the Office of Materials Management pr ovides a written waiver of a hold or witness point inspection, the fabricator shall store members completed during the inspector’s absence in a manner that allows the inspector to completely and safely inspect the finished work. The fabricator shall not sh ip fabricated members performed under Item 513, UF Level or Levels 1 through 6 from the shop without prior hold point inspections unless the Office of Materials Management waives the inspection. The Office of Materials Management will not conduct the sched uled final inspection until the fabricator completes and inspects with documentation, final fabrication and shop coatings and the Contractor documents approval of shop drawings and material test reports. The Office of Materials Management will not conduct a final fabrication inspection of SF Level members. Instead, the Office of Materials Management will conduct random inspections during the fabricator’s work. The fabricator shall provide an office with the following attributes:

A.A minimum floor area of 1 20 square feet (11 m ²).
B.A minimum ceiling height of 7 feet (2.1 m).
C.Adequate working and storage facilities with one locking file cabinet for the exclusive use of the Department’s inspector, lighting, and electrical outlets.
D.Provisions for heating to a minimum temperature of 68 F (20 C) and adequately ventilated.
E.A telephone with direct access to an outside trunk line for the exclusive use of the inspector. If using steel stamps for identification purposes, use the “mini -stress” or “stressless ” type.

513.05 Fabricator Documentation Responsibility. The fabricator shall keep

and maintain documentation records as specified in Supplement 1078. At the Department’s request, provide access to the above documents for audit, inspection, and copying.

513.06 Shop Drawing. Provide shop drawings conforming to 501.04 and the

following requirements: Include details, dimensions, size of materials, match mark diagrams for field connections, a diagram identifying, by some unique mark, each area of a welded splice to be covered by a single radiograph, and other information necessary for the complete fabrication and erection of the metal work. For multiple span beam and girder bridges, include an overall layout with dimensions showing the relative unloaded vertical and horizontal position of beam or girder segments with respect to a full length base or work line. Account for 513.07 381 camber and horizontal curvature of the beams or girders, and the effect of deck surface profile in this layout. Show required offsets for vertical and horizontal curvature at approximately each one -fourth of span length, at field splices, and at bearing points. For horizontally curved members, show the offset to a baseline strung from end to end of the member, every 10 feet (3 m) of length. Identify the grade (ASTM designation), CVN, fracture critical, or any special testing requirements for each piece of steel. Identify pieces made of different grades of steel with different assembling or erecting marks, even if the pieces have identical dimensions and detail. Identify the welding procedure by the WPS number at each joint and the location and identification numbers of all radiograph tests. Detail structural steel to fit under full steel dead load and prior to deck placement with the webs of p rimary members plumb.

513.07 Levels 1 through 6, Pre fabrication Meeting. After providing the notice

and schedule required by 513.04 and at least 3 days after the Department receives shop drawings, conduct a prefabrication meeting at the fabricator’s facili ties, or another location agreed to by all parties. The fabricator and its quality control specialists for fabrication and painting, the inspector, and the Contractor, or its designated representative, shall attend the meeting. The purpose of this meeting is to review any fabrication issues, including information on shop drawings, inspection, hold or witness points, unique fabrication items, special processes, and both the fabrication and project schedule. The fabrication quality control specialist shall co nduct the meeting and record and distribute meeting minutes that document all issues discussed. Fabrication may begin after the prefabrication meeting is complete.

513.08 Materials. Furnish materials conforming to 501.06.

513.09 Material Control. Identify and mark each piece of steel according to the

shop drawings and the following requirements. Immediately after removing steel that is furnished in tagged lifts or bundles, mark the individual pieces of steel with the ASTM A 6/A 6M specification identificati on color code and heat number. The fabricator may furnish material from stock that is marked with the heat number and mill test report. If separated from the full -size piece furnished by the supplier, mark excess material placed in stock for later use with the heat number and, if provided, with the ASTM A 6/A 6M specification identification color code. During fabrication, clearly and legibly mark the specification identification color code and heat number on each piece of steel. Before cutting steel into smaller size pieces, clearly and legibly mark each smaller size piece with the ASTM A 6/A 6M specification identification color code and heat number. Unless otherwise approved by the inspector, mark pieces of steel that will be subject to fabricating opera tions such as blast cleaning, galvanizing, heating for 513.10 382 forming, or other operations that may obliterate paint color code and heat number markings with steel stamps or with a substantial tag firmly attached to the piece of steel. At locations acceptable to the Office of Materials Management, stamp the heat numbers into main material tested for CVN. Issue cutting instructions by cross -referencing the assembly marks shown on the shop drawings with the corresponding item covered on the mill purchase order. The fabricator’s system of assembly -marking individual pieces of steel and issuing cutting instructions shall provide a direct reference to the appropriate mill test report. The fabrication quality control specialist shall provide the Engineer with a letter documenting that the fabricator performed material control according to this specification.

513.10 Care of Material. Store structural material at the shop or field above the

ground, upon platforms, skids, or other supports. Use straight structural steel with clean and dry surfaces before working it in the shop. Before using, clean all rusted or corroded material. Only use this material if it conforms to ASTM A 6/A 6M thickness tolerances after cleaning.

513.11 Workmanship and Straightening. If necessary to st raighten rolled

material, use methods that will not damage the member. If carefully planned and supervised, apply localized heat for straightening. Do not allow the temperature of the heated area to exceed 1150 F (620 C) as controlled by pyrometric stick or thermometers. Do not quench to accelerate cooling. Do not kink or offset the material if using mechanic or hydraulic force to camber or strengthen material. Do not cold bend fracture critical materials. Camber rolled beams as shown on the plans in the prequalified fabricating shop using heat or hydraulic jacks. Control heating as specified above and follow a formal shop heating procedure. Camber plate girders by trimming web plates before assembly. During fabrication, shipping, and erection, support and handle members to maintain camber. Fabricate structural steel to within the dimensional tolerances specified by Articles 3.5 of the AASHTO/AWS Bridge Welding Code , with the following modifications:

A.Waviness, the deviation of the top or bottom surface o f a flange from a straight line or plan curvature, shall not exceed 1/8 inch (3 mm) when the number of waves in a 10 -foot (3 m) length is four or less, or 1/16 inch (1.6 mm) when more than four, but sharp kinks or bends shall be cause for rejection.
B.For the measurement of camber during lay down, position the bearing points both horizontally and vertically to plan dimensions 1/8 inch (3 mm).
C.Measure camber as the vertical offset between the steel and the common base line extending from abutment be aring to abutment bearing. The maximum camber tolerance at mid -span shall be 0 inch (0 mm) and the greater of +3/4 inch (+19 mm) or the designed haunch height. Prorate the maximum camber tolerance at mid -span between the center of the span and each adjacen t bearing to provide a smooth unbroken curve. 513.12 383 D. Permissible difference in horizontal curvature of top and bottom flange at any point on centerline of member, when measured as specified in 3.5.1.4, shall not exceed 3/8 inch (10 mm)

513.12 Finish. Plane she ared edges of all main material to a minimum depth of

1/4 inch (6 mm) except for ASTM A 709/A 709M, Grade 36 (250) steel having a thickness of 5/8 inch (16 mm) or less. Remove fins, tears, slivers, and burred or sharp edges from steel members by grinding. If these conditions appear during the blasting operation, re -grind and re -blast the steel members to the required surface profile. The fabricator may flame cut structural steel. Provide a smooth surface, free from cracks and notches, and use a mechanical g uide to provide an accurate profile. Roll and flame cut surfaces according to the AASHTO/AWS Bridge Welding Code , as amended by Supplement 1011. Provide a surface finish for bearing and base plates and other bearing surfaces that contact each other or conc rete according to ANSI B46.1, Surface Roughness, Waviness and Lay, Part I. TABLE 513.12 -1, ANSI B46.1 Steel slabs 2000 mil (50.0 µm) Heavy plates in contact in shoes to be welded 1000 mil (25.0 µm) Milled ends of compression members, milled or ground ends of stiffeners and fillers 500 mil (12.5 µm) Bridge rollers and rockers 250 mil (6.4 µm) Pins and pin holes 125 mil (3.2 µm) Sliding bearings 125 mil (3.2 µm)

513.13 Stiffeners. Place the bearing end of bearing stiffeners flush and square

with the web and in a manner so at least 75 percent of the area of the bearing end is in contact with the inner surface of the flange. The other end of the bearing stiffener shall have a tight fit as defined below. Position bearing stiffeners to be vertical after erection. Weld intermediate stiffeners that are not used in pairs to the compression flange, and provide a tight fit for the tension flange. Weld intermediate stiffeners connected to cross frame angles to the top and bottom flange. A tight fit is defined a s the contact between the stiffener and flange over some portion of the end of the stiffener and having no gap greater than 1/16 inch (1.6 mm). Clip stiffeners 2 1/2 inches (65 mm) along the web and 1 inch (25 mm) along the flange to clear flange -web welds and fillet or rolled shapes. When attaching stiffeners to the web and flanges, do not extend welds to the edge of the stiffeners or into the clip area. Terminate these welds 1/4 ±1/8 inch at the flange connections and 1/2 ±1/4 inch at the web connection.

513.14 Fillers. Detail the shop drawings to show fill plates that compensate for

the misalignment of abutting elements due to differences in thickness of flanges and webs at the splice locations. Detail the fill plates to the nearest 1/16 inch (1.6 mm) in thickness, but not less than 1/8 inch (3 mm) thick. However, in the final shop assembly, furnish fills of sufficient thickness to compensate for misalignment of abutting elements due to standard rolling mill tolerances or due to differences in 513.15 384 thicknesses of flanges and webs at the splice location. The actual fills used shall compensate for differences in total thickness or relative positions of more than 1/16 inch (1.6 mm) but with no fills less than 1/8 inch (3 mm) thick. Provide fill plates in bolted joi nts that are flush with the perimeter of the splice plates.

513.15 Horizontally Curved Beams and Girders. If members are to be heat

curved, submit the detailed procedure, including necessary calculations, to the Office of Materials Management. Obtain the O ffice of Materials Management’s acceptance of the procedure before starting this work. Curve beams and girders using heat according to AASHTO Standard Specifications for Highway Bridges , except that the fabricator may cut flanges for girders to obtain the required alignment.

513.16 Joints and Splices. In bolted construction where tension or flexural

members are spliced, maintain a clearance of not more than 1/4 inch (6 mm) between the abutting surfaces of spliced members. For spliced compression members, fa ce the abutting surfaces to provide a uniform bearing when properly aligned and completely bolted. In welded construction, prepare abutting surfaces as shown on the shop drawings. Verify the preparation for field welded butt joints in main members by a com plete shop assembly according to 513.24.

513.17 Pin Holes. Bore pin holes after the member is fabricated and true to size,

at right angles to the axis of the member and parallel to each other. Pin holes for up to 5-inch (127 mm) diameter pins shall not exc eed the pin diameter by more than 0.020 inch (0.51 mm) and pin holes for larger pins shall not exceed the pin diameter by more than 0.031 inch (0.79 mm).

513.18 Pins and Rollers. Use pins and rollers made from cold rolled steel,

accurately turned to size, straight and smooth, and entirely free from flaws. Pins over 9 inches (230 mm) in diameter shall be annealed. In pins larger than 9 inches (230 mm) in diameter, bore a hole not less than 2 inches (50 mm) in diameter the full length of the axis. Furnish one pilot and one driving nut for each size of pin.

513.19 Holes for High -Strength Bolts and Bearing Bolts . Provide cylindrical

holes, perpendicular to the member, clean cut, and free of ragged edges. Remove burrs by countersinking not more than 1/16 inch (1.6 mm) or by grinding. Provide finished holes with a diameter not larger than the nominal diameter of the bolt plus 1/16 inch (1.6 mm). The hole diameter shall not vary by more than 1/32 inch (0.8 mm) from a true circle for 85 percent of the holes in a c ontiguous group, and not more than 1/16 inch (1.6 mm) for the remainder. Punch holes using a die with a diameter not exceeding that of the punch by more than 1/16 inch (1.6 mm). Ream and drill holes using twist drills and twist reamers. Wherever possible, direct the reamer by mechanical means. Sub-drill holes 3/16 inch (5 mm) less in diameter than the nominal diameter of the bolt, and ream the holes to size with the parts assembled, except: 513.20 385 A. The fabricator may sub -punch main material conforming to ASTM A 709/A 709M, Grade 36 (250) steel that is less than 3/4 inch (19 mm) thick, and Grade 50 (345) or 50W (345W) steel that is less than 5/8 inch (16 mm) thick.

B.The fabricator may drill full -size holes in materials assembled and adequately clamped together.
C.The fabricator may punch full -size holes in secondary and detail material conforming to ASTM A 709/A 709M, Grade 36 (250) steel that is less than 3/4 inch (19 mm) thick, and Grade 50 (345) or 50W (345W) steel that is less than 5/8 inch (16 mm) thick.
D.The fabricator may make assemblies such as floor beams connected to girders and rolled beam spans connected by diaphragms through steel templates. Place all sub -punched or sub -drilled holes with sufficient accuracy such that after assembling (before reami ng) a cylindrical pin 1/8 inch (3 mm) smaller than the nominal size of the punched hole may be entered perpendicular to the face of the member without drifting in not less than 75 percent of the contiguous holes in the same plane. All holes shall allow a p in 3/16 inch (5 mm) smaller than the nominal size of the punched holes to be inserted in the above manner. Do not plug located holes without written approval from the Office of Materials Management. Provide steel templates with hardened bushings in holes t hat are accurately located in relation to the centerline of the connection as inscribed on the template. The fabricator is not required to use hardened bushings when using a roto -broach, shell drill, or other similar tool, to make the holes. Ream and drill holes through multiple piles only if the plies of the joint are held tightly together with bolts or clamps and if sub -punched or sub -drilled, only if the joint is pinned. Disassemble and clean the piles of burrs and shavings before final assembly. The Con tractor may drill or punch bolt holes full sized in unassembled pieces or connections, including templates for use with matching sub -sized and reamed holes, using suitable numerically controlled (N/C) drilling or punching equipment. If using N/C drilling o r punching equipment, demonstrate the accuracy of the drilling or punching procedure to the inspector according to 513.24. After holes are reamed or drilled full size, 85 percent of the holes in any contiguous groups shall have no offset greater than 1/32 inch (0.8 mm) between adjacent plies. The remainder of the holes shall not be offset more than 1/16 inch (1.6 mm) between adjacent plies. If requested in writing, the Office of Materials Management may consider other methods of preparing holes for high -strength bolts.

513.20 High -Strength Steel Bolts, Nuts, and Washers . Provide high -strength

steel bolts, nuts, and washers conforming for all bolted connections including erection bolts for cross frames and lateral bracing to 711.09.

A.General. Provide the Engineer with access to the work for observing the installation and the tightening and checking of the bolts. 513.20 386 Determine the required bolt length by adding the value from Table 513.20 -1 to the grip. The table values include an allowance for manufacturing to lerances and provide a bolt length for threads to protrude through the nut. Add 5/32 inch (4 mm) for each hardened flat washer used and 5/16 inch (8 mm) for each beveled washer used. Adjust the length, as determined by Table 513.20 -1, to the next longer 1/ 4 inch (6 mm); when installed, the end of the bolt shall be flush with or project several thread lengths outside the face of the nut. TABLE 513.20 -1 Bolt Size (inches) To determine required bolt length, add to grip[1] (inches) 1/2 11/16 5/8 7/8 3/4 1 7/8 1 1/8 1 1 1/4 1 1/8 1 1/2 1 1/4 1 5/8 1 3/8 1 3/4 1 1/2 1 7/8 [1] Total thickness of all connected material excluding washers. TABLE 513.20 -1M Bolt Size (mm) To determine required bolt length, add to grip[1] (mm) M16 24 M20 28 M22 31 M24 35 M27 38 M30 41 M36 47 [1] Total thickness of all connected material excluding washers. Use bolts, nuts, and washers with a residual coating of lubricant when received. Bolts, nuts, and washers without their original lubrication shall not be used.
B.Preparation. With the exception of metalizing, galvanizing, and both organic zinc and inorganic zinc primers, remove coatings from joint surfaces, including surfaces adjacent to the bolt heads, nuts, and washers. Remove lacquer, dirt, oil, loose scale, rus t, burrs, pits, and other substances or defects that prevent solid seating of the parts or interfere with the development of complete frictional contact. Do not place gaskets or other yielding material between joint surfaces.
C.Installation. For each bolt , place a hardened washer under the element (nut or bolt head) turned in tightening. If an outer face of the bolted parts has a slope of more than 1:20 with respect to a plane normal to the bolt axis, use a smooth beveled washer to compensate for the lack of parallelism. If necessary, the Contractor may clip washers, at one location, not closer than seven -eighths of the bolt diameter from the center of the washer. 513.20 387 During final assembly of the parts to be bolted, first install a sufficient number of drift pi ns to provide and maintain accurate alignment of holes and parts, then a sufficient number of bolts tightened to a snug tight condition to bring all the parts of the joint into complete contact. Replace any bolts that were installed before installing drift pins. Before releasing the member from the hoisting equipment, fill half the holes with drift pins and bolts tightened to a snug tight condition in at least 50 percent of the holes (preferably, half pins and half bolts) but use at least two drift pines in each flange and web of each beam or girder. Install bolts starting at the most rigidly fixed or stiffest point and progress toward the free edges. Use cylindrical drift pines that are not more than 1/32 inch (0.8 mm) smaller than the hole diameter. Bolts are snug tight when an impact wrench begins to impact the nut or when a man applies full effort using an ordinary spud wrench. Install bolts in the remaining open holes and tighten the bolts to a snug tight fit, after which all bolts shall be tightened com pletely by the turn -of-nut method. Where difficulty is experienced with the fit of the connection and the bolts are used to draw the elements into contact, check all bolts in the affected portion of the connection for a sustained snug tight condition. Repl ace drift pins with completely tightened bolts only after all the remaining holes are filled with completely tightened bolts. Do not field ream holes drilled full size during fabrication. After bolts are snug tight, the wrench operator shall match -mark the outer face of the nut with the flush or protruding portion of the bolt using a crayon or paint. The Engineer will use the match -marks to determine the relative rotation between the bolt and nut during final tightening using the turn -of-the-nut method. Com mence tightening at the most rigidly fixed or stiffest point and progress toward the free edges, both in the initial snugging up and in the final tightening. If required because of wrench operation clearances, tightening may be done by turning the bolt. If used, provide impact wrenches of adequate capacity to perform the required tightening each bolt in approximately 10 seconds. Do not reuse galvanized A 325 bolts. Re-tightening previously tightened bolts that became loose by tightening adjacent bolts is no t reuse. Follow the additional bolting requirements in 513.26.
D.Bolt Tension. When all bolts in the joint are tight, the minimum bolt tension for each bolt size is shown in Table 513.20 -2. 513.20 388 TABLE 513.20 -2 Bolt Size (inches) Bolt Tension[1] (kips), minimum A 325 1/2 12 5/8 19 3/4 28 7/8 39 1 51 1 1/8 56 1 1/4 71 1 3/8 85 1 1/2 103 [1] Equal to 70 percent of specified minimum tensile strengths of bolts, rounded off to the nearest kip. TABLE 513.20 -2M Bolt Size (mm) Bolt Tension[1] (kN), minimum A 325M M16 91 M20 142 M22 176 M24 206 M27 267 M30 327 M36 475 [1] Equal to 70 percent of specified minimum tensile strengths of bolts, rounded off to the nearest kN. TABLE 513.20 -3 NUT ROTATION FROM SN UG TIGHT CONDITION Bolt Length (as measured from underside of head to extreme end of point) Disposition of Outer Faces of Bolted Parts Both faces normal to bolt axis One face normal to bolt axis and other face sloped not more than 1:20 (bevel washer not used) Both faces sloped not more than 1:20 from normal to bolt axis (bevel washer not used) Up to and including 4 diameters 1/3 turn 1/2 turn 2/3 turn Over 4 diameters but not exceeding 8 diameters 1/2 turn 2/3 turn 5/6 turn Over 8 diameters but not exceeding 12 diameters 2/3 turn 5/6 turn 1 turn Attain the bolt tension specified in Table 513.20 -2 by tightening all bolts, the applicable amount of nut rotation specified in Table 513.20 -3 by the turn -of-nut method. Nut rotation is relative to bolt, regardless of the element (nut or bolt) being turned . Tighten bolts requiring 1/2 turn and less within ±30 degrees and tighten bolts requiring 2/3 turn and more within ±45 degrees. 513.21 389 E. Inspection.
1.The Engineer will inspect the first completed connection of each bridge according to 513.20.E.2 below and sub sequent connections the Engineer deems necessary. Thereafter, where the Engineer has approved the joint compactness and snug -tight condition of bolts prior to bolt tightening by the turn -of-nut method, the bolt tension as required in Table 513.20 -2 shall b e considered as attained if the amount of nut rotation specified by Table 513.20 -3 is verified by the required match - marking.
2.Furnish and use manual torque wrenches to inspect bolts. Perform test to the satisfaction of the Engineer. Calibrate the inspec tion torque wrenches at least once each workday using a device, approved by the Engineer, and capable of indicating bolt tension. Use three bolts, placed and tensioned individually, representative of the grade, size, length, and condition used in the struc ture to determine the job inspection torque according to 513.20.E.3. Place a washer under the part being turned.
3.Tighten each of the three representative bolts, using any convenient manner, to the tension shown in Table 513.20 -2. Then, using the inspect ion wrench, apply a slow steady pull to the tightened bolt and measure the torque required to turn the nut or head 5 degrees, approximately 1 inch (25 mm) at a 12 -inch (300 mm) radius in the tightening direction. Use the average torque measured in the tens ioning of the three bolts as the job inspection torque.
4.With the Engineer present, randomly select for inspection two bolts or 10 percent of the bolts, whichever is greater, from each connection represented by the 3 -bolt sample described in 513.20.E.2. Using the inspection wrench, apply the job inspection torque in the tightening direction. The Engineer will accept the connection if the job inspection torque does not turn the nut or bolt head. If the job inspection torque turns a nut or bolt head, apply the job inspection torque to all the bolts in the connection and reinspect the connection as described above.
F.Calibration Devices. The manufacturer of the calibration device or a qualified testing laboratory shall periodically examine each calibration d evice at least once each year and other times if requested by the Engineer. After calibration, the manufacturer or testing laboratory shall certify that each calibration device accurately indicates the actual bolt tension.

513.21 Welding. Perform welding b y the shielded metal -arc, submerged arc,

flux cored arc, or stud welding process. Only shielded metal arc (stick) welding is prequalified. All other welding processes require testing and approval by the Office of Materials Management. Consideration will be given to other methods of metal - arc welding if a written request is submitted to the Office of Materials Management. In other respects, the AASHTO/AWS Bridge Welding Code , as amended by Supplement 1011, shall govern the work. Post copies of the shop weldi ng procedures at each welding location. Weld only fracture critical and main members when the fabrication quality control specialist and inspectors are physically at the facility. The fabricator shall not perform fracture critical welding without prior sch eduling with the fabrication 513.22 390 quality control specialist and the inspector. The fabrication quality control specialist shall witness the minimum percentages specified in Supplement 1078 and shall check all welding processes. For non -fracture critical welds, the fabrication quality control specialist shall perform frequent inspections, and check all welding processes.

513.22 Stud Shear Connectors. Perform stud welding according to the

AASHTO/AWS Bridge Welding Code, as amended by Supplement 1011, and this subsection. In addition to the stud bend tests of Article 7.6.6.1 of the AASHTO/AWS Bridge Welding Code, perform bend tests of stud shear connectors at the start of each workday, when welding has been interrupted for an hour or more, when changing grounds, when changing weld settings, and when changing cable loop due to arc blow. Do not weld more than 500 studs without the welds being field bend tested in accordance with the specified procedure. The Contractor may leave in the bent position tested studs tha t show no sign of failure, as determined by the Engineer. Weld stud shear connectors to the top flanges of beams or girders after the steel has been erected and suitable scaffolding or deck forming has been provided. Studs may be welded to beam or girder w ebs, end dams, bearing plates, or to other secondary members and detail material in the shop. For galvanized structures with welded shear connectors, remove the galvanic coating by grinding at each connector prior to welding.

513.23 Threads for Bolts and P ins. Threads for pins shall conform to the

Unified Standard Series ANSI B1.1 -UNC (ANSI B1.13M) Class 2A (6g) for external threads and Class 2B (6H) for internal threads, except that pin ends having a diameter of 1 3/8 inches (35 mm) or more shall be thread ed 6 threads to the inch (4.23 mm/thread).

513.24 Shop Assembly. Remove paint, grease, oil, rust, loose mill scale, and

protruding edges or burrs from all contact surfaces. Unless waived by the Office of Materials Management, do not assemble and weld flang es and webs to form girders or other similar members and do not accomplish fabrication or assembly that interferes with the repair of a butt weld until the fabrication quality control specialist for the A rated fabricators or the inspector for B and C rate d fabricators examines and approves radiographs of all butt welds in the component parts. Perform fit -up work with the members assembled in unloaded positions as shown on the shop drawing layout required by 513.06. During shop assembly, adequately support members, especially at joints, to prevent misalignment or deflection and designate supports that prevent settlement during the fit -up, reaming or drilling of connections. The fabrication quality control specialist shall maintain records of the actual horiz ontal and vertical dimensions and relative positions of each assembly for each offset required by 513.06 and, upon request, furnish a copy to the inspector. Reposition members that become a part of two assemblies for the second assembly to the dimensions r ecorded for the first assembly. Using steel stamps, match -mark all connecting parts assembled in the shop for the purpose of reaming or drilling of holes for field connections or for fit -up of field welded connections before disassembly. Punch mark bearing centerlines. 513.25 391 Continuous beam and plate girders, including sections adjacent to hinged, pin connected, sliding, or rocker bearing joints, shall have at least three adjacent segments assembled, and holes reamed or drilled while assembled. Check the fit -up of field welded connections by similar shop assembly. Shop assemble longitudinal or transverse beams and girders that are either framed or connected by diaphragms and floor beams to check fit -up of connections to be field welded, or to ream or drill holes f or bolted connections. Assemble trusses in lengths of at least three abutting panels before drilling or reaming field connections. Include deck plates in the final shop assembly of bridges that involve railroad deck plates, even if welding of these deck pl ates takes place in the field. If the fabricator elects to use numerically controlled drilling or punching, the required assembly shall be performed as specified above. The Office of Materials Management will consider the Contractor’s written request to us e other methods of checking hole alignment and match marking. If the Office of Materials Management does not consider, or disapproves the fabricator’s proposed methods of assembly, perform the work according to 513.19 and 513.24. After fabrication, shop as semble deck expansion devices to check fit -up, straightness, and roadway cross -slope changes. Full width assembly is required with phased construction if expansion devices have interlocking fingers or have mechanical devices that require exact field alignm ent. The fabricator may fabricate part -width deck segments without the required shop assembly under the following conditions:

A.The plans require a phased construction sequence.
B.Shop drawings incorporate a lay down, similar to 513.06, defining vertical offset dimensions from a full length common baseline to all roadway changes including sidewalks, rounding, crowns, and field splice points of the expansion device. Secure parts not completely assembled in the shop with temporary bolts to prevent damage in handling and shipping. In the shop, bolt field splice plates into final position shift the splice plates laterally with respect to their final position so that the ends of the plates are flush with the ends of the member. Without the Office of Materials M anagement’s written acceptance, do not weld or tack -weld to bolted assemblies. Perform authorized welding according to 513.21.

513.25 Nondestructive Testing. Nondestructive testing shall conform to the

AASHTO/AWS Bridge Welding Code , as amended by Suppleme nt 1011 and as specified below. As the Engineer directs, perform ultrasonic or radiographic inspection of field welded repairs in main members for thick scabs, deep kerfs or nicks, and similar gross flaws. Ensure that all examined welds and base metal adja cent to a welded joint conform to the quality requirements specified in 513.21. Submit radiographs, field sketches showing specific locations, lengths and depths of the repair, and two copies of the radiographic or ultrasonic technical reports to the Offic e of Materials Management for acceptance. Receive the Office of Materials Management’s 513.25 392 acceptance before performing construction activities making welds inaccessible for repair. The Contractor or fabricator shall notify the Department at least 48 hours bef ore performing nondestructive testing. Provide this notice even if specific hold or witness point inspections are not required by Supplement 1078. The Office of Materials Management has the final authority to accept welds and will resolve controversies reg arding the interpretation of radiographs, magnetic particle indications, or the acceptability of welds.

A.Radiographic Inspection of Welds. Before inspection, grind welds smooth. Grind web splices only where radiographed, except grind outside fascia surfaces the full length. Inspect the following welds:
1.The full length of all butt welds in flange material of plate girders or rolled beams. One hundred percent of butt welds in back up bars that remain in the structure.
2.The top and bottom one -third of transverse web splices in plate girders or rolled beams and show any cope holes. If an unacceptable weld occurs, radiograph an adjoining 12 -inch (300 mm) length of weld not previously inspected. If unacceptable flaws are found in this adjoining segment , radiograph the remainder of the weld.
3.Butt welds in longitudinal stiffeners attached to tension areas of webs.
4.Twenty -five percent of each longitudinal web splice as selected by the inspector.
5.Full length of field flange cut repairs.
6.Other we lds specified in the Contract or AASHTO/AWS Bridge Welding Code . Use a steel stamp to make the radiograph identification mark shown on the shop drawing layout in the area marked “Weld Identification” of Figures 6.1A through 6.1D of the AASHTO/AWS Bridge Welding Code in a manner to make it visible in the radiograph of the area without resorting to superimposed like markings. Place steel stamped identification marks on flange plates so that after girder assembly the marks are on the inside of flange and out side the area fastened to the web. Identify films of repaired welds by the letter “R”. Do not place steel stamped identification numbers within the weld area. Use superimposed characters to make other required markings. Use film locations or a technique em ployed that will show the top and bottom images of the plate edge. Use films 4 1/2  17 inches (114  432 mm) where practical and a minimum film size of 4 1/2  10 inches (114  254 mm). Supply a technical report for the RT testing similar to Annex III For m III -5 of the AASHTO/AWS Bridge Welding Code , and include the following: Project identification, member piece mark, description of the repairs made, and the qualification level of the technician. 513.25 393 The Department will take ownership of contact films. For ma in material repairs, provide sketches that clearly show specific locations, lengths and depths of field cuts, or damages repaired by field welding.
B.Magnetic Particle Inspection of Welds. Before magnetic particle inspection (MPI), complete welding requir ed to fabricate each beam or girder, correct all visual defects, and clean the weld. If the fabricator’s quality control plan is acceptable to the Department and additional processing does not produce a potential for cracking, the Department may allow the Contractor to perform MPI before complete welding. Inspect welds using the procedure and techniques for the dry powder magnetic -particle examination of welds using the prod or the yoke method according to AWS 6.7.6. The prod test equipment shall have a fun ctioning ammeter. Provide a prod magnetizing current of 100 amperes per inch (25 mm) of prod spacing but not less than 400 amperes. Use only aluminum prods. Inspect at least 1 foot (0.3 m) for every 10 feet (3 m), or fraction thereof, for each size of weld in the following:
1.Flange -to-web welds, including ends of girder after trimming.
2.Moment plate to flange welds.
3.Bearing stiffener welds.
4.Other welds specified in the Contract or AASHTO/AWS Bridge Welding Code .
5.Field weld repairs as directed b y the Engineer. The inspector or the fabrication quality control specialist will select random test sections. Unless waived by the Office of Materials Management, the inspector will observe inspection by C -rated fabricators. Position test sections as neces sary for the inspection and after considering the safety and convenience to the inspecting personnel. If a test section contains unacceptable defects, test 5 -foot (1.5 m) segments on both sides of the test section, or, if less than 5 -foot (1.5 m) segments are on both sides of the test section, test the full length of the weld. Retest welds requiring repair after repairs are complete . MPI will not locate all surface defects of Article 9.21 of the AASHTO/AWS Bridge Welding Code . Unacceptable welds have MPI results that indicate defects exceed the above quality standards. For each unacceptable defect, the fabricator shall record the piece mark, the location of the defect on the member, the defect description, and the proposed repairs.
C.Ultrasonic Testing of Welds. Perform ultrasonic inspection of the following welds:
1.Complete joint penetration flange -to-web, T, or corner joint welds: 25 percent for non -FCM, 25 percent compression or shear FCM, and 100 percent tension FCM. 513.26 394 2. Complete penetration butt welds: 100 percent tension FCM and 25 percen t compression FCM.
3.Other welds: as specified in the Contract or AASHTO/AWS Bridge Welding Code . The fabrication quality control specialist shall provide the Engineer with specified certification, sketches, technician reports, and a letter documenting that the Contractor performed nondestructive testing according to this specification.

513.26 Shipping, Storage, and Erection. Repair or replace, at the discretion of

the Office of Materials Management, members damaged by improper handling, storing, or erec tion. During transportation, place adequate blocking between members to prevent movement and facilitate unloading. Unless reinforced by additional plates, angles, or other material bolted in place, do not use field connection holes for tie -down. Band toget her bearing components. Place material stored in the fabricating shop or in the field on skids or blocks to prevent the metal from contacting the ground. Place and shore girders and beams in an upright position for shipping, and field and shop storage. Field splice plates shall be bolted with temporary bolts, which shall be removed and replaced, when field splice plated are placed in their final position or shifted laterally with respect to their final position. Keep material clean and properly drained. Install bearing devices and anchorages according to Item 516. Thoroughly clean bearing surfaces and surfaces to be in permanent contact before the members are assembled in the field. Before erecting structural steel, completely bolt up field splices and conne ctions that started before steel erection. During erection, the Engineer will allow drifting to draw the parts into position, but do not enlarge the holes or distort the metal. Install drift pins and bolts according to 513.20. Fill at least three -fourths of the holes with completely tightened bolts in splices and connections subject to construction loads during erection. Complete permanent fastening of steel truss tension chord members before removing falsework. Permanently fasten compression chord members after the span is released sufficiently from the falsework to bring the compression chord joints into full bearing. Properly regulate and maintain elevations of panel points and ends of floor beams until the falsework is removed. Do not enlarge the holes of splices and connections between segments or elements of main members without approval by the Office of Materials Management. Adjust structures to the correct alignment and to the marked bearing centerlines before beginning permanent fastening. Do not pe rmanently fasten cross frames and lateral bracing in continuous beam or girder spans until completing main connections in adjacent spans; however, install sufficient bracing to maintain structural stability. For erection bolts used to fasten cross frames, use not less than 5/8-inch (16 mm) diameter, and fully tighten bolts according to 513.20. 513.27 395 Erect end cross frames and end dams in a manner that ensures bearing parts remain in bearing contact. Permanently fasten all intermediate cross frames before deck pla cement begins. The webs of primary members shall be plumb before deck placement begins.

513.27 Shop Coating. For steel surfaces specified to be coated according to

Item 514, apply a prime coat in the shop.

513.28 Cleaning ASTM A 709/A 709M, Grade 50W (345W ) Steel. Before the

new steel is shipped, solvent clean, where necessary, all surfaces of ASTM A 709/A 709M, and Grade 50W (345W) steel that are to be left unpainted to remove all traces of asphalt cement, oil, grease, diesel fuel deposits, chalk, paint ma rks, and other soluble contaminants according to SSPC -SP 1 Solvent Cleaning. QCP #1 and QCP #2 shall apply according to Item 514. Shop blast unpainted Grade 50W material to SSPC -SP 6, commercial blast. QCP #3 shall apply according to Item 514. After placin g superstructure concrete, clean, where necessary, the exterior surface and bottom flanges of all fascia beams or girders that are to be left unpainted to remove all traces of asphalt cement, oil, grease, diesel fuel or petroleum deposits, concrete, and ot her contaminants. Do not use acid for cleaning.

513.29 Method of Measurement. The Department will measure Structural

Steel Members on a lump sum basis or by the number of pounds (kilograms). If payment is per pound (kilograms), submit weight computations t o the Office of Materials Management based upon the accepted shop drawings. Deduct waste material, removed by burning, cutting, machining, holes, etc., but include groove weld bevels. Include the weight of all permanent fasteners, shop fillet welds, other metals and preformed bearing pads. Exclude the weight of paint or galvanized coatings. Exclude thickness or weight of members exceeding the plan requirements (due to overweight or other cause), unless authorized by the Department. As an option, measure and record the weight of structural members before painting in the presence of the inspector. Use the following unit weights for computations. lb/ft³ (kg/m ³) Steel, cast steel, and deposited weld metal 490 (7850) Cast iron 450 (7210) Phosphor or leaded bronze 550 (8810) Lead 710 (11370) Preformed bearing pads 710 (11370) The Department will measure Welded Stud Shear Connectors by the number of each installed and accepted.

513.30 Basis of Payment. If the fabricator’s proposed methods of assembly

with numerically controlled drilling or punching fail to produce specified results and the Office of Materials Management directs the Contractor to perform work, as according to 513.19 and 513.24, the Department will not pay for this work. 513.30 396 For steel surfaces specified to be coated according to Item 514, the cost of applying a prime coat in the shop is incidental to the bid for structural steel. The Department will not pay for repairing or replacing members damaged by improper handling, storing, transportation, or erection. The Department will pay for the accepted quantities at the contract prices as follows: Item Unit Description 513 Lump Sum Structural Steel Members, Level UF 513 Lump Sum Structural Steel Members, Level 1 513 Lump Sum Structural Steel Members, Level 2 513 Lump Sum Structural Steel Members, Level 3 513 Lump Sum Structural Steel Members, Level 4 513 Lump Sum Structural Steel Members, Level 5 513 Lump Sum Structural Steel Members, Level 6 513 Pound (Kilogram) Structural Steel Members, Level UF 513 Pound (Kilogram) Structural Steel Members, Level 1 513 Pound (Kilogram) Structural Steel Members, Level 2 513 Pound (Kilogram) Structural Steel Members, Level 3 513 Pound (Kilogram) Structural Steel Members, Level 4 513 Pound (Kilogram) Structural Steel M embers, Level 5 513 Pound (Kilogram) Structural Steel Members, Level 6 513 Each Welded Stud Shear Connectors ITEM 514 PAINTING OF STRUCTURAL STEEL

514.01 Description

514.02 Materials

514.03 Superintendent

514.04 Quality Control

514.05 Testing Equipment

514.06 Work Limitations

514.07 Protection of Persons and Property

514.08 Pollution Control

514.09 Safety Requirements and Precautions

514.10 Inspection Access

514.11 Job Site Visual Standards

514.12 Quality Control Point Photographic Verification and

Docum entation

514.13 Surface Preparation

514.14 Washing Shop Primer

514.15 Handling

514.16 Mixing and Thinning

514.17 Coating Application

514.18 Removing Fins, Tears, or Slivers

514.19 Caulking

514.20 Dry Film Thickness 514.01

397 514.21 Final Inspection

514.22 Repair Pro cedures

514.23 Method of Measurement

514.24 Basis of Payment

514.01 Description . This work consists of cleaning and painting all steel

surfaces.

514.02 Materials. On existing steel, apply a three -coat paint system consisting

of an organic zinc prime coat, an epoxy intermediate coat, and a urethane finish coat. The coating system shall conform to 708.02 . On new steel, apply a three -coat pain t system consisting of an inorganic zinc prime coat, an epoxy intermediate coat, and a urethane finish coat. The prime coat shall conform to 708.01 , and the intermediate and finish coats shall conform to

708.02 Supply the intermediate and finish coats from the same manufactu rer. The

Contractor is responsible for ensuring the compatibility of the intermediate and finish coats with the prime coat. For caulking, use a single pack moisture cured polyurethane based material, which will not shrink , or sag capable of filling voids up to 1 inch (25 mm) wide . Only material that is listed on the OMM Qualified Product List website may be used.

514.03 Superintendent . In addition to the requirements of 105.06 , the

Superintendent must successfully complete a Bridge Painting pre -qualification course and training offered by the Department. The course must have been completed within the past four years and an individual course certificate must have been received by the Superintendent. Present certificate to the Engineer prior to commencing work. No work is permitted unless the Superintendent provides a valid course certificate.

514.04 Quality Control. Quality control consists of designating quality control

specialists to control the quality of work in each phase established by Quality Control Poi nts (QCPs). Control quality by inspection, tests, and cooperation with inspection and testing performed by the Engineer and inspector.

A.Quality Control Specialist . Identify the individuals dedicated to performing duties as the painting quality control sp ecialists before starting work in the field. Provide a quality control specialist for each structure, but one quality control specialist must be provided for every three structures for which work is progressing concurrently on this contract. Each quality control specialist must be , at a minimum, either a NACE (National Association of Corrosion Engineers) coating inspector Level 1 certified, or a SSPC (The Society for Protective Coatings ) protective coating specialist , or a SSPC protective c oating inspector Level 1, or a SSPC bridge coating inspector Level 1,or formally trained or retrained by , at a minimum, a NACE coating inspector Level 1 certified , or a SSPC protective coating specialist , or a SSPC protective coatings inspector Level 1, or a SSPC bridge coating inspector Level 1 . The training shall be adequate to ensure that the quality control specialist is able to use all the testing equipment and understands the requirements of this specification. Provide a copy of the NACE or SSPC certification or a copy of the trainer’s NACE or SSPC 514.04 398 certification and a letter or certificate signed and dated by the trainer to the Office of Construction Administration. Ensure that the NACE or SSPC certification is current or retrain the quality control specialist every five years in accordance with the above requirements . The quality control specialist must successfully complete a Bridge Painting prequalification course offered by the Department. The training course must have been com pleted within the past four years and an individual course certificate must have been received by the quality control specialist. Select only a quality control specialist who is approved by the Department. The Office of Construction Administration will pub lish a list of approved Quality Control Specialists. Present all required certificates, letters of certification, and valid identification to the Engineer prior to commencing work. The quality control specialist will be immediately removed from the ir dutie s as the quality control specialist and disqualified from future duties as the quality control specialist if any quality control failure occurs. A quality control failure is defined as any of the following:
1.The dry film thickness has been approved by th e quality control specialist and it is later found that over 20 percent of the spot measurements of any one member of a structure, such as a cross frame, web, flange, stiffener, or other parts of the structure are either under the minimum or over the maxim um spot thickness.
2.The dry film thickness has been approved by the quality control specialist and it is later found that the thicknesses of any area of a structure as described in 514.20 are either under the minimum or over the maximum specification thi ckness.
3.Two separate occurrences when the surface preparation has been approved by the quality control specialist of any one member type, such as the cross frames, webs, flanges, stiffeners, or other parts of the structure and it is later found that th e surfaces of those members were either not properly profiled or not properly cleaned as required by the Contract Documents. Occurrences are determined per structure.
4.Two separate occurrences of the quality control specialist performing production dutie s not allowed by the Contract Documents. Occurrences are determined per structure.
5.Two separate occurrences when the quality control specialist fails to perform any one of the duties assigned to the quality control specialist in the Contract Documents. Occurrences are determined per structure. Suspend work if the quality control specialist is not available or has been removed. The Engineer or Inspector will immediately provide written notification to the Office of Construction Administration of any quality control failure identified above. Resum e work when a quality control specialist, qualified and approved as provided in 514.04, is available. 514.04 399 For work in the fabrication shop, e ach fabricator shall identify one or more full-time individuals who shall perform the duties of the painting quality control specialist. The quality control specialist may not be used to perform production duties including supervision, blasting, painting, waste disposal, mixing, operating or repairing equipment, or other tasks not associated with duties of the quality control specialist while the Contractor is performing work toward the completion of a Quality Control Point. Ensure that each quality control specialist is trained and equipped with Safety Data Sheets ( SDS), product data sheets, tools, and equipment necessary to provide quality control on all aspects of the work. Each quality control specialist shall have a thorough understanding o f the plans for the work, including any pertinent addenda, change order, or other contract documents, and these Specifications. Duties each quality control specialist shall perform include:
1.Inspect equipment and abrasive at specified intervals.
2.Appro ve the work and provide documentation that the work has been approved immediately before each QCP.
3.Inspect the work with the Engineer or Inspector at each QCP.
4.Verify the Contractor or fabricator performed work according to the Contract Documents.
5.Cooperate with the inspection and testing performed by the Engineer and inspector.
6.Document test results and compare test results with the Engineer’s and inspector’s test results.
7.Notify Superintendent of nonconforming work.
8.Stop work when test e quipment is not available and when necessary to ensure the work is performed according to the Contract. The fabricator’s quality control specialists shall provide the Engineer with a letter that includes specified information or check point data documentin g acceptance of the work and consisting of the following:
1.Checks on the abrasive to ensure that it has not been contaminated with oil.
2.The profile of the blasted surface.
3.The air and steel temperature and dew point before blast cleaning and painti ng and at 4 -hour intervals during the blasting and painting operation.
4.Readings of the actual dry film thickness.
5.The lot and stock number of the paint and the date of manufacture.
6.Documentation that the paint mixer is functioning properly, that e ach spray operator has demonstrated the ability to paint, and that all spray equipment is used according to the manufacturer’s recommendation. 514.04 400 B. Quality Control Points (QCP) . QCPs are points in time when one phase of the work is complete and approved by the quality control specialist and ready for inspection by the Engineer or the inspector before commencing the next phase of the work. At a QCP, the quality control specialist s hall provide quality control tests bearing his signature to the Engineer or Inspector. The Contractor or fabricator shall provide the Engineer and inspectors access to inspect all affected surfaces. If inspection identifies a deficiency, correct the defici ency according to the Contract Documents before starting the next phase of work. Discovery of defective work or material after a Quality Control Point is past or failure of the final product before final acceptance, shall not, in any way, prevent the Depar tment from rejecting the final product or obligate the Department to final acceptance. Final acceptance will be determined according to 514.21, Final Inspection. Quality Control Points Purpose New Steel Existing Steel
1.Solvent Cleaning Remove asphalt c ement, oil, grease, etc. Yes Yes
2.Grinding Flange Edges Remove sharp corners Yes Yes
3.Abrasive Blasting Blast surfaces to receive paint Yes Yes
4.Containment/ Waste Disposal Contain, collect, & dispose of abrasive blasting debris No Yes
5.Prime Coat Application Check surface cleanliness, apply prime coat, check coating thickness Yes Yes
6.Remove Fins, Tears, & Slivers Remove surface defects and slivers Yes Yes
7.Washing of Shop Primer Remove all water soluble materials (salt, dirt, etc.) Yes No
8.Intermediate Coat Application Check surface cleanliness, apply intermediate coat, check coating thickness Yes Yes
9.Caulking Caulk areas not sealed by the intermediate coat Yes Yes
10.Finish Coat Application Check surface cleanliness, apply intermediate coat, check coating thickness Yes Yes
11.Final Review Acceptance and check total system thickness Yes Yes 514.05 401 Provide signed documentation of inspection, testing, conditions and material information to the Engineer on the following ODOT forms, or forms with the equivalent information. QCS Inspection Documentation Sign Off for QCP’s CA-S-7 QCP#1 Solvent Cleaning CA-S-12 QCP#2 Grinding Flange Edges CA-S-12 QCP#3 Abrasive Blasting CA-S-13 QCP#3 QCS & Visual Standards Information for Abrasive Blasting Test Section CA-S-11 QCP#4 Disposal of Hazardous/Non -Hazardous Waste CA-S-14 QCP#5 Prime Coat Application CA-S-15 QCP#5 Dry Film Thickness Readings for Prime Coats CA-S-2 QCP#6 Grinding Fins, Tears and Slivers CA-S-16 QCP#8 Dry Film Thickness Readings for Intermediate Coats CA-S-2 QCP#9 Caulking CA-S-16 QCP#8 Intermediate Coat Application CA-S-17 QCP#10 Finish Coat Application CA-S-17 QCP#10 Dry Film Thickness Readings for Finish Coats CA-S-2

514.05 Testing Equipment. For the project duration, provide the Engineer or

inspectors with the test equipment listed below for the type of work at each work site with ongoing work. With the exception of the recording thermometer, the fabricator shall provide its quality control specialist s with the test equipment listed below. The Contractor and fabricator shall maintain all testing equipment in good working order, and provide documentation or certification of calibration from the manufacturer. If the Contractor or Fabricator and the Engin eer’s inspector are using different test equipment, the Contractor or Fabricator and the Engineer’s inspector will perform side -by-side testing and compare results. If the difference between the Department’s and Contractor’s or Fabricator’s tests results, such as blast profile, dry film thickness, temperature, dew point and relative humidity, are greater than 1%, the Contractor or Fabricator and the Engineer will determine the reason for the differences and make necessary adjustments .

A.Provide a digital camera with the following features:
1.5.0 Megapixel or greate r resolution.
2.Minimum 3 × Optical zoom lens capability with automatic focus.
3.Minimum 512M B Memory capability.
4.Built -in flash.
B.One Spring micrometer and extra -coarse replica tape or comparable electronic surface profile gauge for the measurement of abrasive blast profil e depth within ±0.2 mils on the project at all times . 514.06 402 C. One SSPC -PA2 Type 2 (electronic) non -destructive coating thickness gage , with a set of calibration thickness foils, (shims), and two sets of National Institute of Standards & Technology calibration p lates. The first set of calibration plates shall be 1.5 to 8 mils (38 to 200 μm), Model No. 1362b, and the second set shall be 10 to 25 mils (250 to 625 μm), Model No. 1363b. Other certified coating thickness standard plates for ferrous substrates must be approved for use by the Office of Construction Administration.
D.One Sling Psychrometer including Psychrometric tables, (or comparable electronic or digital equipment for the measurement of dew point, accurate within 2 °F (1 °C) and within one percent relative humidity).
E.Two steel surface thermometers accurate within 2 °F (1 °C).
F.Flashlight 2 -D cell.
G.SSPC Visual Standard for Abrasive Blast Cleaned Steel (SSPC -VIS 1).
H.One recording thermometer capable of recording the date, time, and tempe rature over a period of at least 12 hours.

514.06 Work Limitations. Apply the prime coat to new structural steel inside

permanent buildings at the fabricator’s facility. If inside permanent buildings, the fabricator may perform year -round abrasive blasting and painting. Perform abrasive blasting and painting in the field from April 1 to October 31. The Department will not issue a time extension due to adverse weather during the month of April. The plans or other Contract Documents may require additional wor k limitations for specific bridges or projects.

A.Temperature . Do not apply Inorganic Zinc Primer if the steel, air, and paint temperature is below 40 ºF (4 ºC). Do not apply Organic Zinc Primer, Epoxy Intermediate, or Urethane Finish Coats if the steel, air, and paint temperature is below 50 ºF (10 ºC). Follow the paint manufacturers printed instructions for the minimum times to handle, recoat and cure the individual coats for specified conditions and thicknesses. Monitor and document that the temperature s listed below are maintained for minimum time frames listed below, after application of each coat, by using the recording thermometer. The Contractor may use a heated enclosure or building. Supply heat continuously and uniformly to maintain the required m inimum temperature within the enclosure or building. Minimum Times to maintain temp. per coating. 50 F (10 C) 60 F (16 C) 70 F (21 C) Primer (Organic Zinc) 4 hrs 3 hrs 2 hrs Intermediate (Epoxy) 6 hrs 5 hrs 4 hrs Finish (Urethane) 8 hrs 6 hrs 4 hrs If combustion type heating units are used, vent the units away from the enclosure or building and do not allow exhaust fumes to enter the enclosure or building. Do not use open combustion in the enclosure or building. The fabricator may use radiant heat when painting new structural steel inside permanent shop buildings. Locate radiant heaters at least 10 feet (3 m) above all 514.07 403 surfaces to be painted. Vent exhaust fumes to prevent fumes from contacting surfaces to be paint ed.
B.Moisture. Do not apply paint:
1.If the steel surface temperature is less than 5 °F (3 °C) above the dew point.
2.If the steel surface is wet, damp, frosted, or ice -coated.
3.If the relative humidity is greater than 85 percent.
4.During periods o f rain, fog, or mist unless the above moisture criteria is met. If steel was abrasive blasted when the temperature of the steel was less than 5 °F (3 °C) above the dew point, reblast the steel when the steel temperature is at least 5 °F (3 °C) above the d ew point.

514.07 Protection of Persons and Property. Collect, remove, and dispose of

all rubbish, buckets, rags, or other discarded materials and leave the job site in a clean condition. Except for deck bottoms and backwalls which have not been sealed or a re not to have a sealer applied, protect all portions of the structure, that are not to be painted from damage or disfigurement by splashes, spatters, and smirches of paint. If the Contractor causes any damage or injury to public or private property, the Contractor shall restore the property, to a condition similar or equal to the condition existing before the damage or injury.

514.08 Pollution Control. Comply with pollution control laws, rules, or

regulations of Federal, State, or local agencies and requir ements of this specification.

514.09 Safety Requirements and Precautions. Comply with the applicable

safety requirements of the Ohio Industrial Commission and OSHA . Provide Safety Data Sheets ( SDS) at the preconstruction meeting for all paints, thinners, and abrasives used on this project. Do not b egin work until submitting the SDS to the Engineer.

514.10 Inspection Access and L ighting . In addition to the requirements of

105.10 , furnish, erect, and move scaffolding and other appropriate equipment to

allow the insp ector and the Engineer the opportunity to closely observe all affected surfaces during all phases of the work and for at least 10 workdays after completely painting each structure to allow for the Final Inspection according to 514.21 . Provide artificial lighting as necessary to supplement natural light with a minimum of 30 foot candles (325 LUX) at the surface of the steel for inspection, cl eaning, and painting. Prevent glare that interferes with traffic, workers and inspection. Submit to the Engineer for information, complete details of the inspection access that complies with the applicable safety requirements of The Ohio Industrial Commiss ion and OSHA. The details shall be reviewed, signed, stamped and dated by an Ohio registered Professional Engineer certifying that they meet these requirements. Maintain the in -place inspection access equipment employed during original painting activities or provide alternate inspection equipment such as platform lifts, bucket trucks, snooper trucks, or equivalent as approved by the 514.10 404 Engineer. If scaffolding, or any hanger attached to the scaffolding, is supported by horizontal wire ropes, or if scaffolding is directly under the surface to be painted, comply with the following requirements:

A.If scaffolding is suspended 43 inches (1092 mm) or more below the surface to be painted, place two guardrails on all sides of the scaffolding. Place one guardrail at 42 inches (1067 mm) above the scaffolding and the other guardrail at 20 inches (508 mm) above the scaffolding.
B.If scaffolding is suspended at least 21 inches (533 mm) but less than 43 inches (1092 mm) below the surface to be painted, place one guard rail on all sides of the scaffolding at 20 inches (508 mm) above the scaffolding.
C.If 514.10.A and 514.10.B do not apply, place two guardrails on all sides of scaffolding. Place one guardrail at 42 inches (1067 mm) above the scaffolding and the other gua rdrail at 20 inches (508 mm) above scaffolding.
D.Provide scaffolding at least 24 inches (610 mm) wide if guardrail is used and 28 inches (711 mm) wide if guardrail is not used and scaffolding is suspended less than 21 inches (533 mm) below the surface to be painted. If using two or more parallel scaffolding to achieve the proper width, rigidly attach the scaffolding together to prevent differential movement.
E.Construct guardrail as a substantial barrier, securely fastened in place and free from protrudi ng objects such as nails, screws, and bolts. Provide a properly located opening in the guardrail to allow the Engineer and inspector access onto the scaffolding.
F.Construct guardrails and uprights of metal pipe, steel angles, or wood. If using pipe raili ng, provide pipe with a nominal diameter of at least 1 1/2 inches (38 mm). If using steel angle railing, provide 2  2  3/8-inch (50  50  9 mm) steel angles or other metal shapes of equal or greater strength. If using wood railing, provide 2  4 inch ( 50  100 mm) nominal stock. Space uprights no more than 8 feet (2.4 m) on center. If using wood uprights, provide 2  4 inch (50  100 mm) nominal stock.
G.If the surface to be inspected is more than 15 feet (4.57 m) above the ground or water, and the sc affolding is supported from the structure being painted, provide a safety harness (not a safety belt) and lifeline for the Engineer and inspector. The lifeline shall not allow a fall greater than 6 feet (1.8 m). Provide a method to attach the lifeline to t he structure that is independent of the scaffolding, cables, and brackets supporting the scaffolding.
H.If scaffolding is more than 2.5 feet (762 mm) above the ground, provide an access ladder and equipment to attach the ladder onto the scaffolding capabl e of supporting 250 pounds (113 kg) with a safety factor of at least four. uniformly space rungs, steps, cleats, and treads no more than 12 inches (305 mm) on center. Extend at least one side rail at least 36 inches (914 mm) above the landing near the top of the ladder.
I.If the distance from the ladder to the access point on the scaffolding exceeds 12 inches (305 mm), provide an additional landing that is capable of supporting a minimum of 1000 pounds (454 kg) and at least 24 inches (610 mm) wide and 24 inches (610 mm) long. Size and shape the landing so that the distance from the 514.11 405 landing to the point where the scaffolding is accessed does not exceed 12 inches (305 mm). Firmly attach the landing to the ladder; however, do not use the ladder to support the landing.
J.In addition to the scaffolding requirements above, comply with all Federal, State, and local laws, ordinances, regulations, orders, and decrees.
K.Furnish all necessary traffic control to allow inspection during and after all phases of the project.

514.11 Job Site Visual Standards. Before starting abrasive blasting, establish

job site visual standards by preparing a test section, subsequent test sections, and by using photographs of approved test sections. Use job site visual standards and S SPC- VIS 1 standard for blasting. The Contractor or fabricator shall prepare an approximately 20 to 30 square foot (2 to 3 m ²) test section from a representative area on the first structure to be painted. After the Engineer or Inspector and the Contractor or fabricator agree the test area was blast cleaned to the requirements of the Contract Documents, photograph the test section and check the steel surface for the proper profile. After the Engineer or Inspector approves the test section and the job site visual standards are documented by photographs and replica tape, the Contractor or fabricator may start abrasive blasting. The quality control specialists and Engineer or Inspector will use the job site visual standards (photographs), the Plan, Specification and requirements to determine acceptance of blast cleaning procedures. In all cases of dispute, the SSPC -VIS 1 standard shall govern. If the Contractor, Engineer, Inspector, or fabricator believe the initial test section does not establish the proper visu al standard for a different structure another test section on the different structure may be performed.

514.12 Quality Control Point Photographic Verification and

Documentation. The Engineer or Inspector will take a sufficient number of photographs to document the condition of the work at Quality Control Points 3, 4 and 11.

514.13 Surface Preparation.

A.Solvent Cleaning (QCP #1) . Solvent clean by methods described in SSPC - SP 1, areas containing oil, grease, asphalt cement, diesel fuel deposits, other petroleum products and contaminants.
B.Grinding Flange Edges (QCP #2) . Before abrasive blasting, round all exposed flange edges of all beams and girders to a radius of 1/8 ±1/16 inch (3 ±1.5 mm). This work has no weather and temperature restrictions. For shop painted steel, ground the sides of thermally cut material 1 ½ inch (40 mm) or thicker to remove the heat effected zone, as necessary, to achieve the specified surface cleaning.
C.Abrasive Blasting (QCP #3) . Do not abrasive blast areas that contain as phalt cement, oil, grease, or diesel fuel deposits. Before abrasive blasting, completely remove all dirt, sand, bird nests, bird droppings, and other debris from the scuppers, bulb angles, and pier and abutment seats. Abrasive blast all steel to be painted according to SSPC -SP 10 and as shown on the pictorial surface preparation standards for painting steel surfaces shown in SSPC -VIS 1. Maintain steel in a blast cleaned condition until it has received a prime 514.13 406 coat of paint. The Contractor may commercial bla st clean the back side of end cross frame assemblies that are 3 inches (75 mm) or closer to backwalls according to SSPC -SP 6. Cover and protect galvanized and metalized steel (including corrugated steel bridge flooring), adjacent concrete already or specif ied to be coated or sealed, and other surfaces not intended to be painted, from damage caused by blasting and painting operations. Repair adjacent coatings damaged during the blasting operation. Backwalls and bottoms of decks not sealed nor specified to be sealed do not need to be covered and protected. For field blasting use a recyclable steel grit, or a recyclable natural mineral, low dusting abrasive. Do not use silica sands, mineral slags, and other types of non - metallic abrasives that contain more than 0.5 percent free silica, by weight, have a chlorides salts content more than 25 ppm, and contain any organic material. For shop blasting use an abrasive that produces an angular profile. All abrasives shall provide a profile from 1.5 to 3.5 mils (40 to 90 μm) as determined by replica tape according to ASTM D 4417, Method C. Adjust the abrasive size, blast hose nozzle pressure or other means in order to provide the 1.5 to 3.5 mil profile. Clean the abrasive of paint chips, rust, mill scale, and other foreig n material after each use and before each reuse. Use equipment specifically designed for cleaning the abrasive. Check abrasives used at the job site or fabrication shop for oil contamination at the beginning of each shift and at 4 -hour intervals. Also che ck each load of abrasive delivered to the job site or fabrication shop for oil contamination before use. Check for oil by placing a small sample of abrasives and tap water into a jar. Reject the abrasive if an oil film is detected on the water surface. To ensure that the compressed air is not contaminated, the quality control specialists shall blow air from the nozzle for 30 seconds onto a white cloth or blotter held in a rigid frame. If the cloth or blotter retains oil or other contaminants, suspend abrasi ve blasting until retests verify the problem was corrected. Perform this test at the start of each shift and at 4 -hour intervals. The Contractor may simultaneously abrasive blast and paint the same bridge provided the abrasive blasting debris and dust does not contact freshly painted surfaces and does not contaminate paint during the curing period. For shop blasting, the fabricator may simultaneously abrasive blast and paint if the two operations are separated by distance or containment that prevents paint contamination. For surface preparation of new structural steel in the fabricator’s shop, the quality control specialist shall take replica tape readings as follows:
1.For an automated blasting process, test the greater of 20 percent of the main members or one member per shift. These tests shall consist of taking five random readings per member.
2.For a manual blasting process, test each main member. The test of a main member consists of taking five readings at random locations.
3.For both an automated an d manual blasting process, test 15 percent of all secondary members. The test of a secondary member consists of taking one random reading. 514.13 407 Remove abrasives and residue from all surfaces to be painted. Keep all structural steel that was blast cleaned in the field or the fabricator’s shop dust free. Apply a prime coat to steel that was blast cleaned in the field within 12 hours of the beginning of the abrasive blasting operation. Apply a prime coat to structural steel that was blast cleaned in the fabricator’ s shop within 24 hours of the beginning of the abrasive blasting operation. If a prime coat is not applied within the times stated above, reblast the steel before applying the prime coat. Remove all dust or abrasives from adjacent work and from the finish coat. Provide the Engineer and Inspector with field wash facilities and an adequate supply of running potable water, soap, and towels for washing face and hands during the surface preparation operation. Properly contain, test, and dispose of the wastewater . Locate a wash facility at each bridge site and in an area that will not be contaminated by the blasting debris.
D.Containment/Waste Disposal (QCP #4) . Waste material generated by abrasive blasting operations in the field is a solid waste and may be a ha zardous waste. Contain, collect, store, evaluate, and properly dispose of the waste material. Comply with all Federal, State, and local environmental protection laws, regulations, and ordinances including, but not limited to, air quality, waste containment , and waste removal. The Contractor is advised that various governmental bodies are involved with solid waste and hazardous waste disposal and the Contractor is responsible for complying with laws enforced by the various governmental bodies. To prevent con tamination of the pavement or soil, park all equipment on ground covers free of cuts, tears, and holes. Clean equipment of spent abrasives or debris before bringing equipment to the project, moving equipment from one bridge site to another, and removing eq uipment from the project. Store debris cleaned from equipment with the debris from the structure that generated the debris. Erect an enclosure to completely surround (around, under and over the top on truss type bridges) the blasting operations. The Contra ctor may use the ground as the bottom of the enclosure if the ground is completely covered with plastic or tarps. Construct the enclosure of flexible materials such as tarpaulins (specifically designed for blasting containments), or construct the enclosure of rigid materials such as plywood. Maintain all materials free of tears, cuts, and holes. Overlap all seams a minimum of 6 inches (150 mm) and fasten the seams together at 12 -inch (300 mm) centers or in a manner that ensures a seal that does not allow op enings between the edges of the containment material. Extend the vertical sides of the enclosure completely up to the bottom of the deck on a steel beam bridge and use bulkheads between beams to enclose the blasting area. Collect all debris from blasting o perations, equipment, or filters, and all debris that fell to the ground. Store the debris in steel containers /drums with lids that are locked at the end of each workday. Store the debris in these locked drums while in the storage location and when hauled from the storage location to the disposal site. The storage location shall be at the bridge site unless, the Engineer and Contractor agree on an alternate storage location. Secure the storage location by surroundi ng the site with a 5 foot (1.5 m) high dumpster or a 5 foot (1.5 m) high chain link fence 514.13 408 fabric supported by traffic sign drive posts 10 feet (3 m) apart. Drive the traffic signposts into the ground at least 2 feet (0.6 m) deep. Secure the dumpster or fen cing with padlocks at the end of each day. The location of centralized cleaning stations for recyclable steel shall also be agreed by the Engineer and the Contractor. Test and evaluate the debris for disposal. Obtain the services of a testing laboratory to obtain directly from the project site and evaluate a composite representative sample of the abrasive blasting debris for each bridge site. The person taking the sample must be an employee of the testing laboratory . Take composite sample in the presence of the Engineer or Inspector, comply with the requirements of U.S. EPA Publication SW 846 and take individual samples from all containers that are on the site at the time of the sampling. Blend individual samples of equal size together to comprise one composite sample. Take one individual sample from each drum and four randomly spaced individual samples from each container other than drums. Take individual samples and place into clean glass or plastic containers. Prepare a chain of custody record (Chain of Custody) for all composite samples. The Chain of Custody must include the name of the person taking the sample, the name of the testing laboratory for which the person works, the date and time the sam ple was taken, the bridge sampled, the Township and Municipality where the bridge is located, and the signatures and dates of all persons in possession of the sample in the Chain of Custody. Sample the abrasive blasting debris within the first week of pro duction blasting at each bridge. Cease all blasting and painting operations on the bridge from which waste was generated, if sampling is not performed within the first week of production blasting. Test composite samples for lead, chromium, cadmium and ars enic according to the U.S. EPA Publication SW 846 Method 1311 (TCLP). Provide the Chain of Custody and test results to the District Regulated Waste Engineer (DRWE) immediately after the test results are available. If the DRWE determines the blasting debris is hazardous, as defined below, provide the Engineer with the names of the hauler and treatment facility. Perform all sampling and testing required by the hauler, treatment facility, or disposal facility. The existing paint removed from bridges may contai n lead, chromium, cadmium or arsenic. The Contractor is responsible for taking the proper safety precautions to ensure workers in this environment are properly protected.
1.Hazardous Waste. The blasting debris is hazardous if lead, chromium, cadmium or ar senic exceed any of the regulatory concentration limits shown below: SW 846 Analyte Regulatory Concentration Limit Lead 5.0 mg/l Chromium 5.0 mg/l Arsenic 5.0 mg/l Cadmium 1.0 mg/l 521.14 409 Label all the containers of hazardous blasting debris “HAZARDOUS”. Post hazardous waste warning signs at obvious locations on the fenced enclosure. The Office of Construction Administration will obtain a generator number assigned to the State. After the Office of Construction Administration obtains the generator number, a rrange for the hauling, treating, and disposing of the hazardous waste. Use a firm licensed by EPA to haul and dispose of the hazardous waste. This firm is also responsible for providing the completed Uniform Hazardous Waste Manifest (EPA Form 8700 -22, or current version). In every case, properly dispose of all hazardous waste within 60 days after it is generated. If hazardous waste is not properly disposed of within 60 days, the Department will consider the Contactor in breach of its Contract and the Depar tment will take the following actions:
a.Immediately suspend all abrasive blasting and painting of structural steel on the Project until hazardous waste is properly disposed.
b.Cease processing all pay estimates.
c.Forward a breach of contract notification to the Contractor’s Surety. The Contractor is responsible for fines or liens assessed by any governmental agency that has jurisdiction over the disposal of this hazardous waste material. Decontaminate or dispose of all collection and containm ent equipment according to EPA guidelines. The Contractor shall inform the Department when all hazardous waste has been removed from the Project so the EPA Site ID Number (Hazardous Waste Generator Number) can be deactivated.
2.Non-Hazardous Solid Waste. For all waste that is determined to be a Non-Hazardous Solid Waste by the DRWE, the Contractor is required to:
a.Before disposing of any material, provide the Engineer with documentation that the disposal facility is licensed by the EPA to ac cept non - hazardous solid waste.
b.Haul and dispose of the waste to the documented, non -hazardous solid waste facility.
c.Obtain from the disposal facility and provide the Engineer with a receipt that documents disposal of waste material at the licensed disposal facil ity.
d.Properly dispose of all waste within 60 days after it is generated.

514.14 Washing Shop Primer (QCP #7) . Wash shop primed structural steel

after it is erected and the concrete deck is placed and within 30 days of applying the intermediate coat. Wash the steel with potable water. Use equipment capable of delivering the water at a nozzle pressure of at least 1000 pounds per square inch (7 MPa) and at a rate of not less than 4 gallons (15 L) per minute. The Contractor shall provide the Engineer 514.15 410 with eq uipment specifications that verify both the delivery pressure and rate. Provide gauges on the equipment to verify the pressure during operation. Hold the nozzle a maximum of 12 inches (300 mm) from the surface being washed. The surface is clean when clear rinse water runs off the structure. After rinsing the surface, inspect for remaining dirt and rewash dirty areas until clean.

514.15 Handling . Deliver all paint and thinner in original unopened containers

with labels intact. The Engineer or Inspector will accept containers with minor damage provided the container is not punctured. Thinner containers shall be a maximum of 5 gallons (19 L). Before use, provide the Engineer with shipping invoices for all painting materials used on the Project. Supply container s of paint and thinner with labels clearly marked by the manufacturer to show paint identification, component, color, lot number, stock number, date of manufacture, and information and warnings as may be required by Federal and State laws. Store paint at t he temperature recommended by the manufacturer and in a storage facility that prevents theft. Provide thermometers capable of monitoring the maximum high and low temperatures inside the storage facility. Before opening paint or thinner containers, check th e labels to ensure the proper container is opened and the paint has not been stored beyond its shelf life. Do not use paint that exceeded its shelf life. Do not open containers of paint and thinner until required for use and then open the oldest paint of e ach kind first. Solvent used for cleaning equipment is exempt from the above requirements. Do not use paint that has livered, gelled, or otherwise deteriorated during storage. Properly dispose of unused paint and paint containers.

514.16 Mixing and Thinnin g. Thoroughly mix all ingredients immediately

before use with a high shear mixer (such as a Jiffy Mixer). Do not mix paint using paddle mixers, paint shakers, or an air stream bubbling under the paint surface. After mixing, carefully examine the paint for uniformity and to ensure that no unmixed pigments remain on the bottom of the container. Before use, strain the paint through strainers that remove skins or undesirable matter but not pigment. Except for primer, mix paint as necessary during application to maintain a uniform composition. Continuously mix primer using an automated agitation system. Do not use hand -held mixers for primer paints. Do not add thinner to the paint without the Engineer’s or Inspector’s approval, and only add thinner if necessary f or proper application as recommended by the manufacturer’s printed instructions. In the Engineer’s or Inspector’s presence, slowly add the amount of thinner recommended and supplied by the manufacturer to the paint during the mixing process. Do not mix oth er additives into the paint. Add catalysts, curing agents, or hardeners that are in separate packages to the base paint only after thoroughly mixing the base paint. With constant agitation, slowly pour the proper volume of catalyst into the required volume of base. Do not pour off liquid that has separated from the pigment before mixing. Use the mixture within the pot life specified by the manufacturer and dispose of unused portions at the end of each workday. 514.17 411 514.17 Coating Application

A.General . Paint al l structural steel, scuppers, expansion joints except top surface, steel railing, exposed steel piling, drain troughs, and other areas as shown on the plans. Paint galvanized or metalized surfaces if shown on the plans. Unless otherwise shown on the plans or specified below, apply paint to provide the specified coating thickness by brush and spray methods. Apply primer and intermediate paint per 708.01 and 708.02 to cover all visible steel surfaces. If gaps or crevices remain between adjacent coated steel surfaces after applying the intermediate coat, caulk according to 514.19 . If brush and spray are not practical to paint places of difficult access, the Contractor may use daubers, small diameter rollers , or sheepskins . Use daubers, small diameter rollers, or sheepskins to paint the following areas:
1.Where cross -frame angles are located within 2 inches (50 mm) of the bottom flange.
2.Where end cross frames are within 6 inches (150 mm) of the backwall.
3.Where there is less than 6 inches (150 mm) between the bottom of the bottom flange and the beam seat.
B.Application Approval. The Engineer or Inspector may inspect the initial applic ation of the prime, intermediate, and final coats. If the Engineer or Inspector discovers defects, adjust the method of application to eliminate the defects then continue applying the coat.
C.Additional Information Pertaining to Shop Applied Paint. Apply a prime coat to all structural steel surfaces by brush or spray methods, including insides of holes, behind stiffener clips and contact surfaces of connection, and splice material that is to be fastened with bolts in the shop or field. Apply a mist coating from 0.5 to 1.5 mils (12.5 to 37.5 μm) on surfaces that are to be imbedded in concrete and on surfaces within 2 inches (50 mm) of field welds other than those attaching intermediate or end cross frames to beams or girders. Apply one coat of primer to pins, pin holes, and contact surfaces of bearing assemblies, except do not paint those containing self -lubricating bronze inserts. Once the prime coat is dry, apply erection marks, using a thinned paint of a type and color that is completely concealed by, and compatible, with the second coat. Do not handle or remove coated structural steel from the shop until the applied paint has met the requirements as specified by the paint manufacturer’s printed instructions. Reduce the thickness of thick films of inorganic zinc primer by screening, sanding, or sweep blasting. If the primer paint cured longer than 24 hours, apply a re-coating of primer paint according to the paint manufacturer’s printed instructions. Abrasive blast and re -apply the primer to the affected are a if “mud cracking” occurs. If “checking” occurs, abrasive blast and reapply the primer or remove the “checking” by screening and evaluate the area by adhesion testing. If specified in the plans,furnish all necessary labor, materials and equipment to apply a three - coat paint system to Item 513 Structural Steel in the shop and touch up areas in the field. 514.17 412 Repair damage to the paint system caused during storage, transportation, erection, bolting, welding, forming, concrete placement, and form removal operat ion, according to C&MS section 514.22. Repair damage to the galvanized coating on the nuts, bolts and washers, in the field due to the bolt tightening or welding operations. Exercise extreme care while handling the steel during erection, and during subsequ ent construction of the bridge. Insulate the steel from the binding chains by softeners and pad all hooks and slings that are used to hoist/erect the steel members. Coating of Bolted Faying Surfaces Treat the surfaces indicated below as described in this s pecification
A.Faying surfaces of all bolted connections.
B.All internal contact surfaces of filler and splice plates.
C.Other surfaces indicated in the plans. Coat the faying surfaces of bolted splices with inorganic zinc primer in the shop. After erec tion is complete, field apply the final coatings of epoxy intermediate coat and urethane protective coats to overlap the shop coatings shown in Figure 1 with the field coats shown in Figure 2. For bolted crossframes, leave a minimum of one inch step back f rom faying surfaces, for epoxy intermediate and an additional one inch for urethane top coat. Remove and reassemble all shop bolted connections and shop bolted cross frames prior to the blasting and coating of the girders or beams. Separately blast and prime the parts, then reassemble and fully tighten the bolts using the turn of the nut method. After bolting is complete, shop apply the epoxy intermediate and urethane protective coats. 514.17 After installation, solvent clean all galvanized nuts, bolts, and washers. Remove any contaminants on the nuts, bolts and washers, prior to the application of paint. Repair any damaged galvanized coating and remove any corrosion prio r to the application of organic zinc by brush. Then apply the epoxy coat and the urethane coats. Erection marks added by the fabricator to highlight or enhance the required steel stamped erection marks must be made without damaging the paint system. Apply Erection marks only after the finish coat is cured and remove at the end of the project. Erection marks may be applied to the faying surfaces. These marks to the inorganic coating need not be removed but must be of a paint supplied by the IZEU system manu facture. Remove any oil, grease, asphalt cement, concrete or other contaminants from the surface of the IZEU system painted structural steel.
D.Surface Cleanliness . All surfaces to be painted shall be free of dust, dirt, grease, oil, moisture, overspray, and other contaminants. If the surface is degraded or contaminated, restore the surface before applying paint. In order to prevent or minimize degradation or contamination of cleaned surfaces in the field, the prime coat of paint shall be applied within 1 2 hours of the beginning of the abrasive blasting operation as required in surface preparation above, for steel which is cleaned and painted in the shop, the prime coat of paint shall be applied within 24 hours of the beginning of the blasting operation. Schedule cleaning and painting when dust or other contaminants will not fall on wet, newly painted surfaces. Protect surfaces that do not receive paint or have already been painted from the effects of cleaning and painting operations. Before applying the ne xt coat, remove overspray and bird droppings with a stiff bristle brush, wire screen, or a water wash with sufficient pressure to remove overspray and bird droppings without damaging the paint. Before applying the next coat, remove 514.17 414 all abrasives and residu e from painted surfaces with a vacuum system equipped with a brush type cleaning tool. Remove all visible abrasives on the finish coat that came from adjacent work.
E.Brush Application . Apply the paint to produce a smooth coat. To ensu re coverage, apply wet stripe coats using brushes, daubers, small diameter rollers or sheepskins to all edges, outside corners, crevices, welds, rivets, bolts, nuts and washers in addition to the spray application of each individual coating Apply stripe coat of organic zinc primer either before or after spray application of primer. Apply stripe coats of intermediate and finish coats before spray application of the respective coats. Apply additional paint as necessary to produce the required coating thicknes s.
F.Spray Application (General) . Apply paint using spray application as follows: Keep spray equipment clean so that dirt, dried paint, solvents, and other foreign materials are not deposited in the paint film. Remove solvent left in the equipment before using the equipment. Apply paint in a uniform layer with overlapping at the edges of the spray pattern. Paint the border of the spray pattern first, followed by painting the interior of the spray pattern. Complete painting a spray pattern before moving to the next spray pattern area. Within a spray pattern area, hold the gun perpendicular to the surface and at a distance that will ensure a wet layer of paint is deposited on the surface. Release the trigger of the gun at the end of each stroke. Each spray op erator shall demonstrate to the Engineer or inspector the ability to apply the paint as specified before the operator sprays paint. If mud cracking occurs, the affected area shall be cleaned to bare metal in accordance with surface preparation above and repainted. Use spray equipment recommended by the paint manufacturer and suitable for use with the specified paint. Provide adequately sized traps or separators to remove oil and condensed water from the air. Periodically drain the traps during operations. To ensure that the traps or separators are working properly, test by blowing air from the spray gun for 30 seconds onto a white cloth or blotter held in a rigid frame. The Engineer or Inspector will verify the test results by inspecting the white cloth or blotter. If the cloth or blotter retains oil, water, or other contaminants, suspend painting until retests verify the problem was corrected. Perform this test at the start of each shift and at 4 -hour intervals. This is not required for an airless sprayer. Do not use spray application unless the operation is totally enclosed as required for abrasive blasting, to prevent overspray damage to the ground, public and private property, vegetation, streams, lakes, and other surfaces not to be painted.
G.Prime, In termediate, and Finish Coat Application (QCP #5, #8, and #10) . Apply paint as a continuous film of uniform thickness, free of all defects such as holidays, pin holes, mud cracking, checking, drips, runs, and sags. The Contractor is responsible for applying the manufacturer’s paint as necessary to satisfy the above requirement. Repaint all thin spots or areas missed before the next coat of paint is applied. 520.18 415 Ensure that the paint manufacturer’s printed instructions for the minimum times to handle, recoat and cure the individual coats for specified conditions and thicknesses are followed for each coat of paint before applying the next coat. Comply with the manufacturer’s written instructions for the time interval between coats and apply the next coat when an ad ditional coat will not cause detrimental film irregularities, such as lifting, wrinkling, or loss of adhesion of the undercoat. Do not exceed the following time intervals. If the prime coat is organic zinc, the maximum time between the prime and intermedia te coats is 30 days. There is no maximum time between the prime and intermediate coats for an inorganic zinc primer. The maximum time interval between intermediate and finish coats is 13 days. These maximum recoat times include adverse weather days and the Engineer will not extend the times. The recoat windows begin with the initial application of each coating type. Additional applications of the same coat do not reset the recoat windows. If the next type of coating is not applied within the t imes stated above, remove the coatings and re -blast the steel according to SSPC -SP 10. If requested by the engineer, perform one or both of the following test to determine the hardness and or the adhesion of an individual coating or the coating system:
1.Determine the hardness of an individual coat or the coating system by performing a Pencil Hardness Test according to ASTM D 3363. Meet or exceed scale of hardness HB for the coating.
2.Perform Adhesion Testing according to ASTM D 4541, Type 4. Meet or exceed 400 psi adhesion between coats or between the paint system and the substrate , or 400 psi cohesion within paint coats . Stencil the Completion Date (month and year) of the finish coat and the letters of the applied paint system on the steel in 4 inch (100 mm) letters with black urethane paint. The appropriate letters for the paint systems are as follows: System Comprised of Letters Inorganic zinc prime coat, epoxy intermediate coat, and urethane finish coat IZEU Organic zinc prime coat, epoxy intermediate coat, and urethane finish coat OZEU Apply the date and paint system at four locations near the end of each outside beam on the outside web visible from the road or as directed by the Engineer.

514.18 Removing Fins, Tears, or Slivers (QCP #6) . Use a grinder to remove

all fins, tears, slivers, or any other burred or sharp edges that become evident after applying the prime coat. Retexture ground surfaces to produce a profile from 1.5 to 3.5 mils (40 to 90 μm) and reprime ground surfaces before a pplying the intermediate coat. The Contractor may begin removing fins, tears, and slivers after blasting and before priming. Temperature and weather restrictions do not apply to removing fins, tears, and slivers, but do to applying the prime coat.

514.19 Caulking (QCP #9). After the intermediate coat cures and before

applying the finish coat, caulk gaps or crevices up to 1/2 inch ( 13 mm) wide. Follow the manufacturer’s recommendations for curing before applying the finish coat . 514.20 416 514.20 Dry F ilm Thickness (QCP #5, #8, and #10). Determine prime coat thickness; prime and intermediate coat thickness; and prime, intermediate, and finish coat thickness using a Type 2 magnetic gage as follows: Measure paint thickness at separate, evenly spaced, spot measurement locations over each 100 square feet (9 m²) of area of structural steel. Locate five spot measurements on each of the following locations: top flanges; bottom flanges; webs; cross bracing; stiffeners; etc. At each spot location, take three gag e readings of either the substrate or the paint. Move the probe 1 to 3 inches (25 to 75 mm) for each new gage reading. Discard an unusually high or low gage reading that is not consistently repeated. The spot thickness measurement is the average of the thr ee gage readings. The average of five spot measurements for each location in the 100 square foot (9 m²) area shall not be less than the specified thickness. No single spot measurement area shall be less than 80 percent of the specified minimum thickness n or greater than 150 percent of the maximum specified thickness when organic zinc is applied and 120 percent of the maximum specified thickness when inorganic zinc is applied. Any one of three readings which are averaged to produce each spot measurement, may under run or overrun by a greater amount. Take five spot measurements per location for each 100 square foot (9 m²) area as follows:

A.For all shop painted steel, regardless of size, randomly select and then measure one 100 square foot (9 m2) area with in each 300 square foot (27 m²) unit of surface area that is painted.
B.For structures not exceeding 300 square feet (27 m²) in area, measure each 100 square foot (9 m²) area.
C.For structures not exceeding 1000 square feet (90 m²) in area, randomly sel ect and then measure three 100 square foot (9 m²) areas.
D.For structures exceeding 1000 square feet (90 m²) in area, measure the first 1000 square feet (90 m²) as stated in section C and for each additional 1000 square feet (90 m²), or increment thereof, randomly select and then measure one 100 square foot (9 m²) area.
E.If the dry film thickness for any 100 square foot (9 m²) area (sections C and D) is not in compliance with the requirements of this subsection, then measure each 100 square f oot (9 m²) area.
F.Measure other areas or revise the number of spot measurements as shown on the plans. Each coat of paint shall have the following thickness measured above the peaks: 514.20 417 Min. Spec. Thickness Max. Spec. Thickness Min. Spot Thickness Max. Spot Thickness (Inorganic Zn) Max. Spot Thickness (Organic Zn) Prime 3.0 mils (75 µm) 5.0 mils (125 µm) 2.4 mils (60 µm) 6.0 mils (150 µm) 7.5 mils (188 µm) Intermediate 5.0 mils (125 µm) 7.0 mils (175 µm) 4.0 mils (100 µm) 10.5 mils (263 µm) 10.5 mils (263 µm) Subtotal 8.0 mils (200 µm) 12.0 mils (300 µm) 6.4 mils (160 µm) 16.5 mils (413 µm) 18.0 mils (450 µm) Finish 2.0 mils (50 µm) 4.0 mils (100 µm) 1.6 mils (40 µm) 6.0 mils (150 µm) 6.0 mils (150 µm) Total 10.0 mils (250 µm) 16.0 mils (400 µm) 8.0 mils (200 µm) 22.5 mils (563 µm) 24.0 mils (600 µm) Remove paint with a film thickness greater than the maximum specified thickness unless: The paint does not exhibit defects such as runs, sags, bubbles, or mud cracking, etc. The manufacturer provides a written statement to the Engineer that the excessive thickness is not detrimental. For any spot or average of five spots at any location of a 100 square foot (9 m²) area that exceeds the maximum spot thickness, either remove and replace the coating according to 514.22 or prove to the Office of Construction Administration that the excess thickness will not be detrimental to the coating system. In order to prove to the Office of Construction Administration that the excess thickness will not be detrimenta l to the coating system, the Contractor must provide the Office of Construction Administration with the following information. Certified test data proving that the excessive thickness will adequately bond to the steel when subjected to thermal expansion an d contraction. The thermal expansion and contraction test shall take place over five cycles of a temperature range from -20 to 120 °F ( -49 to 49 °C). After the thermal contraction and expansion cycles have taken place, the tested system shall be subjected to pull off tests and the results compared to the results of pull off tests that have been performed on a paint system with the proper thicknesses. Perform the adhesion tests according to ASTM D 4541 Type IV. Document the preparation methods for the panel s, including profile and level of cleanliness. Document the application methods, conditions and if any thinner, (percentage), was used. Test the panels according to the following:
1.Lightly sand the coating surface and aluminum dolly, and apply a quick set adhesive. Document the type of adhesive.
2.Allow adhesive to cure overnight.
3.Scribe the coating and adhesive around the dolly before testing.
4.Make a minimum of 4 trials to failure and report the 4 trials. Reject trial if fracture occurs at the primer -substrate interface or pressure at failure is less than 400 pounds per square inch (2.8 MPa). 514.21 418 a. Describe the test specimen as substrate A, upon which successive coating layers B, C, D, e tc. have been applied including the adhesive Y which secures the dolly Z to the topcoat.
b.Designate cohesive failures by the layers within which they occur as B, C, etc., and the percent of each.
c.Designate adhesive failures by the interfaces at wh ich they occur as A/B, B/C, C/D, etc, and the percent of each. In addition to the certified test results, the Contractor shall provide the Office of Construction Administration a written statement from the paint manufacturer stating that the excessive thic kness is not detrimental. If the Office of Construction Administration does not approve the excessive coating thicknesses or the Contractor elects not to provide the required written statement from the paint manufacturer and the certified test results when required, the Contractor shall remove and replace the coating. The removal and replacement of the coating shall be done as specified in 514.19.

514.21 Final Inspection

A.The Engineer will select locations for coating removal for inspection of surface preparation and dry film thickness. For all structures in which the supporting members are rolled beams or girders, remove a minimum of one location per 150 linear feet (46 m) of beam line for webs and flanges and 5 percent of all cross frame assemblies an d other secondary structural members shall be selected for destructive testing. For all other bridge types with structural steel, remove one location for every 1200 square feet (108 m ²) of steel surface for destructive testing. Do not perform destruct ive testing on areas that have been painted with an inorganic zinc prime coat.
B.At the selected areas, the Engineer will perform total dry film thickness testing using a type 2 magnetic gage. If the dry film thickness for that spot does not meet the requ irements of 514.18 , additional measurements will be taken to determine the extent of the deficient coatings.
C.At the selected areas, whe re an organic zinc prime coat has been applied, remove at least 9 square inches (58 cm ²) of the new coatings by methods that will not damage the surface of the steel. Approved removal methods are scraping, sanding, or the use of solvents. Do not use power tools. Perform removal while in the presence of the Engineer. The Engineer will document and photograph the selected areas after removal of the new coatings. If work is found not to be in conformance with the specifications and pertinent contract documents , additional locations may be selected for testing.
D.Make repairs of areas where the coatings were removed and other areas that were determined to be deficient. Make repairs according to 514.22 . If the final destructive testing according to 514.21.C, reveals greater than 15 percent of the areas inspected are not in complete conformance with the specifications and pertinent contract documen ts, the Department will require that surface preparation and painting of the structural steel be completely redone to meet the requirements of the Contract Documents at no additional cost to the Department. 514.22 419 E. Final Acceptance shall be based upon the resul ts of the surface preparation observations and dry film thickness measurements obtained from the final inspection. Final Acceptance will also take into consideration acceptable progressive project documentation and progressive field measurements in determi ning the final acceptability of the Bridge Paint System. Inspection access to the test locations to perform the required final inspection measurements shall conform to the requirements of 514.10 .

514.22 Repair Procedures. Remove paint and correct defects or damaged

areas, including areas damaged by welding, and in areas that do not comply with the requirements of this specification. Correct defects and damaged areas using the same paint as originally applied except the Engineer may approve using organic zinc to repair inorganic zinc in the field. Retexture the steel to a near white condition and a profile between 1.5 to 3.5 mils (40 to 90 μm) . Measure the profile immediately before applying the prime coat to ensure the profile is not destroyed during the feathering procedure. See 514.13 .C. Feather the existing paint to expose a minimum of 1/2 inch (13 mm) of each coat. During the reapplication of the paint, apply paint as follows:

A.Apply the prime coat only to the surface of the bare steel and the existing prime coat exposed b y feathering. Do not apply the prime coat to the adjacent intermediate coat.
B.Apply the intermediate coat only to the new prime coat and the existing intermediate coat exposed by feathering. Do not apply the intermediate coat to the adjacent finish coat.
C.Apply the finish coat only to the new intermediate coat and the existing finish coat that was feathered or lightly sanded. Do not apply the finish coat beyond areas that were feathered or lightly sanded. At the perimeter of the repair area, apply the prime and intermediate coats using a brush. Apply the finish coat using either brush or spray. The Contractor may need to apply several applications to obtain the proper thickness for each coat. During the application of the prime coat, the paint shall be continuously mixed. Perform all surface preparation and painting according to this specification. Instead of abrasive blasting, the Engineer may allow alternate methods of preparing the surface. Blend repair areas with the adjacent coating and provide a fi nished surface in the patched areas that is smooth and has an even profile with the adjacent surface. Submit, in writing, the method of correcting areas with runs to the Office of Construction Administration for approval.

514.23 Method of Measurement. The Department will measure Surface

Preparation of Existing Structural Steel and Field Painting of Existing Structural Steel Prime Coat by the number of square feet (square meters) of structural steel painted or on a lump sum basis. The Department will me asure Field Painting 514.24 420 Structural Steel, Intermediate Coat and Field. Painting Structural Steel, Finish Coat by the number of square feet (square meters) or pounds (kilograms) of structural steel painted, or on a lump sum basis. The Department will determine the number of pounds (kilograms) of new structural steel painted by the accepted pay weight of the new structural steel. For steel beam and steel girder bridges, the Department will determine the surface area by taking a nominal measurement of the beams ( i.e., two times the beam depth plus three times the flange width). In addition to this nominal measurement, the Department will add a percentage to account for incidentals such as cross frames, bearing assemblies, stiffeners, expansion joints, scuppers, et c. It is not necessary for the Engineer or Inspector to field measure every detail of the bridge to verify quantities. If there is a quantity dispute, exact field measurements of all painted surfaces and calculations will govern over the above percentage t o account for incidentals. For extremely complex bridges, such as trusses, the Department will pay for painting on a lump sum basis. The Department will measure grinding fins, tears, slivers on existing structural steel by the number of man hours expended by the workers actually doing the grinding and will include the time when the workers are performing grinding and repairing prime coat and not limited to only the actual grinding duration (i.e., the Department will include all hours of the workers when ass igned to grinding regardless of actual grinding time). The Department will not measure grinding fins, tears, and slivers on new steel but will consider it incidental to unit price for the new steel.

514.24 Basis of Payment . The Department will pay for accepted quantities at

the Contract prices as follows: The Department may consider paint as eligible for payment for material on -hand as specified in 109.10 , however, only paint that the Contractor can prove to the Engineer will be used during the construction season is eligible for payment. The Contractor shall provide the Engineer calculations indicating the total square feet (square meter ) of steel to be painted during the construction season. The Contractor shall also provide calculations showing the total number of gallons (liters) required. If the Contractor causes damage or injury to public or private property, the Department will not pay for restoring the property to its original condition. The Department will not pay for repairing adjacent coatings damaged during the blasting operation. The Department will not pay for removing and replacing an area of coating because a spot or maximum average thickness exceeds the maximum spot thickness. The Department will not pay for additional testing required by any hauler, treatment facility, disposal facility or landfill. The Department will pay for caulking under Field Painting Structural Steel, Intermediate Coat. 514.24 421 The Department will pay for final inspection access, test area preparation and test area repair at each selected area under Final Inspection Repair. The Department will not pay for accessing, inspecting, and repairing areas that are not found to be in conformance with the specifications an d pertinent contract documents. All other requirements of this specification are considered incidental to the work. Item Unit Description 514 Square Foot Surface Preparation of (Square Meter) Existin g Structural Steel Lump Sum 514 Square Foot Field Painting of Existing (Square Meter) Structural Steel, Prime Coat Lump Sum 514 Square Foot Field Painting Structural (Square Meter) Steel, Intermediate Coat Lump Sum, Pound (Kilogram) 514 Square Foot Field Painting Structural (Square Meter) Steel, Finish Coat Lump Sum, Pound (Kilogram) 514 Man Hour Grinding Fins, Tears, Slivers on Existing Structural Steel 514 Each Final Inspection Repair 514 Square Foot Shop Painting and Field Touch -Up of (Square Meter) Structural Steel Lump Sum Pound (Kilogram) ITEM 515 PRESTRESSED CONCRETE BRIDGE MEMBERS

515.01 Description

515.02 Fabricator Approval Procedure

515.03 Levels of Fabricator Qualification

515.04 General

515.05 Fabricator Documentation Responsibility

515.06 Shop Drawings

515.07 Pre-Fabrication Meeting

515.08 Materials

515.09 Materials Approval

515.10 Casting Beds

515.11 Weather Conditions During Production

515.12 Equipment

515.13 Inspection Facilities

515.14 Construction Me thods

515.15 Concrete

515.16 Release of Prestressing Strands 515.01

422 515.17 Fabrication tolerances

515.18 Prestressed Member Acceptance and Repair

515.19 Handling, Storage, Transportation, and Erection

515.20 Safety Requirements

515.21 Method of Measurement

515.22 Basis of Payment

515.01 Description. This work consists of preparing shop drawings, furnishing

and manufacturing prestressed concrete bridge members, testing, fabricator performed quality control, documentation, shop coating, and handling, transporting, storing, and erecting prestressed concrete bridge members. Prepare shop drawings and erect prestressed concrete bridge members, according to Item 501 and the additional requirements specified below. Shop coating shall conform to Item 512.

515.02 Fabricato r Approval Procedure. Select fabricators that are pre -

qualified and evaluated by the Office of Materials Management (OMM) according to Supplement 1079 and listed by the Department before the Contract letting Date.

515.03 Levels of Fabricator Qualification. There are three levels of fabricator

qualification. OMM will classify each fabricator at the highest level of fabrication it is qualified to perform . Level Description of Capabilities 1 Straight strand prestressed box beam members 2 Straight strand prestressed I -beam members 3 Draped strand prestressed I -beam members

515.04 General. Produce all members according to Item 511, except as

otherwise specified herein.

515.05 Fabricator Documentation Responsibility. The fabricator shall keep

and maintain records for each project bid line number concerning:

A.Fabricator plant approval.
B.Shop drawing approval.
C.Material test reports.
D.Welding qualifications.
E.Quality Control Plan (QCP) according to Supplement 1079. The fabricator s hall provide access to the above records for audit, inspection, and copying. Provide a copy of the complete records at the completion and final shipment of the work. The Fabricator shall retain all documentation for at least 5 years from the date of final shipment from the fabrication shop. The fabricator shall document all Quality Control (QC) activities to verify the fabrication conforms to the specification requirements. QC activities include material quality checks, dimensional checks, weld inspections, strand tensioning procedures, release procedures, post -pour inspections, concrete strengths at release of strand and final strength of concrete before shipment, cleaning operations, coating 515.06 423 applications, final QC inspections, repairs and all other QC proc edures required to provide a prestress concrete member conforming to the specifications. Supplement 1079 defines the quality control plan evaluation process and quality control plan enhancement process The Department will perform a quality assurance (QA) evaluation of the fabricator’s quality control performance using forms in Supplement 1079 and will include both validation of the fabricator’s actual records of inspection and Department inspection .

515.06 Shop Drawings. Provide shop drawings conforming t o 501.04 and the

following requirements. Include all details, dimensions, dimensional tolerances, and size of materials, lifting devices, inserts, reinforcing steel supports, fabricator incorporated reinforcing, piece mark diagrams for field connection and erection of any steel and all prestress members, and all other information necessary for the complete fabrication and erection of the prestressed members. Show all items that will be incorporated into each prestressed member. Provide the detensioning proc edure and pattern conforming to 515.16.

515.07 Pre-Fabrication Meeting. At least 3 days after the Department receives

shop drawings, conduct a pre -fabrication meeting at the fabricator’s facilities, or another location agreed to by all parties. As part of the pre -fabrication meeting request, provide a initial fabrication schedule for the prestressed beam project including:

A.Start date for fabrication of the project
B.Expected phasing of fabrication, if any
C.Number of workdays for the projec t and length of work day
D.Quality control final inspection date The fabricator’s production manager, quality control specialists (QCS) for the project, the Department’s inspector, and the Contractor, or its designated representative, shall attend the mee ting. The meeting is to review fabrication issues, including information on shop drawings, previous QC/QA inspection issues, QC and Quality Assurance inspection hold points, unique and special fabrication items, and special processes. The QCS will conduct the meeting and record and distribute meeting minutes that document all issues discusses. Begin fabrication when all meeting issues have been resolved. Office of Material Management may waive the pre -fabrication meeting if accepted by the Fabricator and t he Contractor. If Contractor submitted shop drawings do not comply with the requirements of 515.06, no pre -fabrication meeting can be scheduled or waived.

515.08 Materials. Furnish materials conforming to:

Reinforcing steel ................................ .......................... 509 Concrete ................................ ................................ .. 515.15 515.09 424 Portland cem ent ................................ ... 701.01 thru 701.09 Aggregate * ................................ ............................ 703.02 Air-entraining admixture ................................ ........ 705.10 Chemical admixtures for concrete .......................... 705.12 Prestressing steel ................................ .................... 711.27 Transverse tie rods ................................ ................. 711.01 Welded wire reinforcement ................................ .... 709.12 * For fine aggregate, use natural sand for members without a separate wearing course. Modify coarse aggregate as follows: Do not allow more than 0.4 percent deleterious materials. For gradation, use No. 6, 67, 68, 7, 78, or 8 size coarse aggregate.

515.09 Materials Approval. The fabricator shall control, test, and validate

material requirements for all materials either incorporated into the prestressed fabricated item or supplied under Item 515 as component parts to the fabricated items. The fabricator shall provide Supplement 1079 documentation to the in spector at the time of final inspection. The Department will not sample materials at the fabricator’s shop for Department approval. The Department will randomly sample materials to verify the fabricator’s performance.

515.10 Casting Beds. Use steel or conc rete casting beds set above grade to

ensure the beds remain above the accumulation of water resulting from production and curing operations. Design beds and abutments capable of safely resisting all forces applied to them without appreciable movement or de flection. These forces include compression and eccentric forces due to end -jacking operations, forces at hold down points when draped strands are used, and downward forces due to the dead weight of the members.

515.11 Weather Conditions During Production. Make temperature change

adjustments to initial strand tensioning according to PCI Quality Control Manual 116.

A.Cold Weather. Conform to the requirements of this subsection if the ambient air temperature is below 50 °F (10 °C). Heat mixing water, aggregat es, or both as necessary to produce a concrete temperatures from 50 to 70 °F (10 to 21 °C) when placed. Do not allow water heated above 150 °F (66 °C) to directly contact the cement. Do not place concrete against forms, reinforcing steel, prestressing stra nd, or other hardware materials with a temperatures below 32 °F (0 °C). Immediately prior to final stressing, obtain the temperature correction factor for prestressing strands using a thermometer that has been calibrated against a NIST - traceable thermometer. Define the frequency, location, and thermometer in the Quality Control Plan . Do not place concrete when the ambient temperature with sustained wind chill factor at the point of concrete placement is below 0 °F ( -18 °C).
B.Hot Weather. If the ambient temperature is above 90 °F (32 °C) cool the mixing water, aggregates, or both, as necessary to produce a concrete temperature from 70 to 90 °F (21 to 32 °C). Do not place concrete against forms, mild reinforcing 515.12 425 steel, prestressing strand, or othe r hardware materials with a temperature greater than 120 °F (49 °C). Water fog spray forms, mild reinforcing steel and strand just prior to placing the concrete. Cover beams immediately after casting to prevent surface drying. Do not place concrete when the ambient temperature at the point of concrete placement is above 100 °F (38 °C).
C.Inclement Weather. If a rainfall event begins after placement of concrete in the forms has begun, provide cover and complete only the beam that had concrete in it when the rain began. Provide immediate cover over previously poured concrete, not yet cured. Resumption of concrete placement is permitted after the rainfall stops.

515.12 Equipment. Provide hydraulic jacks of sufficient capacity and stroke to

tension strands. Use either single or multiple strand tensioning. Provide tensioning jacks equipped with automatic cutoff valves and equipped with 6 inch (150 mm) minimum diameter gages that provide readings at 500 pound (2 kN) increments. Calibrate gages for the jacks w ith which they are to be used. Have a graph or table showing the calibration available for the inspector. Calibrate jacks according to a method acceptable to the Laboratory at least every 6 months or as required by the Director. Maintain calibration docume ntation as part of the project’s QC inspection records. Design the jacking system to ensure uniform stress in all strands. If simultaneously tensioning multiple strands, use approved types of dynamometers to equalize the initial stress on all strands befor e applying the full tensioning load with the master jack Provide dynamometers with sufficient capacity to ensure that the desired readings are in the middle to upper range .

515.13 Inspection Facilities. The fabricator shall provide the inspector office

accommodations conforming to the following requirements:

A.Minimum floor area of 120 square feet (11 m2).
B.Minimum ceiling height of 7 feet (2.1 m).
C.Adequate working and storage facilities, work space, lighting, electrical outlets, lockable files or cab inets with key .
D.Heating and cooling capable of maintaining an ambient air temperature between 68 °F (20 °C) and 80 °F (27 °C).
E.Secure internet access.

515.14 Construction Methods. Use metal forms capable of producing members

within the tolerances shown on the plans. Forms made of material other than meta l may be used for bulkheads and voids and may be used for a single project for prestressed members requiring non -standard forms. Ensure that the surfaces of the forms in contact with the concrete are smooth and the joints between panels are tight. The sof fit form shall have a plane surface at right angles to the vertical axis of the members and have the two bottom edges beveled 3/4 inch (19 mm) with a triangular strip built into the forms. Increase the length of the forms for elastic shortening and normal concrete shrinkage, and design the forms to accommodate this movement . 515.15 426 Provide water -resistant formwork for box beam voids constructed of a material that resists breakage and deformation during placement of concrete. Provide form material that does not exc essively increase the dead load of the beams. Prevent the release agent from contacting the prestressing strands or reinforcing steel. Install and assemble reinforcing steel according to the approved shop drawings. If authorized, weld reinforcing cages usi ng welders qualified to AWS D1.4. Do not weld epoxy coated or galvanized reinforcing steel unless approved by Office of Material Management. Repair all coating areas damaged by welding according to the coating manufacturer’s instructions. Reject reinforcin g steel with a loss of cross - section of reinforcing caused by welding. Provide a protective covering for the prestressed steel from the elements until the strand is pulled into the bed. Accurately place strands in the positions shown on the shop drawings. Do not use strands with kinks, bends, nicks, broken wires, scale, loose rust, or other defects. The fabricator may use slightly rusted reinforcing steel provided the rust is not sufficient to cause visible pits. Before placing the concrete, carefully clea n the strands of all dirt, grease, oil, or other foreign matters. Do not splice strands within a member. Tension strands uniformly to the stress indicated on the shop drawings. If multiple stands are stressed simultaneously, use dynamometers to equalize th e initial stress on all strands before applying full tension load with master jack. Measure the required stress in the strands using the calibrated jacking equipment gages, and check the measured stress by the elongation of the strands. If the stress from the gages and the measured elongation are not within a 5 percent tolerance of the design, stop stressing the strands and determine the reason for the differences. The quality control specialist shall keep a record of the jacking forces and elongations of a ll strands . Secure the strands by suitable anchorage devices capable of developing at least 85 percent of the ultimate strength of the strands. The anchorage shall not allow the strand to slip after the tensioning operation. If using draped strands, the lo ss of stress due to friction shall not exceed 5 percent. Tension the strands at both ends. The quality control specialist shall measure the loss due to friction by a procedure approved by the Office of Material Management. Place hold -down points within 3 i nches (90 mm) of the locations shown on shop drawings and within 12 inches (0.3 m) of the locations shown on the plans. Unless otherwise shown in the plans, do not install inserts or holes in the beam web within a distance of 1.5 times the beam height from the end of the beam.

515.15 Concrete . The fabricator shall provide concrete mix designs to Office of

Material Management. The submittal will include:

A.Test data showing the mix achieves the required 28 -day strength when cured by methods used for member fabrication. The strength of the concrete for the mix design approval and during production is determined using sets of two, 6 × 12 -inch cylinders or three, 4 × 8 -inch cylinders. B. w/c ratio (maximum =0.40)
C.A design and maximum slump 515.15 427 D. Test data show ing the mix design achieves 2000 coulombs or less at 90 days when tested according to AASHTO T277. Use samples for the test that were mixed without corrosion inhibitors and that were cured with the same methods that will be used to produce the prestressed concrete bridge members. Do not apply additional cure to samples that have reached the required design strength. Changes in proportioning, cement, pozzolans or aggregate will require retesting and resubmittal. Office of Materials Management may waive the retests. Provide the waiver request in writing and include all information for the new mix design and a comparison to the previously tested and approved mix design(s). Deliver concrete according to Item 499 except that 499.03 and 499.04 does not apply. The plastic air content of the concrete before placement shall be 6 ± 2 percent. If the Department questions the concrete’s placed air content, obtain cores from the prestressed member and have hardened air testing performed by an independent testing lab acceptable to the Department. Beams with hardened air contents below 4 percent will be rejected. Add an approved corrosion inhibiting admixture at the approved dosage and document the dosage that has been incorporated into each batch of concret e. Maintain the mix design slump during production. Segregation of the mix is not acceptable. Do not exceed the maximum water -cement ratio during concrete production. When using admixtures to increase the slump, use Type F or G as described in 705.12. Do n ot use calcium chloride or admixtures containing calcium chloride. Sample and test the concrete for prestressed concrete members as specified below: TABLE 515.15 -1, TEST SPECIMEN REQUIR EMENTS Cubic Yards per Bed Sampling Frequency Number of Cylinders Required Less than or equal to 30 cubic yards First and last load per bed Minimum of 4 30 to 60 cubic yards First and last load per bed plus one random sample. Minimum of 6 Greater than 60 cubic yards First and last load per bed plus 2 random samples. Minimum of 8 Determine strength, for both strand release and final shipping, by testing a group of cylinders, which consists of one cylinder from every sample location. Each group of cylinders shall have an average strength of what is specified in the shop drawings, and no individual cylinder shall have less than 95 percent of the specified strength. The inspector may require additional cylinders from locations were the concrete does not conform to mix design or placement requirements. Include these additional cylinder s in the group of cylinders for determining release and final strength. 515.15 428 The fabricator may place concrete in the bottom flange of a box beam before placing the interior forms and reinforcement for the upper portion of the member, provided continuous concre te placement is not interrupted for more than 45 minutes. Screed the top surfaces of non -composite members and finish the surface with a burlap drag or other means to provide a uniform surface with a gritty texture suitable for waterproofing. Screed the top surface of composite members and finish the surface with a wire broom, in a transverse direction and penetrating the finished surface approximately 1/4 inch (6 mm) + 1/16 inch (1.5 mm) – 1/8 inch (3 mm) at a maximum spacing of 1 -1/2 inches (38 mm). Immediately after final concrete placement and surface finishing, protect the concrete surface with a suitable enclosure until application of live steam or radiant heat. Assure the enclosure’s ambient temperature is at least 50 °F (10 °C). Assure the plastic concrete’s temperature before initial set doesn’t rise more than 10 °F (5 °C) per hour. Limit the total rise before initial set to less than 40 °F (22 °C) and the maximum temperature to 100 °F (38 °C). Record the times and concrete temperature s before initial set. For curing with low -pressure steam, do not apply live steam directly onto the concrete forms if it causes localized high temperatures. For accelerated curing with radiant heat, apply radiant heat using pipes circulating steam, hot oi l, or hot water, or using electric heating elements. Minimize moisture loss by covering all exposed concrete surfaces with plastic sheeting, 705.06, or by applying a liquid membrane curing compound, 705.07, to all exposed concrete surfaces. Before bonding field-cast concrete or other materials in the finished structure, remove the curing compound from the shear faces of composite members and other surfaces. Start initial application of the steam or heat 2 to 4 hours after final concrete placement. If using retarders, start applying the steam or heat 4 to 6 hours after final concrete placement. If determining the time of initial set according to ASTM C 403, these time limits do not apply. Record and report the actual time of concrete placement of the last loa d, placement of enclosure and initial set time. Apply live steam or radiant heat so the ambient temperature within the curing enclosure does not gain more than 40 °F (22 °C) per hour until reaching the curing temperature. Do not exceed 160 °F (71 °C). Only use a maximum temperature of 180 °F (82 °C) if the fabricator documents to the Department that delayed ettringite or alkali silica reaction is not at issue. Maintain the maximum curing temperature until the concrete has reached the required release streng th. De-tension the strands immediately upon completing the accelerated curing. Keep a record of the time the application of heat began, and curing temperatures throughout the entire curing process. Neatly fill cavities in the exposed surface of beams with nonshrink grout. Clean the concrete, and apply and cure the grout according to the manufacturer’s published recommendations. Reject beams with honeycombing that impairs the member’s performance. 515.16 429 515.16 Release of Prestressing Strands. Do not release prestr essed strands until the concrete reaches a minimum strength of 4000 pounds per square inch (28.0 MPa), or plan defined release strength. Determine strength of concrete by testing cylinders produced according to AASHTO T 23 and cured in the same method as the member. Test cylinders in the fabricator’s laboratory. Assure all tested cylinders obtain the required strength of 4000 pounds per square inch (28.0 MPa) or the plan defined release strength. Provide the Department the ability to witness the cylinder testing by notifying the inspector before testing. Before releasing prestressed strands, loosen or remove forms and hold -downs and all other attachments restricting either horizontal or vertical movement of prestressed members. Release the strands immediatel y upon completing accelerated curing. Heat release and burn the strands simultaneously between each beam and at all exposed points between anchorages, and follow an approved pre -determined pattern, to equalize the forces being transferred to the various ar eas of the cross - section of the member. Submit any alternative strand release plans during the prefabrication meeting to OMM for approval. For heat release, use a low -oxygen flame to uniformly heat at least a 4 inch (100 mm) long section of strand before completely cutting the strand.

515.17 Fabrication Tolerances. Construct all members to conform to the

following tolerances. TABLE 515.16 -1, BEAM DIMENSIONAL TOL ERANCES Description Box Beam I Beam Length of beam ±1/8" per 10 ft (1 mm/m) max ±3/4" (19 mm) ±1/8" per 10 ft (1 mm/m) max ±1" (25 mm) Depth of beam ±1/4" (6 mm) -1/4" (6 mm) +1/2" (13 mm) Depth of I beam flange including fillets N/A ±1/4" (6 mm) Beam (box)/Flange (I) Flange Width ±1/4" (6 mm) -1/4" (6 mm) +3/8" (10 mm) Flange Thickness excluding fillets

a.Top -0 +1/2" (13 mm) ±1/4" (6 mm)
b.Bottom -1/8" (3 mm) +1/2" (13 mm) ±1/4" (6 mm) Width Web N/A -1/4" (6 mm) +3/8" (10 mm) Width beam walls -1/4" (6 mm) +3/8" (10 mm) N/A Width of Void ±1/2" (13 mm) N/A Height of Void ±1/2" (13 mm) N/A Box Beam Diaphragm spacing ±2" (50 mm) N/A Deviation from True Vertical ±1/8" (3 mm) 1/8" per ft (8 mm per m) Deviation from Skew Angle ±1/2" (13 mm) ±1/2" (13 mm) 515.18 430 TABLE 515.16 -2, BEAM ACCESSORY TOLER ANCES Description Box Beam I Beam Position of railing anchors ±1/4" (6 mm) N/A Position of lifting devices ±6" (150 mm) ±6" (150 mm) Positions of anchor dowels and tie rods, inserts ±1/2" (13 mm) ±1/2" (13 mm) Deviation from skew angle ±1/2" (13 mm) ±1/2" (13 mm) TABLE 515.16 -3, BEAM STRAND TOLERANCES Description Box Beam I Beam Strand tendon position ±1/4" (6 mm) ±1/4" (6 mm) Strand CG position ±1/4" (6 mm) ±1/4" (6 mm) TABLE 515.16 -4, REINFORCING STEEL TO LERANCES Description Box Beam I Beam Clear cover -0 +1/4" (6 mm) -0 +1/4" (6 mm) Splice lengths -1 1/2 " (38 mm) -1 1/2 " (38 mm) Stirrup spacing i n anchorage zone ±1/4" (6 mm) ±1/4" (6 mm) Stirrup spacing outside anchorage zone ±1" (25 mm) ±1" (25 mm) Stirrup extension above top flange -1/2" (13 mm) +1/4" (6 mm) 0 +1" (25 mm) Reinforcement extension beyond beam end -3/4" (18 mm) +0 -3/4" (18 mm) +0 TABLE 515.16 -5, BEAM SWEEP AND CAMBE R TOLERANCES Description Box Beam I Beam Horizontal Sweep ±1/8" per 10 ft (1 mm/m) max ±3/4 " (19 mm) ±1/8" per 10 ft (1 mm/m) max ±1 " (25 mm) Max Gap between beam 1" (25 mm) N/A Deviation from Design camber (D t) [1] + Sacrificial Haunch [2] or 1/8" per 10 ft (1 mm/m) max 1/2" (13 mm) + Sacrificial Haunch [2] or Variation in camber between beams in same span max 1/2 " (13 mm) N/A [1] Design camber (Dt) calculated in accordance with 511.07 [2] Unless otherwise noted, Sacrificial Haunch thickness is 2 "

515.18 Prestressed Member Acceptance and repair . Throughout the

fabrication process reject all prestressed members not meeting specification requirements. For all rejected members provide the Department with a complete description of the rejection, and unless waived by the Director, an Ohio registered p rofessional engineer’s written evaluation of the criticalness of the rejection and the professional engineer’s proposed repair method that will repair the rejected member to an acceptable condition. The Department will determine the acceptability of the member and the repair procedure. If acceptable, the fabricator will only make repairs witnessed by the Department’s inspector unless waived by Director. 515.19 431 Use the Precast/Prestress Concrete Institute’s Manual for the evaluation and repair of Precast, Prestres sed Concrete Bridge Products MNL -137-06 as a general guide. The Department will not accept for shipping, prestressed members with measured camber exceeding the Design Camber (Dt), used to establish the seat elevations, according to 511.07, by more than the Sacrificial Haunch thickness, until a corrective work plan has been approved by the Engineer. The plan shall be signed, sealed and dated by an Ohio Registered Engineer and shall include all revised plan information necessary to place the deck to the plan thickness. If the prestressed members are acceptable, exclusive of the deviation from Design Camber, the Department will pay for all costs incurred resulting from measured camber exceeding Design Camber calculated for the actual beam age at the time of dec k placement, as Extra Work, 109.05.

515.19 Handling Storage, Transportation, and Erection. Handle, store,

transport, and erect the members in an upright position. The direction of support reactions during storage and transportation shall be the same as the member will experience in its in -service position. Do not ship prestressed members until the concrete obtains its 28 -day design strength and the inspector’s approval. Provide at least 30 inches (762 mm) horizontally between each beam for inspection. Provi de at least 8 inches (200 mm) of vertical clearance from the bottom. Use storage support locations as close as practical to the in -service support locations. During storage, provide unyielding horizontal supports and bracing capable of maintaining the memb ers in a vertical position. Transportation support locations shall be the sole responsibility of the fabricator with respect to member stresses and safe delivery to the job site . Obtain the Director’s written approval to transport the members in a positio n other than vertical ., Provide lifting devices capable of withstanding the required loads to lift and erect the members. During erection, accurately place the prestressed beams on their bearings to ensure a uniform load on all bearings. When shifting a m ember, lift the member up completely off of its bearings. Temporarily brace the first I -beam erected to its substructure support units in the vertical position before releasing the beam from the crane. Tie each subsequent I - beam to the previously braced b eam(s). Provide bracing after erection adequate to prevent sliding, tipping, or other movement that may result from high winds, creeping down the grade, or other causes, until placement of the diaphragms. Within any one day erect and brace at least 2 adjac ent members in any one span before suspending operations for the day. Place box beams to ensure a correct fit of the keyways and to ensure proper grouting of the keyways. After placing the beams and installing tie devices, fill the longitudinal keyways usi ng non -shrink keyway grouts, 705.22, approved by OMM. Mix, install, and cure the grout according to the manufacturer’s published recommendations to obtain a design compressive strength of 5000 pounds per square inch (34.5 MPa). 515.20 432 Do not allow vehicular load on an individual prestressed concrete box beam until the grout in the keyway obtains the specified design strength of 5000 pounds per square inch (34.5 MPa). At the Director’s discretion, repair or replace members damaged by improper handling, storage, tra nsportation, or erection.

515.20 Safety Requirements. Provide effective safety measures to prevent

injuries to personnel due to breakage of strands or failure of anchorage devices during the tensioning operations. Provide adequate protection and assure the OMM inspector can perform inspection of beams and manufacturing processes. The Department inspector will report any inadequate safety precautions to the plant QCS and to OMM if fabricator remedial action is not taken. OMM inspectors will follow safety rul es established by the fabricator, at a minimum. Where fabricator safety rules interfere with the inspectors’ duties, the process should be altered to allow the inspections to be performed while maintaining the required level of safety.

515.21 Method of Measurement. The Department will measure Prestressed

Concrete Bridge Members by the number of members. The Department will measure the intermediate diaphragms by the number of each placed.

515.22 Basis of Payment. Payment for prestressed concrete beams inc lude all

inserts, sleeves, fittings, reinforcing steel fully or partially encased in the members, threaded rods, embedded inserts, embedded bearing sole plates, temporary bracing, fixed anchor dowels, and all transverse tie rods necessary to complete this work . The Department will consider all costs associated with all structural steel, including bolts, nuts, washers and plate washers for steel intermediate diaphragms, as well as concrete and reinforcing steel for cast -in-place concrete intermediate diaphra gms as incidental to the intermediate diaphragms . The Department will pay for expansion joint end diaphragms, semi -integral diaphragms, pier diaphragms, bearing load plates , bearing pads, and other expansion materials, separately . The Department will not pay for repaired or replaced members damaged by improper handling, storing, transporting, or erecting. The Department will pay for accepted quantities at the contract prices as follows: Item Unit Description 515 Each Prestressed Concrete Non - Composite Box Beam Bridge Members, Level 1 515 Each Prestressed Concrete Composite Box Beam Bridge Members, Level 1 515 Each Straight Strand Prestressed Concrete Bridge I-Beam Members, Level 2 515 Each Draped Str and Prestressed Concrete Bridge I-Beam Members, Level 3 515 Each Intermediate Diaphragms 516.01 433 ITEM 516 EXPANSION AND CONTRA CTION JOINTS JOINT SEALERS AND BEARING DEVICES

516.01 Description

516.02 Fabrication

516.03 Coating

516.04 Materials

516.05 Expansion and Contraction Joints

516.06 Joint Sealers

516.07 Bearing Devices

516.08 Method of Measurement

516.09 Basis of Payment

516.01 Description. This work consists of fabricating, assembling,

constructing, coating, and installing expansion and contra ction joints, vertical extension of structural expansion joints, joint sealers, or bearing devices of the type and size specified.

516.02 Fabrication. Fabricate metal joint armor and metal bearings according

to Items 513. Select a fabricator that is at lea st pre -qualified at level SF. The Department will base final acceptance of fabricated members on the Engineer’s approval that the fabricated items that can be successfully incorporated into the structures. Submit mill test reports for structural steel, ste el castings, bronze, and sheet lead certified according to 501.06.

516.03 Coating. Coat exposed steel bearings according to Items 513 and 514

that are to be attached to structural steel. Galvanize bearings according to 711.02 that are to be attached to concrete beams. Coat metal parts of expansion joints with metalized 100 percent zinc wire. Prepare the surface to be coated and apply coating as required by The Society of Protective Coatings SSPC -CS-23.00(1). Apply coating to a minimum thickness of 6 mils. Repair metalized coatings damaged during fabrication by removal of the damaged coating and reapplication as specified above. Repair metalized or galvanized coatings damaged during shipping, construction, or field welding according to 711.02.

516.04 Mater ials. Furnish materials conforming to:

Structural steel ................................ ............................. 513 Bearing bolts and anchor rods ................................ . 711.10 Painting ................................ ................................ ........ 514 Joint sealer, hot applied ................................ .......... 705.04 Preformed elastomeric compression stager ............. 705.11 Neoprene Sheeting ................................ .................. 705.13 Steel castings ................................ .......................... 711.07 Sheet copper ................................ ........................... 711.15 Bronze ................................ ........... 711.16, 711.17, 711.18 Sheet lead. ................................ ............................... 711.19 Preformed bearing pads ................................ .......... 711.21 Elastomeric bearings ................................ ............... 711.23 516.05 434 Preformed fillers ................................ ..................... 705.03 Swedged anchor bolts or bars* ............................... 711.10 Non-Shrink,Non -Metallic Grout ………………….705.20 * Fabricated by deforming a minimu m of 20 percent of the embedded bolt surface with deformations whose radial dimensions are 15 to 20 percent of the bar diameter.

516.05 Expansion and Contraction Joints. Ensure that expansion joints are

completely open for the dimension specified for thei r full length. Remove stones, forms, or other materials that interfere with expansion. Finish the surface adjacent to preformed expansion joints to a smooth, uniform surface. Use methods that do not interfere with the free compression of the joint material to anchor the expansion joint materials. The joint material shall neatly fill the space, and have a uniform thickness for the full extent of the joint. For Integral and Semi -Integral Abutment Expansion Joint Seals, install a 3 foot wide neoprene sheet for waterproofing of the backside of the joint between the integral backwall and the bridge seat at locations shown in the plans. Secure the neoprene sheeting to the concrete with 1 1/4 inch by #10 gage (length × shank diameter) galvanized button head spikes through a 1 inch outside diameter, #10 gage galvanized washer. Maximum fastener spacing is 9 inches. Use of other similar galvanized devices, which will not damage either the neoprene or the concrete, will be subject to the approval of the Engineer. Center the neoprene strips on all joints. For horizontal joints, secure the horizontal neoprene strip by using a single line of fasteners, starting at approximately 6 inches from the top of the neoprene strip. For the vertical joints secure the vertical neoprene strip by using a single vertical line of fasteners, starting at approximately 6 inches from the vertical edge of the neoprene strip nearest to the centerline of roadway. For vertical joints, install two additional fasteners at 6 inches, center to center, across the top of the neoprene strip on the same side of the vertical joint as the single vertical row of fasteners is located. The vertical neoprene strips shall completely overlap the horizontal strips. Lap lengths of the horizontal strips that are not vulcanized or adhesive bonded, shall be at least 1 foot in length, or 6 inches in length if the lap is vulcanized or adhesive bonded. No laps are acceptable in vertically installed neoprene strips. The neoprene sheeting shall be 3/32 inch thick general purpose, heavy -duty neoprene sheet with nylon fabric reinforcement.

516.06 Joint Sealers. Before applying joint sealer to the surface, clean the

concrete of foreign matter, curing compounds, oil, grease, dirt, free water, and laitance and clean steel by sand blasting. Apply joint sealer with a minimum depth of 1 inch (25 mm) at its thinnest section. Fill joints to within 1/4 inch (6 mm) of the roadway surface. Separate joint sealer from contact with asphalt concrete using a barrier of foil or other material th at is impervious to the joint sealer. As required to prevent bonding of the joint sealer with a joint surface, place a suitable bond breaker barrier before applying the joint sealer. 516.07 435 Remove joint sealer that did not bond to the joint face as intended withi n 24 hours after placing. Clean the joint by sandblasting and reseal the joint. Mix and place joint sealer according to the manufacturer’s instructions. Provide the Engineer with a copy of the manufacturer’s instructions. Protect joint sealer with an impervious masking tape during the application of concrete protective coatings containing mineral spirits.

516.07 Bearing Devices. For sliding plates, lubricate the sliding surfaces with

flake graphite, and superimpose plates on each other with their edges flush. Install each bridge bearing to within ± 0.125 inch of its marked centerlines in the horizontal plane and oriented to within an angular tolerance of 0.20 rad. (1 degree). Accurately set , level and align elastomeric bearings, bearing plates, and bols ters. Set bearing plates and bolsters on 0.125 inch (3 mm) thick sheet lead, conforming to 711.19. Set bearing plates or bolsters on bridge seat areas that are flat and smoothly finished. If the bridge seat area is high or uneven, use a bushhammer or grinder followed by thin film of portland cement mortar or paste to fill the pitted surface to bring the seat area to the proper elevation and provide a level, even surface. If the bridge seat area is low, use steel plate shims of the same bearing area as the bearing plates and bolsters to bring the seat area to the proper elevation. Set elastomeric bearing pads directly on the concrete surface. If the beams seats are sealed with an epoxy or non -epoxy sealer prior to setting the bearings, do not apply seale r to the concrete surfaces under the proposed bearing locations. If these locations are sealed, or membrane cured, remove the sealer or membrane cure to the satisfaction of the Engineer before setting the bearings. Perform this removal at no expense to the Department . Position rockers, elastomeric bearings, and rollers so that, when the completed bridge is at 60 F (16 C), the rockers and elastomeric bearings are vertical and the rollers are centered on the base. If the steel is erected at an ambient tempe rature higher than 80 °F or lower than 40 ºF and the bearing shear deflection exceeds 1/6 of the bearing height at 60 ºF ± 10 ºF, raise the beams or girders to allow the elastomeric bearings to return to their undeformed shape at 60 ºF ± 10 ºF. Set anchor bolts for bearing devices that are clear of the beam or girder flanges, in the concrete after erecting the main structural steel, except as specified below for bearing devices at abutments. Place reinforcing steel in the bridge seat to not interfere with t he drilling of anchor holes. Accurately set anchor bolts in the holes and embed the anchor bolts in non-shrink, non -metallic grout . Until the anchors’ are installed, prevent water from entering and or freezing in the anchor bolt holes. If structural steel interferes with the setting of the anchor bolts, set the anchor bolts before erecting the steel. The Contractor may determine the location of the bolts by using a template and form holes or embed the bolts when placing concrete or, drilling holes in the ha rdened concrete. Install anchor bolts to project at least 1/4 inch (6mm) beyond the nut when tightened. Damage or burr the threads on the projecting end of the bolt after the nut is tightened. The bolt threads shall not extend to the planes of the contact surfaces 516.08 436 between the connected parts. Include the length of two additional threads to the specified thread length of the bolt to allow for thread runout. Washers no thicker than 1/4 inch (6mm) are permitted under the nut. Permanently fasten bearing devices to the abutments, steel beams, or girders after backfilling the abutments to within 2 feet (0.6 m) of the top of the bridge seat. Where the load plate of an elastomeric bearing is to be connected to the structure by welding, control the welding so that the plate temperature at the elastomer bonded surface does not exceed 300 °F as determined by use of pyrometric sticks or other temperature monitoring devices.

516.08 Method of Measurement. The Department will measure the specified

items by the number of e ach, square feet (square meters), pounds (kilograms), or feet (meters) horizontally along the joint centerline and between the outer limits of the fabricated joint. For deck resurfacing, the Department will measure Structural Steel Expansion Joints extendi ng vertically by the actual horizontal length of joint.

516.09 Basis of Payment. The Department will pay for accepted quantities at

the contract prices as follows: Item Unit Description 516 Foot or Pound Structural Steel Expansion Joints (Meter or Kilogr am) 516 Foot (Meter) Structural Expansion Joints Including Elastomeric ___ Seals 516 Foot (Meter) Elastomeric Compression Seals for Structural Steel Joints, ___ Width 516 Foot (Meter) Folder Copper Strip ___ 516 Foot (Meter) Vertical Extension of Structural Expansion Joints 516 Square Foot ___ Preformed Expansion Joint Filler (Square Meter) 516 Foot (Meter) Joint Sealer 516 Each, Foot, Bearing Devices Square Foot, Pound (Meter, Square Meter, Kilogram) 516 Each, Square Foot ___ inch ( ___ mm) Elastomeric Bearing Pad (Square Meter) 516 Each Elastomeric Bearing with Internal Laminates Only 516 Each ___  ___  ___ Elastomeric Bearing with Internal Laminates and Load Plate ___  ___  ___ 516 Square Foot 1/8-inch (3 mm) Pr eformed Bearing Pads (Square Meter)

Source: Ohio Construction and Material Specifications, 2019 Edition. Pages 00 of 928.