455.01 General. Use this specification for items 451, 452, 305 and 511 when the bid item
description requires QC/QA. This specification defines the minimum Quality Control Plan (QCP) requirements, the Contractor’s minimum quality control (QC) materials testing and the Department’s quality assurance (QA) materials verification testing requirements. Develop a QCP to assure that all materials and construction practices for the item will conform to the specifications. Establish the responsibilities, duties and frequency for both in-process controls and quality control testing at the concrete’s source and at the job site.
455.02 Quality Control Plan Basic Requirements. Submit a complete QCP that includes, at a
minimum, the following:
455.03 Additional Quality Control Plan Requirements for Structures . In addition to basic
QCP minimum requirements of 455.02, provide the following for structures:
455.04 Additional Quality Control Plan Requirements for Concrete Pavement. In addition
to the requirements of 455.02, provide the following information:
451.09 B.
455.05 Department Quality Assurance . The Department will perform Quality Assurance
materials verification sampling and testing as specified or as deemed necessary.
455.06 QCP Submittal and Corrective Action. Submit the proposed QCP to the Engineer for
acceptance at least 10 days prior to placing concrete. If the submitted QCP is not accepted by the Engineer , revise and resubmit the QCP and provide an additional 10 days for acceptance. Reschedule the concrete placement, when necessary, to allow time for the review and acceptance of the QCP. The QCP acceptance is based on the concept that the proposed QCP procedures will provide work meeting all specification requirements. If the accepted QCP is not being followed the Engineer will require compliance or re-submittal of any modifications for review and acceptance. When the actual work produced by the QCP does not conform to specification requirements, the Engineer will require modification of the QCP to return the work to conformance. When notified by the Engineer propose modifications to the QCP for acceptance. Do not continue work until the Engineer has either accepted the revised QCP or determined work can continue.
455.07 Basis of Payment. The cost of developing and implementing the QCP is incidental to the
cost of the concrete sold with the QC/QA requirement. ITEM 499 CONCRETE—GENERAL