452Non-Reinforced Portland Cement Concrete Pavement

OH · 2023 (rev. 7/17/2026) Standard Specifications✓ Full text on BuildSpecBook pages 276–277 Save this section

Ask about Section 452

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

452.01 Description. This work consists of constructing a non -reinforced portland cement

concrete pavement on a prepared surface.

452.02 Construction. The requirements of Item 451 apply, except as follows.

Do not comply with the requirements of 451.08. Provide dowels at transverse contraction joints in mainline pavement, ramps, acceleration/deceleration lanes, or collector/distributor lanes. Dowels for contraction joints in concrete shoulders on mainline pavement, ramps, acceleration/deceleration lanes, or collector/distributor lanes are not required unless the contraction joint is located within 500 feet (150 m) of a pressure relief joint. Space contraction joints according to the standard construction drawings. If Item 452 pavement is specified for shoulders and is tied longitudinally to Item 451 or 305 pavement, match the joints in the shoulder pavement to the spacing and alignment of the adjacent pavement. Do not place construction joints within 6 feet (1.8 m) of another parallel joint. If making pavement repairs before Department acceptance under 451.17, repair all cracks exclusive of size or location

452.03 Method of Measurement. The Department will measure Non -Reinforced Concrete

Pavement by the number of square yards (square meters) completed and accepted in place. The width equals the pavement width shown on the typical cross -sections of the plans plus additional widening as the Engineer directs in writing. The Department will field measure the length along the centerline of each roadway or ramp.

452.04 Basis of Payment. Payment is full compensation for furnishing and placing all materials,

for surface testing, and for coring the pavement. For pavement found deficient in thickness or compressive strength, the Department will pay a reduced price according to 451.19. The Department will not make additional payment over the contract unit price for any pavement with an average thickness in excess of that shown on the plans. The Department will pay for accepted quantities at the contract price as follows: Item Unit Description 452 Square Yard Non-Reinforced Concrete Pavement, (Square Meter) Class _____ 452 Square Yard Non-Reinforced Concrete Pavement, (Square Meter) Class ______ with QC/QA ITEM 455 QUALITY CONTROL PLAN, TESTING AND ASSURANCE FOR QC/QA CONCRETE

Get an email when 452 changes

Ohio revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Construction and Material Specifications, 2023 (rev. 7/17/2026) Edition. Pages 276–277 of 892. View official source ↗

Ask about this section

Scoped to Ohio Construction & Material Specifications, Section 452 — Non-Reinforced Portland Cement Concrete Pavement. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.