Change Order

Defined in the standard specifications of 2 state transportation agencies. Each definition below is the agency’s own text, with the section it comes from — they do not all say the same thing, and on a contract the difference is the point.

Definitions are quoted from state-authored public specification books. This page carries no I-Code-derived terms.

New Hampshire · NHDOT

A revision to the Contract issued after Award. The Change Order establishes the increase or decrease to the Contract Quantities, Contract Amount or Contract Time, if any, for the revision in accordance with 104.02.

Section 101 — DEFINITIONS AND TERMS
New Mexico · NMDOT

A Change Order is the only method authorized for changing the Contract. A written order, with or without the consent of the Contractor, i mplementing the Contract changes. A Change Order m a y c o n s i s t o f a Supplemental Agreement o r Field

Section 101 — Abbreviations, Symbols, T erms, and Definitions