Critical Path Method Schedule
Defined in the New MexicoDOT standard specifications. This is the agency’s own text, with the section it comes from.
Definitions are quoted from state-authored public specification books. This page carries no I-Code-derived terms.
New Mexico · NMDOT
A network based method to represent the Contractor’s plan for constructing the Project. Th e Critical Path Method Schedule consists of two primary components 1) Activities that represent the entire Project scop e of Work and 2) logic relationships that connect the ac tivities to one another to det ermine the sequence of Work.
Section 101 — Abbreviations, Symbols, T erms, and Definitions →