Section 151 — Mobilization

Division 150 — Project Requirements|PDF pages 79–80

Description

151.01This work consists of moving personnel, equipment, material, and incidentals to the project and performing work necessary before starting work at the project site. This work also includes obtaining permits, insurance, and bonds.

Measurement

151.02Measure the Section 151 pay items listed in the bid schedule according to Subsection 109.02 .

Payment

151.03The accepted quantities will be paid at the contract price per unit of measurement for the Section 151 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05 . Progress payments for mobilization by the lump sum will be paid as follows:

(a)Bond premiums will be reimbursed from the mobilization pay item according to FAR Clause 52.232- 5 Payments under Fixed- Price Constru ction Contracts, after receipt of the evidence of payment.

(b)50 percent of the pay item amount, less the amount paid under Subsection 151.03(a) , will be paid after 5 percent of the original contract amount is earned from pay items (not including mobilization). The amount paid will not exceed 5 percent of the original contract amount.

(c)100 percent of the pay item amount, less the amount paid under Subsections 151.03(a) and 151.03(b) , will be paid after 10 percent of the original contract amount is earned from pay items (not including mobilization). The amount paid will not exceed 10 percent of the original contract amount.

(d)Any portion of the pay item amount more than 10 percent o f the original contract amount will be paid after final acceptance.