Section 622 — Rental Equipment

Division 600 — Incidental Construction|PDF pages 752–753

Descript ion

622.01This work consists of providing and operating equipment for construction work ordered and not otherwise provided for under the contract.

Construction Requirements

622.02Rental Equipment. The CO will order in writing rental equipment for use o n the project. Submit the model number and serial number for each piece of equipment before use. Make equipment available for inspection and approval before use. Provide an operator who is skilled in running the rental equipment. Provide equipment with auxiliary attachments necessary to complete the ordered work. Maintain the equipment in good working order. Obtain approval of the length of workday and workweek before starting work. Keep daily records of the number of operating hours for each piece of equipment. Submit records with pay notes within 24 hours of the work being performed.

622.03Acceptance. Rental equipment work will be evaluated under Subsections 106.02 and 106.04.

Measurement

622.04Measure the Section 622 pay items listed in the bid schedule according to Subsection 109.02 and the following as applicable: Do not measure inoperable equipment or equipment dependent upon another piece of inoperable equipment.

Payment

622.05The accepted quantities will be paid at the contract price per unit of measurement for the Section 622 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05 .