1.Equipment for Pressure Grouting. The equipment for pressure grouting of concrete pavement shall be that customarily used in the pressure grouting of earthen embankments or in mud-jacking of concrete pavement consisting of at least the following:
a.Air compressors of sufficient capacity for operating pneumatic hammers.
b.A discharge pipe with an adequate securing device.
c.Pneumatic hammers equipped with drills that will cut 1.5 inch {38 mm} diameter or other approved diameter holes through the rigid pavement. The equipment shall be operated in such a manner so as to prevent unnecessary damage to the slab.
d.A portable gage apparatus which operates from the shoulder and is capable of monitoring slab movement during grouting of holes near the pavement edge. Dial gages with at least 1 inch {25 mm} of travel arm and capable of detecting 0.001 of an inch {25 µm} of movement shall be placed within 1 foot {300 mm} of the hole being grouted and 1 foot {300 mm} outside the edge of paving. The dial gage measuring movement within 1 foot {300 mm} of the hole being grouted shall have an arm length of at least 6 feet {1.8 m}. The base of the support for the gage apparatus shall be a minimum of 5 feet {1.5 m} outside the edge of paving during the monitoring of movement and shall be moved along the shoulder during the grouting of holes along the pavement edge. An engineer's level, furnished and operated by the Department, will be used, periodically throughout the day, to supplement the gage SECTION 453 PRESSURE GROUTING AND REPAIR OF PORTLAND CEMENT CONCRETE PAVEMENT apparatus to monitor slab movement. Alternate gage apparatus setups may be used if requested in writing by the Contractor and approved by the Engineer.
e.Blow pipe to enlarge void area.
f.Equipment for accurately measuring and proportioning by volume or weight {mass} the various materials composing the grout. When volume is used, the weight per cubic foot {mass per cubic meter} of the materials will be determined and mix proportions adjusted accordingly.
g.A batch type mixer, capable of thoroughly mixing the various components of the grout. A high speed, colloidal type mixer will be required for grout mixes containing only cement and fly ash.
h.A positive action pump capable of forcing grout through a drilled hole into voids and cavities beneath the pavement slab. The pump shall be capable of supplying adequate pressure at the end of the discharge pipe to ensure filling of all voids at the required hole spacing. A gage shall be located on the discharge side of the pump to measure the pumping pressure.
i.A flow cone with all necessary components so that the Engineer may make an accurate field determination of the consistency of the grout. The flow cone shall conform to the dimensions and other requirements of ALDOT-338.
2.Equipment for Removal and Replacement. The equipment for removal and replacement of the concrete pavement slabs shall be suitable for the purpose intended and approved by the Engineer. Attention is directed to the operational requirements for removal and replacement in Subarticle (c) below.
b.Pressure Grouting of Pavement Slabs.
2.Preparation of Grout Mixture. The mixtures used in pressure grouting shall consist of the proportions tabulated in Table I. The consistency may be varied by the addition of water and/or other additives. The quantity by weight {mass} of equivalent 100% pure calcium chloride to be included in the mixture shall be in accordance with Item 1 above. The calcium chloride, when required, shall be thoroughly premixed in the approximate quantity of mixing water required for a predetermined batch size before combining with the other ingredients. The consistency of the grout shall be determined in accordance with ALDOT-338. The quantity of mixing water used shall be that which will produce a grout of such consistency that the time of efflux from the flow cone will be a minimum of 14 seconds and a maximum of 22 seconds for undersealing. After the initial introduction of a sufficient amount of water into the mixture to obtain the necessary consistency, no additional water shall be added. The grout shall be used within 90 minutes after introduction of water into the mixture. Dry ingredients may be added to a mixed batch only in the amounts necessary to bring a too thin mixture to the required consistency. In this case the added dry ingredients shall be in the SECTION 453 PRESSURE GROUTING AND REPAIR OF PORTLAND CEMENT CONCRETE PAVEMENT specified ratio. Grout which fails to meet the flow requirements specified above, shall not be used in grouting operations. A grout mixture shall be selected by the Contractor from the mixtures shown in Table I below. The Engineer reserves the right to specify a different mixture if the one chosen by the Contractor fails to produce the desired results. TABLE I GROUT MIXTURES Mix Proportions, Percent by Volume of Dry Ingredients Grout Type 1 2 3 4 5 6 Fine Sand 30 50 50 Limestone Dust 50 80 30 Fly Ash 80 30 50 30 Cement 20 20 20 20 20 20
3.Construction. Selected slabs designated by the Department for pressure grouting shall be drilled as indicated on the plans or designated by the Engineer. For holes nearest the edges of the slab, the joints, or a major crack, a maximum of 3 inches {75 mm} from the precise marked location is considered to be reasonable. For other holes, a maximum 6 inch {150 mm} tolerance is considered to be reasonable. Should it become necessary or desirable to drill holes at locations other than those shown on the plans, such holes shall be drilled only as approved by the Engineer. In no instance shall holes be drilled in the wheel paths of a lane. The drills shall be rotated to avoid cracking the pavement and to provide satisfactory holes of the proper diameter for effective operations in pressure grouting. When drilling holes, the drills shall be held as nearly perpendicular to the pavement surface as possible. Holes which cannot be satisfactorily used in pressure grouting shall be filled with grout and not measured for pay; new holes shall be drilled. After the holes are drilled, and just prior to pressure grouting, a high pressure air pipe may be required to clean the hole, if deemed necessary by the Engineer, to facilitate introduction of the grout. After the holes are cleaned, the discharge hose on the pressure grout pump shall be connected to the hole in a manner that will provide adequate seal to maintain pressure past the connection. The discharge end of the pipe shall not extend below the lower surface of the concrete pavement. To fill all voids, pumping of grout will be required in holes designated by the Engineer. The maximum pressure allowed during the grouting operation will be 200 psi {1.5 Mpa}. A gage shall be located on the discharge side of the pump to measure the pumping pressure. Normally, indication that grout is flowing out of an adjacent hole or joint or the edge of the slab is sufficient evidence that all cavities or voids are filled within the range of the hole being grouted and pumping in such hole shall cease. Additional evidence that grouting should cease is a rapid rise of the slab, or indications of a rise of the adjacent shoulder. A minimal lifting of the slab will be allowed but not to exceed 0.05 of an inch {1 mm} per grouting pass. Care shall be taken not to crack slabs by differential lifting. Any slab or portion of slab or shoulder which is raised more than 0.05 of an inch {1 mm} each grouting will require corrective action, without payment, by the Contractor. Such corrective action shall consist of grinding or other methods approved by the Engineer. After grouting has been completed in a drill hole, the discharge pipe shall be withdrawn and latent grout removed. The hole shall not be plugged unless authorized otherwise by the Construction Engineer. Patching of the hole shall begin after the grout has taken an initial set. The grout shall be removed to a minimum depth of 4 inches {100 mm} below the pavement surface. A low slump concrete mix consisting of 1-part Type I, Type IL, Type IP, Type IS or Type III cement and 2-parts No. 100 concrete sand by volume shall then be placed in the hole, rodded and leveled with the pavement surface. Filled holes that later shrink below the finished surface, ravel out, or otherwise become damaged before project completion shall be repaired. Corrective measures shall be taken in case stooling occurs by making proper adjustment in the stiffness of the grout being used. In case stooling does occur, additional holes shall be provided as directed and a more fluid grout shall be pumped through these new holes to fill the voids between the stools. At least 24 hours, but no later than 5 days, after a slab has been grouted, it shall be tested for movement between the hours of 3:00 a.m. and 7:00 a.m. On cool, cloudy days, this time frame SECTION 453 PRESSURE GROUTING AND REPAIR OF PORTLAND CEMENT CONCRETE PAVEMENT may be extended if approved by the Engineer. The test rolling equipment shall be rubber-tired and of sufficient weight {mass} to give a 20,000 pounds {90 kN} single axle load with a minimum of 10,000 pounds {45 kN} per side (a properly loaded dump truck may be used). Each slab shall be tested by making one or more passes over it with the test roller. The rolling shall be slow enough to allow an observer to measure the movement and mark the slab if regrouting is needed. If the slab moves 0.03 of an inch {0.8 mm} or more during the test rolling, new holes shall be drilled and the slab regrouted. All slabs which have been regrouted shall be retested as outlined above for the initial testing. After two returns for regrouting, should the slab fail the test rolling, the Engineer will make the decision to leave the slab as is, continue regrouting, or remove and replace the slab. Payment will be made under the appropriate pay items for the additional drill holes and grout used in the regrouting operation. The cost of test rolling shall be absorbed in other items of work. The construction methods outlined above may be modified by the Engineer as field conditions indicate. Pressure grouting operations shall cease at least three hours before sundown, except that on cloudy days pressure grouting operations shall cease earlier as necessary to permit grout to harden at least three hours prior to allowing traffic back on the grouted slab before first darkness. First darkness shall be defined as that time of day the average traveling public vehicle would first begin to use its headlights.
c.Removal and Replacement of Pavement Slabs.
1.Removal. The extent of removal shall be as shown on the plans or directed by the Engineer. The slab section designated for removal shall be sawed as shown on the plans. The Contractor shall not oversaw the slab within 2 feet {600 mm} of another oversaw or within 2 feet {600 mm} of any type of joint. Transverse cuts for removal and the placing of new steel tie bars shall be performed as shown by plan details. The sections of pavement to be removed may be removed in any manner approved by the Engineer which does not damage the underlying base layer, adjacent concrete slabs, or the joint steel. Any damage to the underlying base or adjacent slabs shall be repaired to the satisfaction of the Engineer. Joint steel shall be cleaned and reconditioned to provide the same load transfer and/or tie as in the original pavement design. Any damaged or destroyed steel, which in the opinion of the Engineer would not function properly, shall be replaced in kind and retied to the old pavement by drilling an appropriate size hole of the proper depth and anchoring the new bar with an approved adhesive material. This replacement also includes steel damaged or destroyed previous to the removal operation. All tie bars and dowel bars tied to the old pavement shall be anchored into place with an approved adhesive material in such a manner as to meet a 7200 pound {32 kN}, minimum, pull-out requirement. The Department will perform the pull-out tests in accordance with ALDOT-366. The Contractor shall supply the equipment necessary to perform the pull-out test. Slabs shall be removed and replaced during the same day. Preparation for removal, including sawing the slab into smaller pieces, may be done the day prior to removal, but traffic shall be maintained on the slab the night before removal.