b.Equipment. The equipment for cleaning the concrete bridge decks shall be recommended by the manufacturer of the overlay system. The polymer overlay shall be placed using mechanical equipment capable of mixing, metering, and distributing all components of the overlay system in a continuous application as per the polymer overlay manufacturer’s specifications. The equipment shall be capable of heating and maintaining the components of the epoxy binder at a constant temperature. The equipment shall be capable of mixing the components of the epoxy binder at a constant ratio and shall be capable of consistent application rates of both the epoxy and the aggregate and have the capability to display and record the application rates of both materials. The use of agricultural type spreaders for the distribution of the aggregates will not be allowed when mechanical continuous application is required.
c.Surface Preparation. The entire area of the deck surface shall be cleaned by shot blasting to provide a surface free from curing compound, laitance, dust, dirt, oil, grease, bituminous material, paint, and all foreign matter. The contractor shall use the test method described in ASTM C 1583 “Standard Test Method for Tensile Strength of Concrete Surfaces and the Bond Strength or Tensile Strength of Concrete Repair and Overlay Materials by Direct Tension (Pull-off Method)” to determine the shot blasting procedure. The shot blasting procedure shall consist of size of shot, flow of shot, forward speed, and number of passes of the shot blasting machine necessary to expose the coarse aggregate and provide tensile adhesion strength equal to or greater than 250 psi or a failure area, at a depth of 0.25 in. or more into the concrete deck. A test section of not less than 300 sq. ft. of bridge deck will be used to establish the shot blasting procedure. Three random test sites will be selected within the test section by the Engineer and tested according to ASTM C 1583. The Contractor shall provide all test equipment and perform the tests. If the adhesion strength or failure depth criteria are not met, the Contractor shall adjust the shot blasting procedure and the test section will be re-blasted and re-tested until satisfactory test results are attained. Once an acceptable shot blasting procedure is established it shall be continued for the remainder of the bridge. The Contractor may, with the permission of the Engineer, change the shot blasting procedure or equipment, in which case an additional test section and testing will be required. Shot blast cleaning shall include the preparation of all bridge deck spall repair areas. The shot blast cleaning of an area of the deck shall be performed within a 24-hour period preceding placement of the overlay. The shot blast cleaned areas shall be protected against contamination prior to placement of the overlay. Contaminated areas and areas exposed more than 24 hours shall be shot blast cleaned again as direct by the Engineer at the Contractor’s expense. In areas that the shot blasting equipment cannot reach (i.e., along curbs and median walls), sandblasting will be permitted to an extent satisfactory to the Engineer. This shall be performed prior to the shot blasting whenever applicable and practical. Immediately before applying the overlay system, all prepared surfaces shall be cleaned with compressed air (or vacuumed) to remove dust and debris. All surfaces to be overlaid shall be dry.
e.Application of Overlay. Overlay applications consisting of more than 1,000 square yards shall be placed using mechanical equipment capable of continuous application. Manual application will be allowed only when the overlay application consists of less than 1,000 square yards. The polymer overlay shall be placed in two layers of epoxy and aggregate. Both layers shall consist of a layer of epoxy followed with a layer of aggregate. The layer of aggregate shall completely cover the epoxy. The total thickness of the polymer overlay (both layers) shall not be less than ¼ inch nor greater than ½ inch. The application rates of the polymer overlay shall comply with TABLE 490-4. TABLE 490-4 Application Rates Layer Polymer Gallons/100 Square Feet Aggregate Pounds/Square Yard 1 Not less than 2.5 Not less than 10.0 2 Not less than 5.0 Not less than 14.0