determined from the measurements. For example, if the average of the measurements is 65 % of the target retro reflectivity, payment for the striping will be 65 % of the contract unit price. If the average of the 3 retro reflectivity measurements is 50 % of the target retro reflectivity, or less, the sublot shall be removed and replaced without extra compensation. Any portion of the striping that is determined by the Engineer to be noticeably inconsistent with the overall striping and measures less than 50 % of the target retro reflectivity shall be removed and replaced without extra compensation. The Contractor may request that Referee Testing be performed. Referee Testing will be performed by the Contractor with the Department’s device and under the supervision of the Department’s inspector or project manager. The results of any Referee Testing will be the final measurements used for payment, regardless of whether or not the measurements are greater than or less than the original measurements performed by the Department. Warranty requirements for Class W marking materials are included in MSDSAR manual, List V-4.
701.04 Method of Measurement.
701.05 Basis of Payment.
703.01 Description.
This Section shall cover the work of placing permanent or temporary traffic control markings and legends at the locations shown on the plans or where directed by the Engineer. Preformed thermoplastic markings may be used for permanent striping, and for other circumstances as designated by the Engineer. This Section shall also cover the removal of existing or temporary traffic control markings and legends.
703.02 Materials.
703.03 Construction Requirements.
703.04 Method of Measurement.
The area of Traffic Control Markings or Legends (Items 703-A, 703-B, 703-H, and 703-I) complete in place and accepted will be the sum of the areas shown on the plans for each marking and legend constructed within the required placement tolerance. The Removal of Traffic Control Markings or Legends (Item 703-C) shall be measured in the same manner as prescribed above except that it shall cover only the area from which the markings were actually removed. The area of Temporary Traffic Control Markings or Legends, (Items 703-D and 703-E) complete in place and accepted, will be the sum of the areas shown on the plans for each marking and legend constructed within the required placement tolerance. No measurement for payment will be made for the removal of temporary markings or legends, the removal of such being classified as incidental to the Items of Temporary Traffic Control Markings and Temporary Traffic Control Legends.
703.05 Basis of Payment.
TRAFFIC STRIPE in other states
Get an email when 701 changes
Alabama revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.