5 48 TEMPORARY STRUCTURES
48-1 General
48-1.01 General
48-1.01A Summary
Section 48 -1 includes general specifi cations for constructi ng temporary structures . If a railroad company is involved, f alsework, temporary supports, and jacking support systems must comply with any additional requirements of the railroad company. Section 11 does not apply to temporary structures.
48-1.01B Definitions
frame: Portion of a bridge between expansion joints. jacking: Positioning of new or existing structure s or portions thereof , by jacks or other mechanical methods. previously welded splice: Splice made in a temporary -structure member in compliance with AWS D1.1 or other recognized welding standard , before contract award. temporary -structure adjustment : Grading or adjusting of te mporary structures.
48-1.01C Submittals
48-1.01C(1) General
Submit 6 copies of shop drawings and 2 copies of calculations for:
48-1.01C(2) Temporary -Structure Inspection Report
Temporary -structure inspection report s must be:
48-1.01C(3) Adjustment Plan Shop Drawings
Submi t adjustment plan shop drawings if the falsework or temporary supports are to be adjusted more than 1/2 inch. The adjustment plan shop drawings and calculations must be sealed and signed by the temporary - structure engineer. Adjustment plan shop drawings and calculations must include:
48-1.01D Quality Assurance
48-1.01D(1) General
Reserved
48-1.01D(2) Temporary -Structure Engineer
The temporary -structure engineer must :
48-1.02 Materials
Not Used
48-1.03 Construction
Not Used
48-1.04 Payment
Full compensation for work specified in section 48 is included in the payment for the bid items involved unless:
48-2 Falsework
48-2.01 General
48-2.01A Summary
SECTION 48 TEMPORARY STRUCTURES You must design, construct, and maintain falsework that:
48-2.01B Definitions
independent support system: Support sys tem that is in addition to a falsework removal system that employ s methods of holding falsework from above by winches, hydraulic jacks with prestressing steel, HS steel rods, or cranes. falsework release: Lowering of falsework to the point that it no longe r supports the loads imposed by the permanent structure, or any element, that the falsework was designed to support during construction. Falsework release includes blowing sand from sand jacks, turning screws on screw jacks, and removing wedges. falsework removal: Releasing, lowering, and disposing of the falsework.
48-2.01C Submittals
48-2.01C(1) General
Submit a certificate of compliance for each delivery of structural composite lumber used in falsework. Submit a certificate of compliance for the timber used to construct falsework. The certificate of compliance must verify the grade and species of the timber. Submit a letter of certification that certifies all components of manufactured assemblies are used in compliance with the manufacturer's inst ructions. If requested, (1) submit manufacturer's data for manufactured assemblies to verify manufacturer's instructions or (2) perform tests demonstrating adequacy of the proposed assemblies. Submit field acceptance criteria for falsework piles with a cal culated nominal resistance greater than 200 tons. Base acceptance criteria on a wave equation analysis performed on dynamic monitoring of falsework pile driving. Analyses must be sealed and signed by an engineer who is registered as a civil engineer in the State. Submit acceptance criteria before falsework erection is complete. Submit a letter of certification for all falsework members with welded splices. The letter must certify that all welding and NDT, including visual inspection, comply with the Contrac t and the welding standard shown on the shop drawings. The letter must be sealed and signed by an engineer who is registered as a civil engineer in the State. Submit the letter before placing any concrete on the falsework being certified. Submit a welding certification for falsework members with previously welded splices. The certification must:
48-2.01C(2) Shop Drawings
Submit shop drawings and calculations for falsework. The falsework shop drawings and calculations must be sealed and signed by the tem porary -structure engineer for any of the following conditions:
48-2.01D Quality Assurance
48-2.01D(1) General
Reserved SECTION 48 TEMPORARY STRUCTURES
48-2.01D(2) Welding and Nondestructive Testing
Except for previously welded splices, welding must comply with AWS D1 .1. Welding of bar reinforcement must comply with AWS D1.4. Perform NDT on welded splices using UT or RT. Each weld and any repair made to a previously welded splice must be tested. You must select locations for testing. The length of a splice weld where N DT is to be performed must be a cumulative weld length equal to 25 percent of the original splice weld length. The cover pass must be ground smooth at test locations. Acceptance criteria must comply with the specifications for cyclically loaded nontubular connections subject to tensile stress in clause 8 of AWS D1.1. If repairs are required in a portion of the weld, perform additional NDT on the repaired sections. The NDT method chosen must be used for an entire splice evaluation, including any repairs. For previously welded splices, perform and document all necessary testing and inspection required to certify the ability of the falsework members to sustain the design stresses.
48-2.01D(3) Falsework Lighting
After the installation of falsework lighting, mea sure the illumination levels in the presence of the Engineer , during the hours of darkness . For pavement and pedestrian walkway lighting, the measurements must be taken at g round level with the meter sensor pointing upward. For portal lighting , measurement s must be taken at the face of the surface areas specified with the meter sensor perpendicular to the surface areas. Falsework lighting must comply wit h the illumination levels shown in the following table: Illumination Levels Illumination Area Average Illuminance (fc) (E avg) Uniformity (E avg/Emin) Pavement 0.6 4.0 Portal 1.0 4.0 Pedestrian Walkway 2.0 4.0
48-2.02 Materials
48-2.02A General
Wood must comply with the N DS. Timber used for falsework construction must be seasoned with moisture content not to exceed 19 percent .
48-2.02B Design Criteria
48-2.02B(1) General
Design falsework to resist the sum of the dead and live vertical loads and an assumed horizontal load. Anticipated falsework settlement must not exceed 1 inch. Design footings to carry the imposed loads without exceeding estimated soil bearing values or anticipated settlements. Falsework spans for T -beam girders must not exceed 14 feet plus 8.5 times the T -beam girder depth. Design falsework supporting deck slabs and overhangs on girder bridges such that there is no differential settlement between the girders and the deck forms during deck concrete placement. For individual steel towers with maximum leg loads exceeding 30 kips, design foundations to provide unifor m settlement under all legs of each tower. Design support systems for form panels supporting concrete deck slabs and overhangs on girder bridges as falsework. Temporary bracing must be designed to withstand all imposed loads during erection, construction, and removal of any falsework. Wind loads must be included in the design of the bracing. Falsework removal systems employing methods of holding falsework from above, and members of the independent support system, must support the sum of the actual vertical and horizontal loads due to falsework materials, equipment, construction sequence or other causes, and wind loading. Identifiable mechanical devices used in the falsework removal plan must comply with applicable industry standards SECTION 48 TEMPORARY STRUCTURES and manufacturer instruct ions for safe load carrying capacity. Unidentifiable winches must be capable of carrying twice the design load. The load used for the analysis of overturning moment and sliding of the winch system must be 150 percent of the design load. Where falsework for multiple level bridges is supported on the deck of a structure:
48-2.02B(2) Loads
The design load for falsework must consist of dead and live vertical loads, and an assumed horizontal load. The minimum total design load for any falsework for combined live and dead load is 100 psf, including members that support walkwa ys. Dead loads must include the weight of concrete, reinforcing steel, forms, and falsework. Loads due to concrete, reinforcing steel, and forms must be assumed to be at least:
48-2.02B(3) Stresses, Loadings, and Deflections
48-2.02B(3)(a) General
Maximum allowable stresses and loadings specified in section 48 -2.02B(3) are based on the use of undamaged high -quality materials. Reduce stresses and loadings for materials of lesser quality. Deflection due to reinforced concrete loading only must not exceed 1/240 of the span length.
48-2.02B(3)(b) Timber
Design stres ses for timber and timber connections must not exceed stresses specified in the current NDS. Adjustment factors used to determine allowable stresses for timber members and connections must comply with NDS for the appropriate condition of use and species. Pile design load for timber piles must not exceed 45 tons. SECTION 48 TEMPORARY STRUCTURES
48-2.02B(3)(c) Steel
Except for flexural compressive stresses, the design load for identified grades of steel must not exceed the allowable strength specified in the AISC Steel Construction Manual . Except for flexural compressive stresses, the design load for unidentified steel must not exceed the allowable strength specified for steel complying with ASTM A36/A36M in the AISC Steel Construction Manual or as shown in the following table: Quality characteristic Requirement Tension, axial and flexural (psi) 22,000 Compression, axial (psi) 16,000 -0.38( L/r)2 a Shear on gross section of web of rolled shapes (psi) 14,500 Web yielding for rolled shapes (psi) 27,000 Modulus of elasticity (E) (psi) 30 x 106 NOTES: L = unsupported length, inches r = radius of gyration of the member, inches aL/r must not exceed 120 . Design stresses and deflections for all grades of steel must not exceed the requirements shown in the following table: Quality characteristic Requirement Compression, flexural (psi) 12,000,000 /[(L x d)/(b x t)]a Modulus of elasticity (E) (psi) 30 x 106 NOTES: L = unsupported length, inches d = least dimension of rectangular columns or the width of a square of equivalent cross -sectional area for round columns, or the depth of beams, inches b = width of the compression flange, inches t = thickness of the compression flange, inches Fy = specifie d minimum yield stress in psi aNot to exceed (1) 22,000 psi for unidentified steel, (2) 22,000 psi for steel complying with ASTM A36/A36M, or (3) 0.6 Fy for other identified steel .
48-2.02B(3)(d) Manufactured Assemblies
Do not exceed the manufacturer's instructions for loadings and deflections on jacks, brackets, columns, joists, and other manufactured devices except the dead load deflection of joists at locations other than under deck slabs between girders must not exceed 1/240 of their s pans.
48-2.02B(4) Special Locations
Design and construct falsework over or adjacent to roadways or railroads that are open to traffic such that the falsework is stable if subjected to impact by vehicles. Falsework posts at the following locations are cons idered adjacent to roadways or railroads:
48-2.02C Falsework Lighting
48-2.02C(1) General
A falsework luminaire must:
48-2.02C(2) Pavement Illumination
Reserved
48-2.02C(3) Portal Illumination
Portal illumination include s plywood clearance guides 4 feet wide by 8 feet high and luminaires.
48-2.02C(4) Pedestrian Walkway Illumination
Reserved
48-2.03 Construction
48-2.03A General
Install temporary bracing as necessary to withstand all imposed loads during erection, construction, and removal of any falsework. The materials used in the falsework construction must be of the quality necessary to sustain the stresses required by the falsework design. During concrete placement , if (1) events occur that the Engine er determines will result in a structure that does not comply with the structure as described or (2) settlement variance is greater than 3/8 -inch from the values shown on shop drawings, stop concrete placement and apply corrective measures. If the SECTION 48 TEMPORARY STRUCTURES measures are not provided before initial concrete set occurs, stop concrete placement at the location ordered. Detour traffic from the lanes over which falsework is being erected, released, adjusted, or removed.
48-2.03B Found ations
Construct falsework on solid footings capable of supporting falsework loads. Protect footings from softening and undermining. The Engineer determines if you must verify that the design soil bearing values do not exceed the soil capacity using load t esting. You may place falsework foundation pads and piles before shop drawings are authorized. Falsework piles must be driven and assessed under section 49. The actual nominal driving resistance must be at least twice the falsework pile design load. For pi le acceptance, the required number of hammer blows in the last foot of driving is determined using the formula in 49 -2.01A(4)(c).
48-2.03C Erection
Construct falsework to support the loads imposed without settlement or take -up beyond that shown on the falsework drawings. Install the final bracing system before placing falsework members above stringers. Falsework erection includes adjustments or removal of components that contribute to the horizontal stability of the falsework system. If falsework is over o r adjacent to roadways or railroads, all details of the falsework system that contribute to horizontal stability and resistance to impact, except for bolts in bracing, must (1) be installed when each element of the falsework is erected and (2) remain in pl ace until the falsework is removed. If ordered, use camber strips to compensate for falsework deflection, vertical alignment, and anticipated structure deflection. The Engineer furnishes the amount of camber to be used in constructing falsework. Install te ll-tales that (1) are attached to the soffit forms and (2) can be read from the ground. Provide sufficient tell -tales to allow the total settlement where concrete is being placed to be determined. Construct deck slab forms between girders with no allowance for settlement relative to the girders. Do not apply dead loads other than forms and reinforcing steel to falsework until authorized.
48-2.03D Removal
Release and r emove falsework such that portions of falsework to be removed remain stable. Falsework rel ease includes blowing sand from sand jacks, turning screws on screw jacks, and removing wedges. Except for concrete above the deck, do not release falsework supporting any span of a:
48-2.03E Falsework Lighting
48-2.03E(1) General
Notify the Engineer at least 5 business days before the installation of the falsework lighting . Fasten power cables to the supporting structure at a minimum 3 -foot intervals and within 12 inches from every box. Encase cables within 8 feet of the ground in a minimum 1/2-inch Type 1 conduit. Enclose splices in junction boxes. Provide power for the falsework lighting under section 87 -20. Energize lighting circuits immediately after supporting structure s have been erected . SECTION 48 TEMPORARY STRUCTURES
48-2.03E(2) Pavement Illumination
Provide pavement illumination on roadways beneath falsework structure s. Install luminaires:
48-2.03E(3) Portal Illumination
Provide portal illumination on the side s facing traffic. Install luminaires and clearance guides immediately after falsework vertical members are erected. Fasten clearance guides:
48-2.03E(4) Pedestrian Walkway Illumination
Provide pedestrian walkway illumination immediately after the protective overhead covering is erected. Install the luminaires a minimum 8 feet clea rance in the protective overhead covering and center them over the pedestrian walk way. Space the luminaires through the pedestrian walkway as needed to comply with the illumination levels table. Install luminaires at the ends no more than 7 feet inside the pedestrian walkway openings. Measure the illumination levels at a minimum two points, one on each side within one-quarter of the walkway width from the edge. Use this pattern to start the measurements at both ends of the falsework and then at 10-foot intervals through the length of the pedestrian walkway.
48-2.04 Payment
Not Used
48-3 Temporary Supports
48-3.01 General
48-3.01A Summary
Section 48 -3 includes specifications for providing temporary supports for structures during retrofit, reconstruction, erection, and removal activities. Jacking assemblies, accessories, and activities required to jack and support structures must comply with section 48 -5. SECTION 48 TEMPORARY STRUCTURES Falsework must comply with section 48 -2.
48-3.01B Definitions
Reserved
48-3.01C Submittal s
48-3.01C(1) General
Submit 2 copies of the initial location survey of the existing structure sealed and signed by an engineer who is registered as a civil engineer in the State. Submit a copy of the displacement monitoring record after completing the work.
48-3.01C(2) Shop Drawings
Submit the following:
48-3.01D Quality Assurance
48-3.01D(1) General
Welding, welder qualification, and welding inspection for temporary supports must comply with AWS D1.1.
48-3.01D(2) Quality Control
Reserved
48-3.02 Materials
48-3.02A General
Manufactured assemblies must comply with section 48 -2.02B(3)(d).
48-3.02B Design Criteria
The Engineer does not authorize temporary support designs based on allowable stresses or design load greater than those specified in section 48 -2.02B(3). If falsework loads are imposed on temporary supports, the temporary supports must also satisfy the deflection criteria in section 48 -2.02B(3). The temporary support system must support the initial jacking loads and the minimum temporary support design loads and forces shown. As a minimum, the horizontal load to be resisted in any direction by the temporary support system must be (1) the sum of actual horizontal loads due to equipment, construction SECTION 48 TEMPORARY STRUCTURES sequence, or other causes plus an allowance for wind and (2) not less than 10 percent of the total supported dead load at the location being considered. Adjust vertical design loads for the weight of the temporary supports and jacking system, construction equipment loads, and additional loads imposed by jacking acti vities. Construction equipment loads must be at least 20 psf of deck surface area of the frame involved. For column repair or removal, the temporary supports must resist the described lateral design forces applied at the point where the column to be remove d meets the superstructure. Stiffness of temporary supports must match the described minimum stiffness. If the temporary support stiffness exceeds the described minimum stiffness, increase the lateral design forces to be compatible with the temporary suppo rt lateral stiffness. Place temporary supports , that are resisting transverse lateral loads , within 1/2 of the span length from the existing bent. Place temporary supports , that are resisting longitudinal lateral loads , within the frame where columns are t o be removed. You may use the permanent piles as part of the temporary support foundation. Do not move or adjust permanent piles from the locations shown. If you install permanent piles longer than described to support the temporary supports above the top of the footing and later cut off the piles at their final elevation, you must use shear devices adequate to transfer all pile reactions into the footing. Design temporary support footings to carry the loads imposed without exceeding the estimated soil bearing values or anticipated settlements. You must determine soil bearing values. Where temporary supports are placed on the deck of an existing structure:
48-3.03 Construction
Where described, install temporary crash cushion modules under section 12 -3.22 before sta rting temporary support activities. Remove crash cushion modules when authorized. SECTION 48 TEMPORARY STRUCTURES Construct and remove temporary supports under the specifications for falsework in section 48 -2.03. If traffic is carried on the structure on temporary supports, do not releas e temporary supports until the supported concrete has attained 100 percent of the described strength. Remove attachments from the existing structure. Restore concrete surfaces to original conditions except where permanent alterations are shown.
48-3.04 Pa Yment
Payment for crash cushion modules is not included in the payment for temporary support.
48-4 Temporary Decking
48-4.01 General
48-4.01A Summary
Section 48 -4 includes specifications for temporary decking for joint or deck reconstruction. Temporary decking must consist of a steel plate system that spans the incomplete work. Concrete anchorage devices and nonskid surface must comply with section 75 -3.
48-4.01B Definitions
Reserved
48-4.01C Submittals
Submit shop drawings and calculations for temporary decking. Shop drawings and calculations for temporary decking must be sealed and signed by an engineer who is registered as a civil engineer in the State. Temporary decking shop drawings and calculations must include:
48-4.01D Quality Assurance
Reserved
48-4.02 Mate Rials
48-4.02A General
Yield strength of s teel plate must be greater than or equal to 36 ksi . Bolts must comply with ASTM F3125, Grade A325. Nuts must comply with ASTM A563/563M. Material for temporary tapers must be rapid setting concrete or polyester co ncrete comply ing with section
60-3.02B(2) or 60 -3.04B(2).
48-4.02B Design Criteria
If temporary decking is not shown, the temporary decking design must : SECTION 48 TEMPORARY STRUCTURES
48-4.03 Construction
For bolted connections, drill the holes without damaging the adjacent concrete. Do not damage existing reinforcement. If the temporary decking does not extend the entire width of the roadway, taper the sides of the temporary decking at a 12:1 (horizontal: vertical) ratio. Cure temporary tapers at least 3 hours before allowing traffic on the temporary decking. If unanticipated displacements, cracking, or other damage occurs to the e xisting structure or to any new components installed in or adjacent to the deck, stop work on the deck and perform corrective measures. Edges of steel plate systems must be in full contact with the existing deck and the adjacent approach slab. If used, shi ms must be securely attached to the plate. Do not allow traffic on deck concrete until it has attained the compressive strength shown. When temporary decking is no longer needed, immediately remove temporary decking materials and connections from the exist ing structure. Patch holes with rapid setting concrete complying with section
60-3.02 Remove modifications to the existing structure except where permanent alterations are shown.
48-4.04 Payment
Not Used
48-5 Jacking
48-5.01 General
48-5.01A Summary
Section 48 -5 includes specifications for jacking the bridge superstructure using a jacking support system.
48-5.01B Definitions
Reserved
48-5.01C Submittals
The submittal for shop drawings and calculations must include :
48-5.01D Quality Assurance
48-5.01D(1) General
Calibrate each jack within 6 months of use and afte r each repair. Each jack and its gauge must (1) be calibrated as a unit with the cylinder extension in the approximate position that it will be at the final jacking force and (2) accompanied by a certified calibration chart. Each load cell must be calibrat ed. Calibration must be performed by an authorized laboratory.
48-5.01D(2) Displacement Monitoring
Perform an initial survey to record the location of the structure before starting work. Monitor and record vertical and horizontal displacements of the jack ing support system and the structure. Use vandal - resistant displacement monitoring equipment. Perform monitoring continuously during jacking activities. Make monitoring records available at the job site during normal work hours. Monitoring records must be sealed and signed by an engineer who is registered as a civil engineer in the State. As a minimum, monitor the structure at the supported or jacking locations and at the midspan of both adjoining spans. Locate control points at each location near the cente r and at both edges of the superstructure. As a minimum, record elevations at the following times:
48-5.02 Materials
48-5.02A General
Reserved
48-5.02B Design Criteria
The jacking support system must resist the structure dead load and lateral design forces shown, plus an y additional loads from jacking equipment and activities. As a minimum, the horizontal load to be resisted in any direction for the jacking support system and temporary bracing must be (1) the sum of actual horizontal loads due to equipment, construction s equence, or other causes plus an allowance for wind as specified in section 48 -2.02B(2) and (2) not less than 10 percent of the total dead load of the structure being jacked. If the jacking support system lateral stiffness exceeds the described minimum sti ffness, increase the lateral design forces to be compatible with the jacking support system lateral stiffness. Systems involving modifications to the bridge that impair the structural integrity, intended serviceability, or design capacity of the bridge are not allowed. SECTION 48 TEMPORARY STRUCTURES
48-5.03 Construction
Equip each jack with a pressure gauge or load cell for determining the jacking force. Each pressure gauge must have an accurately reading dial at least 6 inches in diameter. Each load cell must be provided with an indica tor to determine the jacking force. Provide a redundant system of supports to ensure stability of the jacking system during jacking activities. Stop jacking activities if unanticipated displacements, cracking, or other damage occurs. Corrective measures mu st be authorized and implemented before resuming jacking activities. Before starting jacking activities at a location being supported, the jacking support system must (1) apply a force to the structure that is equal to the initial jacking load or the dead load shown and (2) hold that load until all initial compression and settlement of the system is completed. During jacking activities, apply loads simultaneously. Control and monitor jacking operations to prevent distortion and stresses that would damage th e structure. Maintain total vertical displacements at control points to less than 1/4 inch from elevations recorded before jacking or as authorized. Jack the superstructure uniformly to the position described. Distribute the load uniformly across each hinge, abutment, bent , or span . If authorized, place galvanized shims as necessary to provide uniform loading at bearing pads. After reconstruction activities, the monitored control points must not deviate by more than 1/4 inch from the initial vertical survey elevations or other authorized elevations. Remove attachments required for jacking from the superstructure and apply the described finish to concrete surfaces .
48-5.04 Payment
Not Used
48-6 Temporary Wood Poles
48-6.01 General
48-6.01A Summary
Section 48-6 includes specifications for constructing, maintaining, and removing temporary wood poles for the support of electrical systems. Temporary wood poles include attached wire components.
48-6.01B Definitions
Reserved
48-6.01C Submittals
48-6.01C(1) General
Submit a letter of certification that certifies all components of the manufactured assemblies are used in compliance with the manufacturer's recommendations. If requested, (1) submit manufacturer's data for manufactured assemblies to v erify manufacturer's recommendations or (2) perform tests demonstrating adequacy of the proposed assemblies and submit the test results. Submit the letter before installing messenger wires, tether wires, or self -supporting conductors or cables. You may sub mit a request to use alternative mounting brackets or wire termination hardware. Your request must include:
48-6.01C(2) Guy Wire Anchors
Submit the guy wire anchor manufacturer's product information and installation instructions. Do not install anchors u nless authorized.
48-6.01D Quality Assurance
48-6.01D(1) General
A temporary -structure engineer is not required.
48-6.01D(2) Welding
Welding must comply with AWS D1.1.
48-6.02 Materials
48-6.02A General
Wire used for messenger wires, tether wires, or guy wires must be 7 -wire strand complying with ASTM A475, Utilities Grade. Connection hardware for wires must provide a termination efficiency factor of not less than 0.80. Wood poles, push braces, and stubs must comply with ANSI O5.1. Treat wood under AWP A U1, Use Category UC4B, Commodity Specification D. Except for wire, helical anchors, expanded steel plate anchors, cross plate anchors, and expanding rock anchors, steel components must comply with section 56 -3.
48-6.02B Helical Anchors, Expanded Steel Plate Anchors, Cross Plate Anchors, and Expanding
Rock Anchors Fabricate helical anchors, expanded steel plate anchors, and cross plate anchors under section 75. Fabricate attachable thimble eyes and expanding rock anchors from suitable ferrous mater ial. Fabricate as a continuous piece or as separate segments with mechanical connections between segments. Include integral thimble eye or include attachable thimble eye. Galvanize all helical anchor parts under section 75. Paint expanded steel plate ancho rs, cross plate anchors, and expanding rock anchors as specified for repairing damaged galvanized surfaces in section 75 -1.02B. The final assembly must have (1) a minimum ultimate tensile strength greater than the minimum required breaking strength of the guy wire and (2) a minimum ultimate torsional strength greater than twice the minimum installation torque.
48-6.02C Reuse of Materials and Relocation of Temporary Supports
You may reuse structural components and relocate temporary supports provided that t he materials remain in acceptable condition for reuse, except do not reuse:
48-6.03 Construction
48-6.03A General
Install construction bracing as necessary to withstand all imposed loads during erection, construction, and removal of any temporary wood poles. Install a temporary barr ier system at temporary wood pole locations that are less than 15 feet from the edge of a traffic lane. Install temporary barrier system before erecting temporary wood poles. Do not remove temporary barrier system until authorized. SECTION 48 TEMPORARY STRUCTURES For overhead line constr uction not specifically covered in the contract documents, comply with Public Utility Commission General Order 95.
48-6.03B Foundations
Verify the design soil parameters before starting construction of temporary wood poles. Remove any accumulated water fr om the pole excavation prior to placing granular backfill at the bottom of the pole excavation. Thoroughly compact and level the granular backfill at the bottom of the pole excavation prior to setting the pole. Backfill around poles with manufactured sand that is free of rocks or other deleterious material. Place the backfill material in 4 -inch-thick layers. Moisten and thoroughly compact each layer. Remove accumulated water from the anchor excavation prior to placing an expanded steel anchor. Expand the ba se of the expanded steel anchor prior to placing backfill. Place backfill around the expanded steel anchor in 4 -inch thick layers. Thoroughly compact each layer. Protect foundations from softening and undermining.
48-6.03C Erection
If temporary wood poles are over or adjacent to roadways or railroads, all construction bracing must (1) be installed at the time each element of the temporary wood pole is erected and (2) remain in place until the temporary wood pole is removed. Suspend conductors from messenger wire by continuous lashing wire. No spare wire conductors or cables are allowed unless described. Sag overhead bundles to maintain required clearances over the ambient temperature range from -30 to 120 degrees F. The sag must be between 4.6 and 5 .4 percent of horizontal span unless otherwise shown. Minimum vertical clearance over grade is 25 feet unless otherwise shown.
48-6.03D Attachments
If specific connection details are not shown, mount attachments under the manufacturer's written instructio ns and such that there is no loss of cross section.
48-6.03E Damping
If at any time during service the temporary structural support exhibits excessive vibration, immediately install dampers. Dampers must be effective in mitigating the vibration and must n ot compromise the structural supports or the supported hardware.
48-6.03F Removal
Remove temporary structural supports such that portions not yet removed remain stable at all times. Remove temporary wood poles and helical anchors. Fill the void with excav ated material or sand that is free of deleterious material. Place the backfill material in 4 -inch-thick layers. Moisten and thoroughly compact each layer. Dispose of surplus excavated material uniformly along the adjacent roadway. Dispose of temporary stru ctural support materials and work debris.
48-6.03G Guy Wire Helical Anchors
48-6.03G(1) General
Reserved
48-6.03G(2) Installation Parameters
Use the minimum installation torque shown. You may request an alternative minimum installation torque based on a revised value for empirical torque factor. For alternative minimum installation torque, use the following equation to calculate the installation torque: T = Qa(FS/Kt) SECTION 48 TEMPORARY STRUCTURES where: T = Minimum installation torque, ft -lb FS = Factor of safety of 2.0 Qa = Minimum allowable tensile capacity shown, lb Kt = Empirical torque factor, 1/ft (inverse foot) Include a geotechnical report sealed and signed by a licensed geotechnical engineer with recommended values for empirical torque factor and alternative minimum install ation torque with your request. Do not start installation unless your alternative installation parameters are authorized. Verify the installation parameters before the start of anchor installation.
48-6.03G(3) Installation
Install anchors under the manufacturer's written instructions and the following:
48-6.03G(4) Removal
After service is complete, remove anchors using reverse torque. Fill the void with excavated material or sand free of deleterious materials. Place the backfill material in 4 -inch-thick layers. Moisten and thoroughly compact each layer.
48-6.03H Expanded Steel Plate Anchors, Cross Plate Anchors, and Expanding Rock Anchors
48-6.03H(1) General
Reserved
48-6.03H(2) Installation
Install anchors under the manufacturer's written instructions. Locate and mark all substructures and utilities. Do not install anchors underneath subsurface utilities or structures.
48-6.03H(3) Removal
After service is complete, remove anchors to a depth of at least 3 feet below finished grade. Fill the void with sand free of deleterious materials. Place the backfi ll material in 4 -inch-thick layers. Moisten and thoroughly compact each layer.
48-6.04 Payment
Not Used