610Median Cover Material

CO · 2023 Standard Specifications✓ Full text on BuildSpecBook pages 635–636 Save this section

Ask about Section 610

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

Median Cover Material

Description

610.01This work consists of the construction of median cover over the median area, or over

other areas designated, per these specifications and in conformity with the lines and grades shown on the plans or established.

Materials

610.02Bituminous median cover material shall conform to the requirements of Section 403

and as shown on the plans. Concrete shall be Class B and shall conform to Section 601. Coloring agent, if required, shall be as shown on the plans or specified.

Aggregate for median cover shall conform to the requirements of subsection 703.10.

Plastic sheeting shall be black polyethylene with a minimum thickness of 10 mils or approved equal.

Herbicides shall conform to the requirements of Section 217.

Construction Requirements

610.03Median cover operations shall not be started until the underlying surface has been

compacted, smoothed and, if required, treated with herbicides. Other requirements are as follows: (a)Bituminous Median Cover Material. Bituminous median cover material shall be placed in conformance with the requirements of subsection 608.04(c).

(b)Concrete. Construction requirements shall conform to the requirements of subsection

608.03. The surface finish or pattern shall be as shown on the plans or per the recommendations

of the supplier of the median cover material.

(c)Stone. Areas to receive stone median cover shall be treated, if required, with an approved

herbicide treatment per Section 217 or as directed. Immediately after the placement of the herbicides, the plastic sheeting and stones shall be placed per details shown on the plans, or as specified.

Method of Measurement

610.04Bituminous median cover material will be measured by the number of tons of

bituminous material placed and accepted. Concrete median cover material will be measured by the square foot of surface placed and accepted.

Stone median cover material will be measured by the number of tons of aggregate placed and accepted.

610.05

Basis of Payment

610.05The accepted quantities will be paid for at the contract unit price for each of the

pay items listed below that appear in the bid schedule. Payment will be made under:

Pay Item Pay Unit Median Cover Material (Bituminous) Ton Median Cover Material (Concrete) Square Foot Median Cover Material (Patterned Concrete) Square Foot Median Cover Material (Stone) Ton

Herbicide treatment will be measured and paid for per Section 217.

Subgrade compaction and plastic sheeting will not be measured and paid for separately but shall be included in the work.

611.01

Get an email when 610 changes

Colorado revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Colorado Standard Specifications for Road and Bridge Construction, 2023 Edition. Pages 635–636 of 943. View official source ↗

Ask about this section