PROFILED THERMOPLASTIC PAVEMENT MARKINGS
701-1 Description.
Profiled thermoplastic pavement markings consist of thermoplastic material with raised thermoplastic bumps creating a raised profile marking. Apply profiled thermoplastic pavement markings in accordance with the Contract Documents.
701-2 Materials.
Use only materials listed on the Department’s Approved Product List ( APL) as an approved system and meeting the following requirements : Profiled Thermoplastic ................................ ............ 971-1 and 971 -9 Retroreflective Elements* ................................ ..................... 971-1.7 Glass Spheres* ................................ ........................ 971-1 and 971 -2 *Use retroreflective elements or glass spheres recommended by the manufacturer . The Engineer will take random samples of the materials in accordance with the Department’s Samplin g, Testing and Reporting Guide schedule.
701-3 Equipment.
Use equipment capable of providing continuous, uniform heating of the pavement marking material to temperatures exceeding 390ºF, mixing and agitating the material in the reservoir to provide a homo genous mixture without segregation. Use equipment that will maintain the pavement marking material in a plastic state, in all mixing and conveying parts, including the line dispensing device until applied. Use equipment which is capable of producing a consistent pattern of bumps with a longitudinal distance between bumps of approximately 30 inches center -to-center intervals. Use equipment which meets the following requirements:
701-4 Application.
701-4.1 General: Remove existing thermoplastic pavement markings and raised bumps
using a method approved by the Engineer such that pavement surface scars or traces of the FY 2023-24 Return to Table of Contents removed thermoplastic pavement markings will not conflict with new pavement markings. Do not use paint to blackout, hide, or disguise existing pavement markings . Before applying pavement markings, remove any material that would adversely affect the bond of the pavement markings by a method approved by the Engineer. Before applying pavement markings to any portland cement concrete surface, apply a primer, sealer o r surface preparation adhesive of the type recommended by the manufacturer. Offset longitudinal lines at least 2 inches from construction joints of portland cement concrete pavement. Apply pavement markings to dry surfaces only, and when the ambient air and surface temperature is at least 50°F and rising for asphalt surfaces and 60°F and rising for concrete surfaces . Apply pavement markings to the same tolerances in dimensions and in alignment specified in 710 -5. When applying pavement marking over exis ting markings, ensure that no more than 2 inches on either end and not more than 1 inch on either side of the existing line is visible. Conduct field tests in accordance with FM 5-541. Take test readings representative of the pavement marking performance. Remove and replace pavement markings not meeting the requirements of this Section at no additional cost to the Department.
701-4.2 Thickness: Apply flat base lines having a thickn ess of 0.100 inches or 100 mils
to 0.150 inches or 150 mils , exclusive of the bumps, when measured above the pavement surface. Measure, record and certify on a Department approved form and submit to the Engineer, the thickness of white and yellow pavemen t markings in accordance with FM 5-541. The Engineer will verify the thickness of the pavement markings in accordance with FM 5-541 within 30 days of receipt of the Contractor’s certification.
701-4.3 Dimensions of Raised Bumps: Apply the raised bumps with a profile such that
the leading and trailing edges are sloped at a sufficient angle to create an audible and vibratory warning. Bumps on edge line and centerline markings shall be at least 0.45 inches at the highest point of t he bump, above the pavement surface, including the base line. The height shall be measured after application of drop -on retroreflective elements or glass spheres. Bumps shall have a minimum baseline coverage dimension of 2.5 inches in both transverse and l ongitudinal directions. The bumps may have a drainage channel, the width of each drainage channel will not exceed 1/4 inch at the bottom of the channel. The longitudinal distance between bumps shall be approximately 30 inches.
701-4.4 Retroreflectivity: Apply white and yellow profiled thermoplastic markings that
will attain an initial retroreflectance of not less than 300 mcd/lx·m2 and not less than 250 mcd/lxm2, respectively. Measure, record and certify on a Department approved form and submit to the Eng ineer, the retroreflectivity of white and yellow pavement markings in accordance with FM 5-541.
701-4.5 Color: Use pavement marking materials that meet the requirements of 971 -1.
701-4.6 Retroreflective Elements or Glass Spheres : Apply retroreflective elements or
glass spheres to all markings at the rates determined by the manufacturer’s recommendations as identified for the APL System.
701-4.7 Loss: If more than 1% of the bumps or more than three consecutive bumps are
missing or broken (les s than half a bump remaining) with in the first 45 days under traffic, FY 2023-24 Return to Table of Contents replace all failed bumps at no expense to the Department. If more than 2% of the bumps fail within the first 45 days under traffic, the replacement peri od will extend an additional 45 days from the date all replacement bumps were installed. If, at the end of the additional 45 days, more the 2% of all bumps (initial and replacement) fail, replace all failed bumps at no expense to the Department . Measure, record and certify on a Department approved form and submit to the Engineer, the loss of bumps.
701-5 Contractor’s Responsibility for Notification.
Notify the Engineer prior to the placement of the materials. At the time of notification, submit a certification to the Engineer with the APL number and the batch or LOT numbers of the thermoplastic materials and retroreflective elements or glass spheres to be used. Packaging labels that contain the information required by 971 -1.1 will be accepted in lieu of a certification.
701-6 Protection of Newly Applied Profiled Thermoplastic Markings.
Do not allow traffic onto or permit vehicles to cross newly applied pavement markings until they are sufficiently dry. Remove and replace any portion of the pavement markings damaged by passing traffic or from any other cause, at no additional cost to the Department.
701-7 Observation Period.
Longitudinal pavement markings , with the exception of bumps, are subject to a 180 day observation period under normal traffic. The observation period will begin with the satisfactory completion and acceptance of the work. The observation period for bumps will be in accordance with the require ments of 701 -4.7. The longitudinal pavement markings shall show no signs of failure due to blistering, excessive cracking, chipping, discoloration, poor adhesion to the pavement, loss of retroreflectivity or vehicular damage. The retroreflectivity shall m eet the initial requirements of
701-4.4 The Department reserves the right to check the retroreflectivity anytime prior to the end
of the observation period. Replace, at no expense to the Department, any longitudinal pavement markings that do not perform satisfactorily under traffic during the 180 day observation period.
701-8 Corrections for Deficiencies .
Correct all deficiencies by removal and reapplication of a one-mile section centered around the deficiency , at no cost to the Department.
701-9 Method of Measurement.
701-9.1 Profiled Thermoplastic Markings: The quantities of 6 inch solid and 10’-30’
skip lines to be paid will be the plan quantity length , in gross miles, subject to 9 -1.3.2. The gross mile measurement will be taken as the distance from the beginning of the profiled thermoplastic line to the end of the profiled thermoplastic line and will include the unmarked gaps for skip lines. The gross mile will not include designated unmarked lengths at intersections, turn lanes, etc.
701-9.2 Removal of Existing Thermoplastic Markings: The quantity to be paid for
removal of existing thermoplastic pavement markings will be the area, in square feet, acceptably removed. Payment for removal of thermoplastic pavement markings will only be ma de for locations where the existing pavement surface is to remain . FY 2023-24 Return to Table of Contents
701-10 Basis of Payment.
Price and payment will be full compensation for all work specified in this Section, including, all cleaning and preparing of surfaces, furnishing of all materials, application, curing and protection of all items, protection of traffic, furnishing of all tools, machines and equipment, and all incidentals necessary to complete the work. Final payment will be withheld until all deficiencies are corrected. Payment will be made under: Item No. 701 Profiled Thermoplastic Pavement Markings. Solid - per gross mile Skip - per gross mile Remove - per square foot FY 2023-24 Return to Table of Contents SECTION 704 TUBULAR MARKERS
704-1 Description.
Furnish and install tubular markers at the locations called for in the Standard Plans or in the Plans.
704-2 Materials.
Meet the following requirements: Durable Tubular Markers ................................ ....Section 991 Standard Tubular Markers ................................ ..Section 991
704-2.1 Product Acceptance on the Project: Use tubular markers listed on the
Department’s Approved Product List (APL).
704-3 Installation Requirements.
Install tubular markers in accordance with the manufa cturer’s installation instructions posted on the APL. Use the same color as the pavement marking being emphasized .
704-4 Method of Measurement.
The quantity to be paid will be the plan quantity of the number of tubular markers furnished, installed, and ac cepted.
704-5 Basis of Payment.
Prices and payments will be full compensation for work specified in this Section, including the cost of labor, materials, and incidental items required to complete the work. Payment will be made under: Item No. 704 - 1 Tubular Marker - each. FY 2023-24 Return to Table of Contents