649Concrete Glare Screen

GA · 2021 Standard Specifications✓ Full text on BuildSpecBook pages 1199–1200 Save this section

Ask about Section 649

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

649.1 General Description

This work includes erecting a Portland cement concrete glare screen according to plan dimensions on top of a concrete median barrier.

649.1.01 Definitions

General Provisions 101 through 150.

649.1.02 Related References

A. Standard Specifications Section 621—Concrete Barrier B. Referenced Documents General Provisions 101 through 150.

649.1.03 Submittals

General Provisions 101 through 150.

649.2 Materials

Use materials that comply with Section 621 and the plan details.

649.2.01 Delivery, Storage, and Handling

General Provisions 101 through 150.

649.3 Construction Requirements

649.3.01 Personnel

General Provisions 101 through 150.

649.3.02 Equipment

General Provisions 101 through 150.

649.3.03 Preparation

General Provisions 101 through 150.

649.3.04 Fabrication

General Provisions 101 through 150.

649.3.05 Construction

Construct the glare screen using one of the following alternatives: A. Alternative One Cast the median barrier and while the concrete is still plastic, insert “D” bars into the fresh concrete as indicated on the Plans. Wait until the median barrier concrete has reached a compressive strength of 2000 psi (14 MPa) or an age of seven days. Then place a second course of barrier, of the dimensions shown on the plans, on top of the first course and finish and cure according to Subsections 621.3.05.C and 621.3.05.D. B. Alternative Two As an alternative to inserting “D” bars into the plastic concrete, wait until the median barrier concrete has reached a compressive strength of 2,000 psi (14 MPa), then drill holes for the “D” bars and epoxy them in place. Construct the second course of barrier on top of the first course according to plan dimensions. Finish and cure according to Subsections 621.3.05.C and 621.3.05.D.

649.3.06 Quality Acceptance

General Provisions 101 through 150.

649.3.07 Contractor Warranty and Maintenance

General Provisions 101 through 150.

649.4 Measurement

Concrete glare screen is measured for payment in linear feet (meters) of accepted work of each specified height. The surface is measured along the top of the glare screen.

649.4.01 Limits

General Provisions 101 through 150.

649.5 Payment

This work will be paid for at the Contract Unit Price per linear foot (meter) for each specified height. Payment will be full compensation for furnishing materials and performing the work. Payment will be made under: Item No. 649 Concrete glare screen (height) Per linear foot (meter)

649.5.01 Adjustments

General Provisions 101 through 150.

Referenced in this section

Get an email when 649 changes

Georgia revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for Construction of Transportation Systems, 2021 Edition. Pages 1199–1200 of 2,050. View official source ↗

Ask about this section

Scoped to Georgia 2021 Standard Specifications, Section 649 — Concrete Glare Screen. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.