B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Libraries
Estimate & calculate
CalculatorsChecklists
PricingLog in
Division 600 — Incidental Construction

685Blast Cleaning Portland Cement Concrete Structures

GA · 2021 Standard Specifications✓ Full text on BuildSpecBook pages 1312–1314 Save this section

Ask about Section 685

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

685.1 General Description

This work includes blast cleaning Portland cement concrete surfaces and removing blasting residue from roadway and shoulder surfaces.

685.1.01 Definitions

General Provisions 101 through 150.

685.1.02 Related References

A. Standard Specifications Section 109—Measurement and Payment B. Related Documents General Provisions 101 through 150.

685.1.03 Submittals

General Provisions 101 through 150.

685.2 Materials

General Provisions 101 through 150.

685.2.01 Delivery, Storage, and Handling

General Provisions 101 through 150.

685.3 Construction Requirements

685.3.01 Personnel

General Provisions 101 through 150.

685.3.02 Equipment

Maintain and use the following equipment for this work so as not to threaten anyone’s safety or health. • Blasting/cleaning equipment • Supporting traffic control devices, such as arrow boards, signs, barricades, cones, etc., according to the Traffic Control Section of the Contract and the MUTCD A. Environmental Protection Provide blasting equipment with either of the following environmental protections: • An enclosure to keep dust from escaping into the surrounding area • Water spraying equipment that encircles the blast nozzle(s) to suppress the dust created by the blasting operation B. Protective Devices Provide and have personnel use eye and hearing protection devices when working near the blasting operation. Also, provide personnel with respirators (with appropriate filters) or with forced air hoods when working in dust- contaminated areas.

685.3.03 Preparation

General Provisions 101 through 150.

685.3.04 Fabrication

General Provisions 101 through 150.

685.3.05 Construction

A. Blast Cleaning Methods Use any of the following blast cleaning methods: • Dry abrasive blasting with compressed air, blast nozzles, and abrasive • Recirculating dry abrasive blasting with compressed air, blast nozzles, abrasive, and a recovery system • Dry abrasive blasting with centrifugal wheels and abrasive • Recirculating dry abrasive blasting with centrifugal wheels, abrasive, and a recovery system • Wet abrasive blasting with compressed air, blast nozzles, abrasive, and a water injection system B. Blast Cleaning Operation Follow these requirements for blast cleaning operations: 1. When using compressed air in the blasting operation, provide and maintain traps to prevent contaminating the blasted substrate with oil or grease. 2. When blast cleaning within 10 ft. (3 m) of a lane occupied by traffic, immediately remove the residue to prevent a traffic hazard. 3. Control dust to the Engineer’s satisfaction to protect motorists from reduced visibility or damage to passing vehicles. The Engineer judges dust control effectiveness. If the Engineer believes that the blasting makes the highway unsafe, stop operations until instituting effective dust control measures. C. Appearance of the Blasted Surface Blast the surface uniformly, leaving only minute quantities of existing coating remaining in pit surface imperfections. The remaining existing coating may be no more than one percent of the blast-cleaned surface in each square yard (meter). Match the structure’s finished appearance to the standard photographs. Copies of these can be found in the District Office, the Office of Materials and Research, or the Office of Maintenance.

685.3.06 Quality Acceptance

All work performed under this specification is subject to timely inspection by the Department. Correct defective work by re-blasting at no additional cost to the Department.

685.3.07 Contractor Warranty and Maintenance

General Provisions 101 through 150.

685.4 Measurement

Blast cleaning of the Portland cement concrete structures is measured by the square foot (meter), according to Section 109. Median barrier walls are measured by the linear mile (kilometer) for variable height. Each face of the blast- cleaned wall is measured separately.

685.4.01 Limits

General Provisions 101 through 150.

685.5 Payment

Blast cleaning will be paid for at the Contract Unit Price bid. Payment is full compensation for costs, direct and indirect, incurred in complying with the requirements of this specification. Payment will be made under: Item No. 685 Blast cleaning Portland cement concrete structures Per square yard (meter) Item No. 685 Blast cleaning Portland cement concrete median barriers—variable height Per linear mile (kilometer)

685.5.01 Adjustments

General Provisions 101 through 150.

Referenced in this section

Get an email when 685 changes

Georgia revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for Construction of Transportation Systems, 2021 Edition. Pages 1312–1314 of 2,050. View official source ↗

Ask about this section

Scoped to Georgia 2021 Standard Specifications, Section 685 — Blast Cleaning Portland Cement Concrete Structures. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.