719.1 General Description

This specification provides the requirements for furnishing and installing a silt filter bag to trap dissolved silt when pumping accumulated water from sediment basins or other areas where water may accumulate.

719.1.01 Definitions

General Provisions 101 through 150.

719.1.02 Related References

A. Standard Specifications General Provisions 101 through 150. B. Referenced Documents ASTM D 3776 ASTM D 4632 ASTM D 4833 ASTM D 4491 ASTM D 3786 ASTM D 4991 ASTM D 4355 ASTM D 4751 ASTM D 4884

719.1.03 Submittals

General Provisions 101 through 150.

719.2 Materials

Ensure that all materials meet the requirements of the following: A. Fabric The silt filter bag fabric shall be a non-woven geotextile conforming to the following properties: Property Minimum Value Test Method Weight 10 oz./yd2 (340 g/m2) ASTM D 3776 Tensile strength (minimum average of 5 specimens) 270 lb. (1100 N) ASTM D 4632 Puncture Resistance, 150 lb. (730 N) ASTM D 4833 Initial Flowrate 70 gal/min-ft.2 (3500 L/min- m2) ASTM D 4491 Bursting Strength 550 psi (3800 kPa) ASTM D 3786 Permitivity 1.3 sec-1 ASTM D 4991 UV Stability, 70% of initial Tensile Strength 173 lb. (770 N) ASTM D 4355 AOS Retained 100% ASTM D 4751 B. Seams All seams shall be sewn with a double needle machine using a high strength thread. The seams shall have a minimum average wide-width strength of 100 lb./in (17.5 N/mm) when tested according to ASTM D 4884. C. Opening Provide a silt filter bag with an opening to accommodate a 6 in. (150 mm) hose.

719.2.01 Delivery, Storage, and Handling

General Provisions 101 through 150.

719.3 Construction Requirements

719.3.01 Personnel

General Provisions 101 through 150.

719.3.02 Equipment

General Provisions 101 through 150.

719.3.03 Preparation

General Provisions 101 through 150.

719.3.04 Fabrication

General Provisions 101 through 150.

719.3.05 Construction

1. Place the silt filter bag on a #57 stone gravel bed sloped to ensure that the filtered water will exit at the desired location. Chose the exit location to prevent erosion. 2. Extend the pump hose past the inlet opening to ensure that the silt-laden water will discharge in the center of the bag. Ensure that the seal between the inlet and hose is watertight. 3. When the filter bag is full of silt and cannot readily pass any more water, use a new filter bag. If approved by the Engineer, bury the full filter bag on site or remove the top section of fabric and seed the exposed filtrate. The size and number of silt filter bags will be shown on the plans or determined by the Engineer.

719.3.06 Quality Acceptance

General Provisions 101 through 150.

719.3.07 Contractor Warranty and Maintenance

Continue water filtration as directed by the Engineer.

719.4 Measurement

Silt filter bags measured for payment will be the actual number of bags used for filtration, complete and accepted.

719.4.01 Limits

General Provisions 101 through 150.

719.5 Payment

Payment will be made under: Item No. 719. Silt filter bag Per each

719.5.01 Adjustments

General Provisions 101 through 150.

Get an email when 719 changes

Georgia revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for Construction of Transportation Systems, 2021 Edition. Pages 1412–1414 of 2,050. View official source ↗

Ask about this section

Scoped to Georgia 2021 Standard Specifications, Section 719 — Silt Filter Bag. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.