Division 21 — Earthwork, Subgrades, and Subbases

2105Stripping, Salvaging, and Spreading Topsoil

IA · 2023 Standard Specifications✓ Full text on BuildSpecBook pages 195–197 Save this section

Ask about Section 2105

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

2105.01

DESCRIPTION.

A.

Strip topsoil and prepare sod.

B.

Haul, deposit, and spread topsoil.

Stripping, Salvaging, and Spreading Topsoil

2105.04

2105.02MATERIALS

For topsoil furnished by the Contractor, provide material meeting the requirements of Articles 4170.09, A, 1 and 4170.09, A, 3, or strip existing topsoil from beneath template fill sections within the project limits if stripping of that topsoil is not already included as part of the project. Replace topsoil stripped from beneath template fill with an equivalent quantity of Class 10 or Embankment-in-Place material at no additional cost to the Contracting Authority.

2105.03CONSTRUCTION

Remove topsoil from borrow pits, cuts, or areas to be covered by embankments. Prepare sod. Haul, deposit, and spread topsoil on shoulders, slopes, excavated areas, borrow pits, and other designated areas according to the contract documents. A.

B.

Stripping Topsoil. Remove topsoil from borrows, cuts, or areas to be covered by embankments. 1.

Sod Preparation. Mow, or remove, weeds, grass and growing crops or other herbaceous vegetation close to the ground as directed by the Engineer. Shred sod by shallow plowing or blading and thoroughly disking. Shred sod thoroughly enough to permit the soil to be easily spread in a thin layer over areas to be covered.

2.

Topsoil Excavation. After existing sod has been prepared, remove the topsoil to the depth specified. If not otherwise specified, the depth shall be 12 inches. The topsoil may be moved directly to an area where it will be used or may be stockpiled for future use.

Placing Topsoil. Haul, deposit, and spread topsoil uniformly on shoulders, slopes, excavated areas, borrows, and other designated areas according to the contract documents to a minimum depth of 4 inches or to the depth specified in the contract documents. Smooth the surface of the topsoil and leave in a finished condition so that it will drain properly.

2105.04 A.

METHOD OF MEASUREMENT. Topsoil Stripped Onsite. 1.

The number of cubic yards of topsoil moved will be computed on the basis of a uniform 12 inch cut, or the depth as specified in the contract documents, over the area involved. Sufficient field measurements will be taken to assure reasonable conformity with the required depth of cut.

2.

Topsoil salvaged from excavated areas and paid for as topsoil will not be included in excavation quantities for which payment is made.

B.Topsoil Furnished by Contractor or Previously Stockpiled Onsite.

The number of cubic yards of topsoil will be computed on the basis of a uniform 8 inch placement, or the depth as specified in the contract

2106.03

Settlement Plates

documents, over the area involved. Sufficient field measurements will be taken to assure reasonable conformity with the required depth of placement. 2105.05

BASIS OF PAYMENT.

A.

Payment will be the contract unit price per cubic yard.

B.

Payment is full compensation for preparing, stripping (if required), transporting, and placing the topsoil according to the contract documents.

Get an email when 2105 changes

Iowa revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Iowa Standard Specifications for Highway and Bridge Construction, 2023 Edition. Pages 195–197 of 1,288. View official source ↗

Ask about this section