Division 21 — Earthwork, Subgrades, and Subbases

2113Subgrade Stabilization Material

IA · 2023 Standard SpecificationsBook pages 222223View official source ↗

2113.01DESCRIPTION

Place material to stabilize the subgrade under the pavement at locations specified in the contract documents.

2113.02MATERIALS

The type of subgrade stabilization material required will be specified in the contract documents. Use material that meets the requirements of Article 4196.01, B, 5. 2113.03 A.

CONSTRUCTION. Placement. Place the subgrade stabilization material as shown in the contract documents (typically on subgrade with a specified backfill material placed on top). Overlap subgrade stabilization material sections a minimum of 2 feet during placement operations. Place backfill material so the material remains in place or is not damaged.

2115.03

B.

Modified Subbase

Repair. In the event of subgrade stabilization material failure or damage during construction: 1.

Remove the damaged portion of material.

2.

Replace the damaged portion with a patch of new material of the same type extending a minimum of 6 feet in all directions beyond the edge of the failed area.

3.

Replace the backfill material.

2113.04METHOD OF MEASUREMENT

Subgrade Stabilization Material of the type specified, in square yards, will be the quantity shown on the contract documents to the nearest square foot. 2113.05

BASIS OF PAYMENT.

A.

Payment for the type of Subgrade Stabilization Material specified will be the contract unit price per square yard.

B.

Payment is full compensation for all work, materials, equipment, and labor necessary to furnish, install, place, repair and maintain the subgrade stabilization material.

Source: Iowa Standard Specifications for Highway and Bridge Construction, 2023 Edition. Pages 222223 of 1,288.

Ask about this section

Scoped to Iowa Standard Specifications for Highway and Bridge Construction, Section 2113 — Subgrade Stabilization Material. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.

Iowa DOT Standard Specifications for Highway and Bridge Construction Section 2113 Subgrade Stabilization Material — Full Text | BuildSpec