Division 21 — Earthwork, Subgrades, and Subbases

2126Reclaiming Present Surfacing Material

IA · 2023 Standard Specifications✓ Full text on BuildSpecBook pages 243–244 Save this section

Ask about Section 2126

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

2126.01DESCRIPTION

Scarify, windrow, load, stockpile, rehaul, and deposit granular material found on the present road surface. 2126.02 None.

MATERIALS.

2126.03

CONSTRUCTION.

A.

Blade loose surfacing material from the shoulders to the central area of the roadway.

B.

Scarify the old road surface to be reclaimed to a width and depth that will yield suitable surfacing material. The Engineer will determine what material is suitable for reclaiming. Pulverize the loosened material to the extent that 100% of the particles will pass a 3 inch sieve.

Reconstruction of Roadbed

2127.03

C.

Haul and deposit reclaimed material in stockpiles and spread uniformly over the length of the project, or haul and spread the reclaimed material on specified sections of the project after grading is completed.

D.

At the Contractor's option and without extra payment, the Contractor may substitute special backfill material, meeting requirements of Section 4132, for reclaimed surfacing in treatment areas. Obtain the Engineer's approval for scarification and disposition of the surfacing material.

E.

Reclaim surfacing material prior to installation of crossroad culvert pipe or grading operations. After surfacing material has been removed, satisfactorily blade and shape the roadway for local traffic.

2126.04METHOD OF MEASUREMENT

Measurement for Reclaiming Present Surfacing Material will be in cubic yards in the transporting vehicle, and according to Article 2312.04, A. If such measurement is impractical, measurement may be made by the Engineer of the stockpile by the cross section method or by other feasible methods. 2126.05

BASIS OF PAYMENT.

A.

Payment for Reclaiming Present Surface Material will be the contract unit price per cubic yard.

B.

Payment is full compensation for reclaiming present surfacing material, scarifying, blading, loading, hauling, stockpiling, and spreading the reclaimed material as directed by the Engineer.

Get an email when 2126 changes

Iowa revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Iowa Standard Specifications for Highway and Bridge Construction, 2023 Edition. Pages 243–244 of 1,288. View official source ↗

Ask about this section

Scoped to Iowa Standard Specifications for Highway and Bridge Construction, Section 2126 — Reclaiming Present Surfacing Material. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.