Division 22 — Base Courses

2203Hot Mix Asphalt Base

IA · 2023 Standard Specifications✓ Full text on BuildSpecBook pages 250–250 Save this section

Ask about Section 2203

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

2203.01DESCRIPTION

Construct an HMA base, as specified, upon a prepared or corrected subgrade or a previously constructed base or subbase.

2203.02MATERIALS

Apply Article 2303.02.

2203.03CONSTRUCTION

Construct HMA base to the dimensions shown in the contract documents and according to Section 2303.

2203.04METHOD OF MEASUREMENT

Measurement for the various items involved in the construction of a HMA base will be according to Article 2303.04.

2203.05BASIS OF PAYMENT

Payment for the various items involved in the construction of a HMA base will be as provided in Article 2303.05.

Referenced in this section

Get an email when 2203 changes

Iowa revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Iowa Standard Specifications for Highway and Bridge Construction, 2023 Edition. Pages 250–250 of 1,288. View official source ↗

Ask about this section

Scoped to Iowa Standard Specifications for Highway and Bridge Construction, Section 2203 — Hot Mix Asphalt Base. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.