2520.01DESCRIPTION
Furnish and maintain field office space or laboratory space, or both, to be used for project testing of: • Earthwork where moisture control or moisture density control is required, • Subbase, base, and pavement, and • Any other designated use. 2520.02 None.
MATERIALS.
2520.03
FIELD LABORATORY AND FIELD OFFICE.
A.
Field Laboratory. 1.
General. Meet the following requirements. Items a through h are meant as a guide rather than minimum requirements. The Engineer may approve suitable alternative facilities.
dimensions of 7 feet by 18 feet with 7 feet of head room.
emergency.
ventilation.
space.
shaker (template furnished upon request).
set level and stable for minimum vibration. The laboratory space may be independent or dependent on other space, but is for the exclusive use of the Contracting Authority.
placed.
exhaust fan.
between 70°F and 80°F.
wirelessly, such as a mobile hotspot. Provide a minimum of 10 GB of data usage monthly. This device will be considered a part of the field laboratory and shall stay with the field laboratory. If the field laboratory and field office are located adjacent to each other, one device may be adequate to cover both, so long as the signal can be accessed from both trailers. The Contracting Authority will pay data charges for usage above the monthly minimum.
Field Laboratory and Field Office
o.
2.
2520.03
Suitable sanitary facilities located within 75 feet of the laboratory for use by the inspection forces.
Furnishing Field Laboratory. A field laboratory will be required as follows:
1) Field laboratories will be required for acceptance testing when specified on the proposal. The items for which the field laboratory is intended will be designated. If base and pavement are of similar types which require similar plant and testing facilities, only one field laboratory will be shown on the proposal for both items. 2) Furnish the field laboratory before all work is started. Keep the field laboratory on the project at all times regardless of work being performed or testing required. Duplicate field laboratories may be required when the plant facilities are duplicated or dispersed so that plant operation of base or pavement work cannot be monitored from one field laboratory. 3) Relocate laboratories used to control asphalt binder or Portland cement proportioning as the plant facilities are relocated. Field laboratories used primarily to test densities of base, subbase, or earthwork may be required to be relocated once for each 4 miles or fraction thereof in the length of the project.
1) Materials will be inspected at the project site if prior inspection has not been made, and a materials laboratory may be required for this purpose. If inspection prior to shipment to the project site is necessary, in the opinion of the Engineer, or agreeable to the Engineer and Contractor, furnish inspection facilities near the location for inspection. 2) Inspection facilities will be necessary at the site of production or warehousing of: • Pipe, • Cement, • Asphalt, • Structural steel and other metal items, • Precast concrete, • Aggregates, • Other materials requiring or utilizing approved warehousing, and • Proportioning and mixing plants for concrete and bituminous mixtures at permanent facilities. 3) Ensure inspection facilities are suitable for the use intended, including testing space or office space for record keeping, or both. Facilities may vary from designated or separate space in a shared building for occasional inspection, to a materials laboratory (defined below) for continuous and full time use. 4) Material laboratories will be required for any inspection for individual or combinations of projects involving more than:
2520.03
Field Laboratory and Field Office
•
5)
6)
B.
5000 tons of aggregate from an individual source for use in pavement, base, or subbase, or • 10,000 tons of aggregate for other purposes. Ensure laboratories are located close to production operations. For facilities furnished jointly, ensure the laboratory is within a driving distance of 5 miles from each source. For the materials laboratory, furnish facilities similar to those specified in Article 2520.03, A, 2, a. Equip the laboratory for testing the type of material to be produced according to an equipment listing available upon request. The Engineer may modify parts of this specification to allow for: • Facilities furnished prior to first use of this specification, • Small amounts of material to be furnished from widely separated sources, or • Unusual testing procedures.
Field Office. 1.
General. Meet the following requirements. Items a through i are meant as a guide rather than minimum requirements. The Engineer may approve suitable alternative facilities.
Contractor and for the exclusive use by the Contracting Authority.
Engineer.
nominal area of 192 square feet of floor space.
square feet.
the Engineer.
drafting stool, a water cooler dispenser, a floor broom, and a 10 pound rated capacity carbon dioxide fire extinguisher.
storage.
temperature between 70°F to 80°F.
fixtures in the office to provide a minimum of 70 foot-candles of light on all working surfaces.
to access the internet wirelessly, such as a mobile hotspot. Provide a minimum of 3 GB of data usage per month. This device will be considered a part of the field office and shall stay with the field office. If the field laboratory and field office are located adjacent to each other, one device may be adequate to cover both, so long as the signal can be accessed from both trailers.
Certified Plant Inspection
2521.02
the inspection forces.
not less than five vehicles at the field office for the use of the inspection forces. 2.
C.
Furnishing Field Office.
this contract, maintain the building in a satisfactory state of repair and supply all heating fuel, electricity, and drinking water. The Contractor is responsible for paying all installation charges. The Contracting Authority will pay data charges for usage above the monthly minimum.
Limitations. Contractor's maintenance of these facilities does not include normal housekeeping.
2520.04METHOD OF MEASUREMENT
The Engineer will count the Field Laboratories or Field Offices, or both, furnished according to this specification, as required by the contract documents. Field laboratories furnished for materials inspection will not be counted for payment. 2520.05
BASIS OF PAYMENT.
A.
Payment for each Field Laboratory or Field Office, or both, will be the contract unit price.
B.
Payment is full compensation for furnishing, moving, and maintaining the field laboratory or field office, or both, and for furnishing the utilities and sanitary facilities.