2547Temporary Stream Access

IA · 2023 Standard SpecificationsBook pages 948949View official source ↗

2547.01DESCRIPTION

This work consists of the construction, use, maintenance and removal of temporary structures used to provide construction access across along or into waters of the United States. Temporary structures are any features not a part of the completed project that are constructed or installed to provide access to the project site including stream crossings, causeways, pads and temporary bridges or barges.

2547.02MATERIALS

Furnish fill materials. Do not obtain from the stream unless specifically allowed elsewhere in the contract documents. 2547.03

CONSTRUCTION.

A.

The type of structure used, if any, is at the Contractor's discretion provided it complies with Article 1107.18. Unless indicated otherwise in the contract documents, the Contracting Authority will obtain approval for temporary stream crossings, constructed according to Standard Road Plan EW-401 or as shown in the contract documents, in the Section 404 permit. Should the Contractor elect to access the waterway using different methods than provided for in the contract documents, the Contractor shall be responsible to obtain a Section 404 permit for temporary stream crossings from the US Army Corps of Engineers.

B.

Unless indicated otherwise in the contract documents, the Contracting Authority will obtain Section 408 approval from the US Army Corps of Engineers and the local sponsor for work on a federal levee, federal control structure, or access to a waterway within a federal levee and the use of a

2548.02

Milled Rumble Strips - HMA or PCC Surface

temporary stream crossing (Standard Road Plan EW–401). Should the Contractor elect to construct the project using different methods than provided for in the contract documents, the Contractor will be responsible to obtain Section 408 approval from the US Army Corps of Engineers and the local sponsor and Section 404 approval from the US Army Corps of Engineers. C.

Ensure temporary structures: Maintain normal downstream flows, do not restrict expected high flows, do not disrupt movement of aquatic life native to the stream or water body, and minimize the potential for flooding. Expected high flows are flows which the Contractor expects to experience during the period of time the crossing is in place.

D.

Maintain temporary structures to prevent unnecessary erosion and other non-point sources of pollution.

E.

Completely remove temporary structures and return affected areas to preconstruction conditions within 30 calendar days of no longer being needed. Revetment that has been removed may be incorporated elsewhere in the project, provided it meets the specification for the intended final use. Remove all other fill material to an upland area. Reshape, stabilize, and revegetate as appropriate all disturbed areas.

2547.04 None.

METHOD OF MEASUREMENT.

2547.05BASIS OF PAYMENT

Temporary Stream Accesses is incidental to Mobilization.

Source: Iowa Standard Specifications for Highway and Bridge Construction, 2023 Edition. Pages 948949 of 1,288.