Division 41 — Construction Materials

4123Modified Subbase Material

IA · 2023 Standard Specifications✓ Full text on BuildSpecBook pages 1089–1090 Save this section

Ask about Section 4123

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

4123.01DESCRIPTION

Aggregate of the following Types: • Crushed stone, • Gravels for which 75% or more of the particles retained on the 3/8 inch sieve have at least one fractured face as defined in Materials I.M. 305, • Recycled pavements meeting Materials I.M. 210, or • Uniformly blended combinations of these materials with a maximum of 50% RAP. • Do not place RAP below high water table. 4123.02

GRADATION.

A.

Meet the requirements for Gradation No. 14 of the Aggregate Gradation Table, Article 4109.02.

B.

Process RAP to pass the 2 inch sieve.

C.

Uncrushed gravel and/or sand may be uniformly blended with crushed recycled pavement or crushed stone at a maximum rate of 50% to meet gradation requirements.

4123.03 A.

QUALITY. The requirements of Table 4123.03-1 apply to virgin materials:

Aggregate for Bituminous Sealcoat

4125.01

Table 4123.03-1: Aggregate Quality Aggregate Quality

Maximum Percent Allowed

Test Method

Abrasion

50

AASHTO T 96

C Freeze

Iowa DOT Materials Laboratory Test Method No. 211, Method C

B.

The requirements of Table 4123.03-1 apply to recycled PCC when the aggregate source is unknown as outlined in Materials I.M. 210.

Get an email when 4123 changes

Iowa revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Iowa Standard Specifications for Highway and Bridge Construction, 2023 Edition. Pages 1089–1090 of 1,288. View official source ↗

Ask about this section

Scoped to Iowa Standard Specifications for Highway and Bridge Construction, Section 4123 — Modified Subbase Material. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.