Before mobilization, submit a plan of operations for CRABS processing, including traffic control.
A.General.
1.Weather Limitations . Construct the CRABS while the existing pavement temperature is above and is exp ected to remain above 40°F for 24 hours after final completion. Do not spread portland cement over puddled water, during rain, w hen rain is imminent, or when wind will not allow uniform spread on the roadway.
2.Operational Restriction. Add cement and process no more of the roadway than can be repaved in 2 days of paving production.
3.Traffic Control. Unless the approved traffic control plan requires traffic to be detoured to an alternate roadway, open the roadway to traffic at the end of each working day by either re- laying the unprocessed pulverized material and compacting firmly or adding cement and processing for a finished product.
4.Grade Control Requirements.
a.On Class I work, establish the final CRABS surface elevation in the field. Finish the CRABS surface to within 0.03 foot of the field -established elevation and provide the field- established or specified cross slope at 12 feet from centerline and at the edge of the CRABS surface. for Highway Construction Page 193 of 71 5 b. On Class II work, obtain a grade book from the Department establishing grade elevations for the top of the CRABS layer. Finish the CRABS surface to within 0.03 foot plus or minus of the elevati ons provided. Do not waste material before approval of the final elevation for either class.
B.Initial Pulv erization.
1.Preparation of Roadbed. Before pulverization, strip and waste any vegetation encountered inside the typical C RABS section.
2.Pulverize Existing Surface. Pulverize the pavement to the widths and dept hs as specified and at a minimum, to the full depth of the existing pavement. Reduce the material to a minus 3- inch size.
a.Document the existing pavement thickness every 0.1 mile in each lane. Submit this documentation to the Department. Ensure that the full thickness of the pavement is being pulverized.
b.Notify the Engineer of any poor quality subbase materials (e.g., soft spots, clays, silts, organic materials) as they are encountered.
c.Shape and compact the pulverized material before the CR ABS mixing process.
d.In superelevated curve sections, shape the material before the application of portland cement .
3.CRABS Process.
a.Proportioning. Furnish portland cement in bulk. Add the cement to the pulverized material using a mechanical spreader at the specified rate within 5 percent for the full width of the typical section. Synchronize the application rate with the machine speed to provide uniform applicati on. Spread the cement in a dry state and do not allow blowing of the cement. After spreading the portland cement, mix the cement with the pulverized material to obtain the required depth and width. Distribute only as much portland cement as can be mixed and compacted within the same working day.
b.Mixing . Use a road mixing machine (pugmill, auger, or cross -shaft mixer ) capable of providing a uniform homogeneous mixture. Introduce the water through the mixing machine using a metering device. Add the correct quantity of water to produce a mixture between 4 and 7 percent by weight of mixed and compacted material. Do not allow water leakage from equipment. Do not add excessive water. Mix the existing pulverized pavement, base, and cement to the full depth as specified. Shape and roll where necessary to allow the roadway to be open to traffic (i.e., approaches to businesses and residencies). More th an 1 pass of the mixer may be required. Introduce water with the final mixing pass. Ensure and document the mixing t hickness every 0.3 mile in each lane.
4.Shaping and Grade Control. Provide continuous grade and cross -slope control including surveying (blue topping or wire line control) depending on CRABS Class. It is expected that the pulverized material will swell 15 to 30 percent before compaction. Use the centerline of the existing roadway as the typical section control line. Construct the cross slope as shown. Adjustments may be required to the existing roadway profile to provide a consistent grade and to avoid adding new material or wasting existing material. If necessary, reestablish the for Highway Construction Page 194 of 715 roadway profile and cross slopes to provide a roadway section that is consistent with the typical section. Obtain approval for transverse grades . For CRABS Class II work, the grades in the Department -provided gradebook may be adjusted to avoid adding new material or wasting existing material upon approval. Use equipment for shaping and setting grade capable of automated (mec hanical or electronic) setting of grade and cross slope angle. Account for swell in the grading operation that may leave the processed surface above the adjacent surface. Incorporate all pulverized material into the CRABS layer. Shape and finish the CRABS surface without adding new material or wasting existing material. Do not waste or use pulverized material as shoulder material. Grade designated shoulder material to a location and elevation on the shoulder that is below the top of the C RABS layer. Do not use cement -treated material for shoulder material. Place windrow material designated for removal adjacent to, but outside the limits of pulverization. Dispose of material following final shaping and before application of cement.
5.Compacting and Finishing. Use a motor grader, mechanical spreader, paver , or grade trimmer to shape the mixture. For the compaction train, include at least 1 rubber -tired roller, 1 vibratory roller, and 1 vibratory pad-foot soil compactor. Use compaction equipment and/or rolling methods to produce the required compaction without damaging the work. The v ibratory soil compactor will have a minimum centrifugal force of 15 tons, minimum drum width of 60 inches, and minimum pad height of 3½ inches. Use the vibratory pad- foot soil compactor after the cement has been mixed. Cover the material with at least 3 complete passes. Additional passes may be required to achieve compaction. Perform all other final process rolling and blading after completion of the vibratory pad foot operation. Establish a roller pattern using in- place density from an uncorrected nuclear gauge. Use the roller pattern as a standard from which t o measure compaction. Compaction is achieved when additional roller passes add no more than 0.5 pound per cubic feet to the previous in- place de nsity. Ensure a “false break” or leveling- off point is not used for compaction density. Reest ablish a new roller pattern when mixture properties change and at least every 7,200 square yards of finished surface. Perform grading and rolling without wasting material. Accomplish all shaping, final process rolling and associated blading within 1½ hours of the initial blending of the cement and water. Do not use vibratory rollers on the CRABS surface bey ond the 1½ hours after the addition of water and cement.
6.Protection. Keep the processed and compacted material visibly moist at all times until the initial lift of plant mix is applied. Use equipment that will apply the water in a fog or mist type appli cation free of pressure on the surface being treated.
7.Paving. Pave over the CRABS as soon as possible following compaction and within 48 hours after the introduction of cement and water to the CRABS. When the approved traffic control plan requires traffic to be detoured to an alternate roadway, the 48-hour paving requirement may be waived provided the CRABS surface is kept sufficiently moist. for Highway Construction Page 195 of 715 Tight -blading and static rolling may be required before applying the initial lift of plant mix due to surface deformation, raveling, or other irregularities created by tr affic. Ensure there is no loose material on the CRABS surface at the time of plant mix paving. After paving, dress the roadway shoulders to provide a uniform appearance.
8.Prime Coat . Immediately before placement of the initial lift of plant mix pavement , apply a prime coat full width at the rate specified or as direc ted. Do not apply a prime coat to the CRABS if standing water is on the surface. Apply the prime coat as specified in 402.