for Highway Construction Page 238 of 715 SECTION 407 – SCRUB COAT
407.01 Description.
Construct a scrub coat on the road surface.
407.02 Materials.
Provide asphalt of the type and grade specified. Provide asphalt and anti -stripping additive as specified in 702, if required. The Engineer will determine acceptability of the asphalt at the point of delivery. Provide aggregate for scrub coat as specified in 703.04. The Contractor does not need to use multiple stockpiles. The E ngineer will determine acceptability of the aggregate from the Contractor -provided sources at the point of delivery and at the crushing plant from designated sources.
407.03 Construction Requirements.
407.04 Method of Measurement.
The Engineer will measure acceptably c ompleted work as follows:
407.05 Basis of Payment .
The Department will pay for accepted quantities at the contract unit prices as follows: for Highway Construction Page 239 of 715 Pay Item Pay Unit ___ Plant Mix Scrub Coat ....................................................................... Ton ___ Aggregate for Road Mix Scrub Coat ................................................ Ton ___ Emulsified Asphalt for Scrub Coat ................................................... Ton ___ Percent Anti -Stripping Additive for Scrub Coat ................................ TOA ___ Plant Mix Scrub Coat , including asphalt and additives .................... Ton The Department will not make separate payment for asphalt and additives for plant mix scrub coat , including asphalt and additives. for Highway Construction Page 240 of 71 5 SECTION 408 – FOG COAT
408.01 Description.
Apply a fog coat and blotter , if required.
408.02 Materials.
Provide fog coat material that is diluted emulsified asphalt . Provide the emulsified asphalt as specified in 702 . Mix approximately equal volumes of emulsified asphalt and water before application. Provide blotter material as specified in 703. The Engineer will determine acceptability of material from the Contractor -provided sources at the point of delivery and at the source from designated sources.
408.03 Construction Requirements.
408.04 Method of Measurement.
The Engineer will measure acceptably completed work as follows:
408.05 Basis of Payment .
The Department will pay for accepted quantities at the contract unit prices as follows: Pay Item Pay Unit Diluted Emulsified Asphalt for Fog Coat ................................................. gal