B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Libraries
Estimate & calculate
CalculatorsChecklists
PricingLog in
General Provisions (00100-00999)

735REMOVE AND RELOCATE OVERHEAD SIGN STRUCTURE OR

IL · 2022 Standard Specifications✓ Full text on BuildSpecBook pages 666–666 Save this section

Ask about Section 735

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

Remove Overhead Sign Structure Art. 736.03

a.Overhead Sign Structure. The complete horizontal superstructure, including walkways when present, shall be removed from the structural steel support(s), and the structural steel support(s) removed from the foundation(s). The overhead sign structure shall then be transported to its new location and erected according to Section 733, using new hardware. When necessary, the overhead sign structure shall be stored according to

Article 505 — 08(c). When new structural steel supports are required, they

shall be constructed according to Section 733 and the details shown on the plans.

b.Ground Mounted Sign Supports. Each support shall be removed from the foundation, transported to its new location, and erected according to Section 727 using new mounting hardware.

735.03 Basis of Payment. This work will be paid for at the contract unit price

per each for REMOVE OVERHEAD SIGN STRUCTURE – SPAN, CANTILEVER, BUTTERFLY, or MONOTUBE; RELOCATE STRUCTURAL STEEL SUPPORT FOR OVERHEAD SIGN STRUCTURE - SPAN, CANTILEVER, BUTTERFLY, or MONOTUBE; RELOCATE OVERHEAD SIGN SUPERSTRUCTURE - SPAN, CANTILEVER, BUTTERFLY, or MONOTUBE; or REMOVE AND RELOCATE GROUND MOUNTED SIGN SUPPORT. When required, new structural steel supports for an overhead sign structure will be paid for according to Article 738.03. SECTION 736. REMOVE OVERHEAD SIGN STRUCTURE

736.01 Description. This work shall consist of removing an overhead sign

structure. CONSTRUCTION REQUIREMENTS

736.02 General. The entire overhead sign structure, including supports,

superstructure, sign panels, sign lighting, and walkway shall be removed from the foundation(s) and removed from the right-of-way. The removed structure shall be disposed of according to the contract. When the contract specifies re-using the existing foundations, the Contractor shall exercise care to not damage the existing anchor bolts that will be re-used to install the new structural steel supports. Methods of removing anchor bolt nuts, such as penetrating fluid, sandblasting, or scoring and cracking the anchor bolt nuts, shall be approved by the Engineer. Under no circumstances will heat be allowed. When grout exists in the void between the existing base plate and the foundation, the grout shall be completely removed down to the top surface of the original foundation.

736.03 Basis of Payment. This work will be paid for at the contract unit price

per each for REMOVE OVERHEAD SIGN STRUCTURE - SPAN, CANTILEVER, BUTTERFLY, MONOTUBE, or BRIDGE MOUNTED.

Get an email when 735 changes

Illinois revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Illinois Standard Specifications for Road and Bridge Construction, 2022 Edition. Pages 666–666 of 1,217. View official source ↗

Ask about this section

Scoped to Illinois Standard Specifications for Road and Bridge Construction, Section 735 — REMOVE AND RELOCATE OVERHEAD SIGN STRUCTURE OR. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.