825LIGHTING CONTROLLER

IL · 2022 Standard Specifications✓ Full text on BuildSpecBook pages 720–721 Save this section

Ask about Section 825

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

Lighting Controller Art. 825.03 CONSTRUCTION REQUIREMENTS

822.03 Installation. Mounting of the luminaire shall be as recommended by

the luminaire manufacturer in such a manner that they clear all obstacles when retrieved for maintenance and relamping.

822.04 Basis of Payment. This work will be paid for at the contract unit price

per each for WATERWAY OBSTRUCTION WARNING LUMINAIRE, LED or AVIATION OBSTRUCTION WARNING LUMINAIRE, LED. CONTROLLERS SECTION 825. LIGHTING CONTROLLER

825.01 Description. This work shall consist of furnishing and installing an

electrical controller.

825.02 Materials. Materials shall be according to the following.

Item Article/Section

a.Portland Cement Concrete (Note 1) ....................................................... 1020
b.Lighting Controller .............................................................................. 1068.01
c.Transformer, General Purpose .......................................................... 1068.02
d.Lightning Protection ........................................................................... 1065.02
e.Fasteners and Hardware ................................................................... 1088.03 Note 1. Class SI concrete shall be used. CONSTRUCTION REQUIREMENTS

825.03 Installation. The lighting controller installation shall be according to

the details, location, and orientation shown on the plans. A 4 in. (100 mm) thick portland cement concrete work pad, not less than 48 x 48 in. (1.2 x 1.2 m) shall be provided in front of the cabinet, except where the cabinet faces an adjacent sidewalk. All conduit entrances into the lighting controller shall be sealed with a pliable waterproof material.

a.Controller Mounted on Concrete Foundation. The Contractor shall confirm the orientation of the lighting controller and its door side, with the Engineer, prior to installing the foundation. A portland cement concrete foundation shall be constructed to the details shown on the plans. The lighting controller enclosure or pedestal shall be set plumb and level on the foundation. It shall be fastened to the anchor rods with hot-dip Art. 825.03 Obstruction Warning Lighting Controller galvanized or stainless steel nuts and washers. Foundation mounted lighting controllers shall be caulked at the base with silicone. Where the controller has a metal bottom plate, the plate shall be sealed with a rodent and dust/moisture barrier.
b.Controller Mounted on Pole. The lighting controller enclosure shall be mounted to the pole as shown on the plans. Aluminum brackets designed for pole mounting shall be used. Enclosures greater than 26 in. (650 mm) in height shall have stiffener plates on both top and bottom of the rear wall for mounting brackets. All mounting hardware shall be stainless steel.
c.Controller Mounted on Wall. The lighting controller enclosure shall be mounted to the wall with stainless steel fasteners as indicated in the plans. Stainless steel mounting brackets designed for wall mounting shall be used.

825.04 Grounding. Grounding shall be according to Section 806.

825.05 Basis of Payment. This work will be paid for at the contract unit price

per each for LIGHTING CONTROLLER, of the enclosure and control type specified. SECTION 826. OBSTRUCTION WARNING LIGHTING CONTROLLER

826.01 Description. This work shall consist of furnishing and installing an

electrical controller for obstruction warning lighting.

826.02 Materials. Materials shall be according to the following.

Item Article/Section

a.Portland Cement Concrete (Note 1) ........................................................ 1020
b.Obstruction Warning Lighting Controller ............................................. 1068.03
c.Transformer, General Purpose ........................................................... 1068.02
d.Lightning Protection ............................................................................ 1065.02 Note 1. Class SI concrete shall be used. CONSTRUCTION REQUIREMENTS

826.03 Installation. Installation shall be according to Article 825.03.

826.04 Grounding. Grounding shall be according to Section 806.

826.05 Basis of Payment. This work will be paid for at the contract unit price

per each for OBSTRUCTION WARNING LIGHTING CONTROLLER, of the enclosure and control type specified.

Get an email when 825 changes

Illinois revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Illinois Standard Specifications for Road and Bridge Construction, 2022 Edition. Pages 720–721 of 1,217. View official source ↗

Ask about this section

Scoped to Illinois Standard Specifications for Road and Bridge Construction, Section 825 — LIGHTING CONTROLLER. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.