Art. 888.03 Temporary Traffic Signal CONSTRUCTION REQUIREMENTS
888.03 Installation. The pedestrian push-button shall be located next to the
curb ramp, sidewalk, or a paved clear space with a minimum size of 2.5 ft x 4.0 ft (760 mm x 1.22 m). The front face of the push-button should be even with the nearest edge of the curb ramp, sidewalk, or clear space but shall in no case be further away than 10 in. (250 mm). The height of the push-button should be 36 in. (900 mm) above the paved surface but shall in no case be less than 30 in. (760 mm) or more than 42 in. (1.05 m). The housing of the push-button shall be completely in contact with the post, pole, or extension arm on which it is mounted. The Contractor shall apply an anti-seize paste compound on all nuts and bolts prior to assembly. The methods of mounting both the pedestrian push-button and the sign shall be approved by the Engineer.
888.04 Basis of Payment. This work will be paid for at the contract unit price
per each for PEDESTRIAN PUSH-BUTTON. MISCELLANEOUS SECTION 890. TEMPORARY TRAFFIC SIGNAL
890.01 Description. This work shall consist of furnishing, installing,
maintaining, and removing a temporary traffic signal installation as shown on the plans. CONSTRUCTION REQUIREMENTS
890.02 Installation. The Contractor shall notify the Engineer at least 48 hours
in advance when the temporary signal installation is ready to be activated. The Engineer will then inspect the installation. After approval by the Department, the maintenance of the temporary signal installation, including all energy charges, shall become the responsibility of the Contractor until removal is directed by the Engineer. After the removal of the temporary installation, the equipment and materials furnished by the Contractor shall remain the property of the Contractor.
890.03 Maintenance. The temporary traffic signal maintenance shall be
according to Article 801.11(b).
890.04 Basis of Payment. This work will be paid for at the contract unit price
per each for TEMPORARY TRAFFIC SIGNAL INSTALLATION. Each intersection will be paid for separately. Following approval of each installation, 60 percent of the bid price will be paid. The remaining 40 percent will be paid following removal of each installation.