1601.1 Description
This specification governs the steel bars for concrete reinforcement that are produced from billet steel.
1601.2 Requirements
a. General.
1601.3 Test Methods
Conduct all tests required by the app licable AASHTO material specification of subsection 1601.2b.
1601.4 Prequalification
Follow the instructions on the AASHTO National Transportation Product Evaluation Program’s (NTPEP) website to participate in the audit program for reinforcing steel mill. Forward an official copy of the initial (and latest) NTPEP audit report, including split sample results, to the Bureau Chief of Construction and Materials for evaluation. Producing mills that have successfully met the requirements of the audit (including test results that comply with subsection 1601.2b.) and are listed on the NTPEP website as compliant will be prequalified. In order to maintain prequalified status, send a copy of the annual NTPEP certificate of compliance as soon as it is received. Producing mills th at have been removed from the NTPE P website listing will be removed from prequalified status. For producing mills that attain “provisional” status on the NTPE P website, immediately forward a description of the failing material (sizes, grade, and heat) to the Bureau Chief of Construction and Materials. Producing mills that fail to provide the annual certificate of compliance or descriptions of failing material associated with a “provisional” NTPEP status, or are no longer in compliance with the audit requirements may be removed from prequalified status.
1601.5 PREQUALIFICATION (Alternate Method)
a. General. Contact the Bureau Chief of Construction and Materials to arrange for the required sampling, observation of testing procedures and review of the plant quality control program. The plant is to absorb all the Engineer’s representa tive expenses associated with the inspection. This includes travel, subsistence and lodging, and the expenses of shipping the selected specimen bars to the KDOT Materials and Research Center for comparison testing. It is the option of the Bureau Chief of Construction and Materials to grant approval status to a plant based upon the qualification test and inspection results of the transportation agencies of other states. A plant will be notified by written documentation in the event of any change in their approval status. The Bureau of Construction and Materials w ill maintain a list of all plants that are prequalified and approved to provide 1601 - STEEL BARS FOR CONCRETE REINFORCEMENT 1600-2 bars to KDOT projects. b. Plant Quality Control Requirements. The plant must have a quality control section identified within its organization that is adequately staffed to perform the re quired lot by lot testing. The plant laboratory must have proper equipment, calibrated according to AASHTO T 67 (ASTM E 4) annua lly as a minimum, with which to adequately perform all testing according to subsection 1601.3. Provide a copy of the plant quality control plan to the Engineer’s representative during the plant inspection. c. Sampling and Testing Procedure. The Engineer’s representative will select the test samples, at random, at the plant. Provide access to all facilities necessary for the Enginee r’s representative to randomly select samples from all lots defined below. Provide plant personnel to cut and label the necessary specimens from the randomly selected bars.
1601.6 Verification
a. Samples. All prequalified plants that are currently pr oviding bars for KDOT projects will have their product quality monitored through the use of verification samples. The Regional Materials Laboratories will randomly select on average 1 verification sample per month from the bars being provided by each prequalified plant for use on KDOT projects. Special arrangements may be considered for plants providing small quantities during the course of a year. These samples are to include all bar grades and sizes that may be available for use on KDOT projects. These samples will be obtained from various shipme nts and at any fabrication, coating, or precast facility, or warehouse selected by the Region al Materials Engineer. On occasion, it will be necessary for the Regional Materials Engineer to notify the District to obtain verification samples at a project. Samples will be submitted to the MRC for testing according to the procedures and requirements of subsection 1601.2b. Reduction in sampling will follow the criteria established in Part V, Appendix A, Multi-level Sampling Frequency Chart, with the following exception: Reduced Frequency Approved by Regional Materials Engineer with Notification to Bureau of Construction and Materials. b. Sample testing. The verification samples are to comply with the minimum requirements of the applicable AASHTO specification of subsection 1601.2b. with the exceptions as noted in the following. It will be permissible for the test results from only one annual verification sample from each prequalified plant to be less than the following: TABLE 1601-2: STEEL BARS VERIFICATION TESTING Property Requirement Unit Weight: 99% of the specified minimum Yield Strength: 95% of the specified minimum Tensile Strength: 95% of the specified minimum Elongation, %: Specified minimum minus 2 Not more than 10% of the annual verification sample s from each prequalified plant will be permitted to have test results less than the applicable specification minimums. Not more than one annual verifica tion sample from each prequalified plant will be permitted to fail the bend test. In the event that the verification samples fail to comply with the proceeding, the Engineer’s representative may resample the failing heat(s) one time only on a 2 to 1 basis or reject the failing heat(s). The Contractor is to re place the rejected heats at no additi onal cost to the KDOT. The initial test results will be replaced by those of the resample specimens. c. Disqualification. Failure of the verification sample bars from a plant to comply with subsection 1601 - STEEL BARS FOR CONCRETE REINFORCEMENT 1600-4 1601.6b. will result in disqualification of the plant and remova l from the prequalified source list. In the event of disqualification, the plant is subject to the prequalification requirements of subsection 1601.5 even if originally prequalified under subsection 1601.4. A plant that fails to comply with subsection 1601.6b. 2 times, consecutive or otherwise, will be permanently disqualified.
1601.7 Basis of Acceptance
a. The plant must be currently prequalified. b. Submit for approval a Type A certification (certified mill test report), as specified in DIVISION 2600, that governs the analysis of all bar steel heats delivered to the project. c. The Engineer’s representative of the project must be provided with shipping orders, an invoice, or cover letter that documents the project number, bar sizes and grades, heat, job, or mill order number(s), and the total weight of each heat of the represented bars delivered to the project. d. The Engineer’s representative of the project must be provided with a document stating that the bars delivered to the project comply with this specification. This documentation must bear the signature and title of an official of the plant with Contract Document binding authority, and must be notarized. This requirement may be included on the certified mill test report referenced in subsection 1601.7b. e. Single or bound groups of bars must be tagged or otherwise marked in a durable manner. At a minimum, this identification must list the bar manufacturer’s corporat e identification and plant loca tion, the heat number, and job or mill order number. Display a copy of the plant’s un ique mill marking character set that identifies the bar on the tag. f. The final disposition of the bars will be completed at the final destination as the result of inspection for the quality of workmanship and the delivery condition.
Steel Bars for Concrete Reinforcement in other states