1618 - STEEL PLATE GUARDRAIL 1600-29
1618.1 Description
This specification governs corrugated sheet steel beam s and related components utilized in the construction of highway guardrail systems.
1618.2 Requirements
a. General. The guardrail system design, dimensions, method of corrosion protection, end terminals, and specific fabrication requirements are specified in the Contract Documents. Property requirements for the steels and components are governed by the classifications, designations, or grades of steel, and the component specifications designated on the Contract Documents and subsection 1618.2b. Proprietary energy dissipating end terminal system s may be supplied only if prequalified by the KDOT. For threaded fastener components, comply with the thread series requirements of ANSI/ASME B1.1 Coarse Thread Series, with a tolerance class that accommodates the corrosion protective coating when applicable. Provide corrosion protecti on for all steel components utilized in gu ardrail systems by a nonmagnetic metal coating. Non-coated copper bearing weathering steel is not an acceptable alternative. Store guardrail components to prevent water retention and condensation, intimate contact between individual components, and contact with the soil. b. Material Specifications.
Division 2300
1618.3 Test Methods
Conduct all tests required by the applicable AASHTO, ASTM, or other component or material specifications of subsection 1618.2. Coating thickness may be measured by any one of the methods specified in ASTM B 633 and by eddy current methods, ASTM B 244, provided that appropriate calibration procedures and standards have been applied. The magnetic induction and eddy current methods are nondestructive in nature and are preferred. Destructive techniques, i.e., coating removal, may be utilized as referee methods. 1618 - STEEL PLATE GUARDRAIL 1600-30
1618.4 Prequalification
a. All guardrail system components provided by th e manufacturer of the b eam, except for proprietary energy dissipating end terminal systems, must be prequalified before approval for installation on KDOT projects. The prequalification procedure is to be in accordance w ith AASHTO M 180, section 5.3, "Acceptance by Brand Registration and Guarantee." Submit the information required by section 5.3 to the Bureau Chief, Construction and Materials, for evaluation. For components not specifically addressed by section 5.3, provide the information relevant to the component that is required by subsection 1618.2. Include all FHWA notif ications of acceptance relevant to the components or system. b. Proprietary energy dissipating end terminal systems must be prequalified as a unit. The prequalification procedure requires that complete evaluation data, including design and test information and materials list, and the FHWA notification of acceptance, be submitted to the Bureau of Road Design. c. All manufacturers will be notified of their prequa lification status upon evaluation of the submitted information. When granted approval, the manufacturer, components, and or system will be placed on a listing of prequalified manufacturers and providers of guardrail system components and or energy dissipating end terminal systems. The list will be maintained by the Bureau of Construction and Materials.
1618.5 Basis of Acceptance
a. Receipt and approval of a Type C certification as specified in DIVISION 2600 for all components governed by subsection 1618.2b.(1), (3), (4), (5), and (7) . This supersedes the certification requirements of the specific SECTIONS 1607, 1608, and 1619. b. Submit for approval a Type A certification as specified in DIVISION 2600 for all threaded fastener components, subsection 1618.2b(2), , and required by SECTION 1616. c. The disposition of wood components, e.g., posts, blocks, etc., subsection 1618.2b.(6), is to be in accordance with the applicable subsection of DIVISION 2300. d. The KDOT reserves the right to request and test sp ecimens from certified component lots to verify the certification results or when there is reason to suspect their validity. e. Inspection and testing by field personnel of all steel components for compliance with dimensional requirements and corrosion protection coating thickness. Coating thickness will measured according to any of the procedures of subsection 1618.3. f. The final disposition of all components will be comp leted at the final destination as the result of inspection for the quality of workmanship and the delivery condition.